EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 930
activities
in C01 Construction OCI
× clear
Code
Activity
Start
Finish
Flt
%
EK000CK065
Compl. Layout of Temp. Facil. (including OCI)
29-Jan-25
01-Oct-25
—
100%
EK000CK075
Review Tech & Commercial Proposal - Field Fab Tank
16-Feb-25
02-Oct-25
—
100%
EK000CK060
Locate tie in pnts for temp water, phone, & pwr
26-Feb-25
16-Mar-25
—
100%
EK000CK100
Site Visit - Construction
26-Feb-25
16-Mar-25
—
100%
EK000CK005
OCI Subcontract - Executed
19-Mar-25
19-Nov-25
—
100%
EK000CK010
OCI Meeting to Define custom clearance requests
20-May-25
19-Jun-25
—
100%
EK000CK015
Define OCI's Point of Delivery & Liability
20-May-25
19-Jun-25
—
100%
EK000CV038
Select Geotech Vendor / Issue Award
20-May-25
17-Aug-25
—
100%
EK000CV039
Geotech Conducts Soil Borings / Draft Prelim Report
24-Aug-25
17-Dec-25
—
100%
CO000GE105
Commence Admin. Building Design (OCI)
05-Oct-25
05-Oct-25
—
100%
CO000K0106
Mobilize Temporary Facilities (& Punchlist & Perm. Power)
09-Nov-25
27-Dec-26
—
40%
EK000GE150
Execute OCI Subcontract (KBR)
16-Nov-25
16-Nov-25
—
100%
EK000GE170
Issue Material Supply PO to OCI (Elect, Struct, Insul)
11-Dec-25
11-Dec-25
—
100%
CK000YA306
Establish Tax Free Zone Status
13-Dec-25
31-Jan-26
—
100%
CO000C0150
Perimeter Wall
15-Dec-25
29-Mar-27
27.0d
28%
WO010K0110
010 Site Prep - Perimeter Wall
15-Dec-25
29-Mar-27
27.0d
28%
CO000M0100
Commence Engineering - Field Fab Tanks
04-Jan-26
04-Jan-26
—
100%
CO02HC0140
02H Form Pour Strip Fnds - Structure
21-Mar-26
27-Dec-26
—
12%
WO020C0100
020 Concrete & Excavation
21-Mar-26
23-Mar-27
215.0d
9%
CO000CK110
Set-Up KBR Pipe Fab Shop
24-Mar-26
27-Dec-26
—
11%
WO010C0100
010 Concrete & Excavation
27-Mar-26
04-May-27
149.0d
7%
CO01GC0150
01G Form, Pour, Strip Fnd - Control Building
27-Mar-26
01-Apr-26
—
100%
CO02JC0150
02J Form, Pour, Strip Fnd - 104-D2 (Low Temp Shift Converter)
30-Mar-26
27-Dec-26
—
9%
CO02JC0160
02J Form, Pour, Strip Fnd - 104-D1 (High Temp Shift Converter)
30-Mar-26
27-Dec-26
—
9%
CO01DC0150
01D Form, Pour, Strip Fnd - 2101-U (Cooling Tower)
31-Mar-26
27-Dec-26
—
9%
CO000A0110
Start Buildings - Admin, Canteen, Warehouse, Control
31-Mar-26
31-Mar-26
—
100%
CO000K0100
Start Construction
31-Mar-26
31-Mar-26
—
100%
CO02JC0110
02J Form, Pour, Strip Fnds - Major Fnds Gen'l
01-Apr-26
27-Dec-26
—
9%
CO000A0150
Install Guard Towers
01-Apr-26
14-Apr-26
—
100%
CO02LC0150
02L Form, Pour, Strip Fnd - 101-E (CO2 Absorber)
03-Apr-26
27-Dec-26
—
8%
CO02MC0110
02M Form, Pour, Strip Fnds - Major Fnds Gen'l
03-Apr-26
27-Dec-26
—
8%
CO02MC0140
02M Form Pour Strip Fnds - Structure
03-Apr-26
27-Dec-26
—
8%
CO02KC0150
02K Form, Pour, Strip Fnd - 114-F (Benfield Solution Tank)
04-Apr-26
27-Dec-26
—
7%
CO03DC0110
03D Form, Pour, Strip Fnds - 2002-F (Demin Water Tank)
06-Apr-26
27-Dec-26
—
7%
WO030C0100
030 Concrete & Excavation
06-Apr-26
19-Mar-27
229.0d
5%
CO02BC0110
02B Form, Pour, Strip Fnds - Major Fnds
09-Apr-26
27-Dec-26
—
6%
CO000K0108
Start Foundations - Field Fab Tanks
09-Apr-26
09-Apr-26
—
100%
CO000K0110
Start Foundations - Equipment & Piperacks
09-Apr-26
09-Apr-26
—
100%
CO010K0120
010 Construct Perimeter Roads
15-Apr-26
28-Dec-26
—
5%
CO02AC0110
02A Form, Pour, Strip Fnds - Major Fnds
15-Apr-26
09-Mar-27
189.0d
5%
CO01BC0160
01B Form, Pour, Strip Fnd - 2001-FB (Water Storage Tank)
20-Apr-26
27-Dec-26
—
5%
CO02HC0150
02H Form, Pour, Strip Fnd - 103-D (Secondary Reformer)
21-Apr-26
27-Dec-26
—
5%
CO03CC0110
03C Form, Pour, Strip Fnds - Major Fnds
21-Apr-26
27-Dec-26
—
5%
CO000M0110
Mobilize Field Fab Tank Contractor
27-Dec-26
27-Dec-26
—
0%
CO01BC0110
01B Form, Pour, Strip Fnds - Major Fnds Gen'l
27-Dec-26
27-Dec-26
—
0%
CO01BC0150
01B Form, Pour, Strip Fnd - 2001-FA (Water Storage Tank)
27-Dec-26
27-Dec-26
—
0%
CO01DC0140
01D Form Pour Strip Fnds - Sleepers
27-Dec-26
27-Dec-26
—
0%
CO01YC0140
01Y Form Pour Strip Fnds - Pipe Rack
27-Dec-26
27-Dec-26
—
0%
CO02CC0160
02C Form, Pour, Strip Fnd - 103-JTC
27-Dec-26
27-Dec-26
—
0%
CO02CM0140
02C Set - 103-JTC Surface Condenser
27-Dec-26
27-Dec-26
—
0%
CO02EC0110
02E Form, Pour, Strip Fnds - Major Fnds Gen'l
27-Dec-26
27-Dec-26
—
0%
CO02EC0140
02E Form Pour Strip Fnds - Structure
27-Dec-26
27-Dec-26
—
0%
CO02GC0160
02G Form, Pour, Strip Fnd - 102-J Fd Gas Compr. & Aux.
27-Dec-26
27-Dec-26
—
0%
CO02HC0110
02H Form, Pour, Strip Fnds - 101B (Primary Reformer)
27-Dec-26
27-Dec-26
—
0%
CO02HC0160
02H Form, Pour, Strip Fnd - 156-F (Steam Blowdown Drum)
27-Dec-26
27-Dec-26
—
0%
CO02HM0140
02H Set - 156-F Steam Blowdown Drum
27-Dec-26
27-Dec-26
—
0%
CO02LC0160
02L Form, Pour, Strip Fnd - 102-E (CO2 Stripper)
27-Dec-26
27-Dec-26
—
0%
CO02MC0150
02M Form, Pour, Strip Fnd - 105-D (Ammonia Synthesis Converter)
27-Dec-26
27-Dec-26
—
0%
CO02NC0110
02N Form, Pour, Strip Fnds - Major Fnds
27-Dec-26
27-Dec-26
—
0%
CO02YC0140
02Y Form Pour Strip Fnds - Pipe Rack
27-Dec-26
27-Dec-26
—
0%
CO03CM0110
03C Set Static Equipment - 2203/4-F Caustic, Sulfuric Acid Tanks
27-Dec-26
27-Dec-26
—
0%
CO03DC0150
03D Form, Pour, Strip Fnd - 2002J/JA (Fresh Cooling Water Pumps)
27-Dec-26
27-Dec-26
—
0%
CO03FC0110
03F Form, Pour, Strip Fnds - Package Boiler
27-Dec-26
27-Dec-26
—
0%
CO05AC0170
05A Install Test Piles
27-Dec-26
27-Dec-26
—
0%
CO01AC0120
01A Form, Pour, Strip Fnds - Misc Fnds & Sumps...
28-Dec-26
09-Jan-27
247.0d
0%
CO01BC0120
01B Form, Pour, Strip Fnds - Misc Fnds
28-Dec-26
06-Jan-27
210.0d
0%
CO01BC0140
01B Form Pour Strip Fnds - Sleepers to Evap Pond
28-Dec-26
27-Jan-27
148.0d
0%
CO01DM0130
01D Erect 2101-U Cooling Tower
28-Dec-26
04-May-27
61.0d
0%
CO01GA0110
01G Erect Control Building (Continuation w/ Design Rev)
28-Dec-26
24-Jun-27
-14.0d
0%
CO01HC0110
01H Form, Pour, Strip Piers - Substation Building
28-Dec-26
06-Feb-27
112.0d
0%
CO01YU3110
01Y U/G Earthing Installation - Pipe Rack
28-Dec-26
06-Feb-27
134.0d
0%
CO02AU4120
02A U/G Piping Installation
28-Dec-26
29-Jan-27
222.0d
0%
CO02BU4120
02B U/G Piping Installation
28-Dec-26
29-Jan-27
219.0d
0%
CO02CC0110
02C Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
26-Jan-27
165.0d
0%
CO02CC0150
02C Form, Pour, Strip Fnd - 103/105-J & Table Tops
28-Dec-26
28-Dec-26
—
0%
CO02CM0110
02C Set Static Equipment - 128/167-C
28-Dec-26
28-Dec-26
—
0%
CO02CU4120
02C U/G Piping Installation
28-Dec-26
29-Jan-27
162.0d
0%
CO02DC0110
02D Form, Pour, Strip Fnds - Major Fnds
28-Dec-26
09-Jan-27
252.0d
0%
CO02DU4120
02D U/G Piping Installation
28-Dec-26
29-Jan-27
248.0d
0%
CO02EU4120
02E U/G Piping Installation
28-Dec-26
29-Jan-27
227.0d
0%
CO02FC0110
02F Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
234.0d
0%
CO02FU4120
02F U/G Piping Installation
28-Dec-26
29-Jan-27
234.0d
0%
CO02GC0150
02G Form, Pour, Strip Fnd - 101-J/JT & 2ea. Table Tops
28-Dec-26
01-Feb-27
134.0d
0%
CO02GM0140
02G Set/Install - 102-J Fd Gas Compr. & Aux.
28-Dec-26
22-Apr-27
188.0d
0%
CO02HU4120
02H U/G Piping Installation
28-Dec-26
29-Jan-27
162.0d
0%
CO02JU4120
02J U/G Piping Installation
28-Dec-26
29-Jan-27
211.0d
0%
CO02KC0110
02K Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
192.0d
0%
CO02KU4120
02K U/G Piping Installation
28-Dec-26
29-Jan-27
214.0d
0%
CO02LC0110
02L Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
29-Jan-27
123.0d
0%
CO02LC0140
02L Form Pour Strip Fnds - 02L Structure
28-Dec-26
29-Jan-27
45.0d
0%
CO02MU4120
02M U/G Piping Installation
28-Dec-26
29-Jan-27
239.0d
0%
CO02UP0130
02U LB Pipe Erection (CW & Misc Headers)
28-Dec-26
29-Jan-27
71.0d
0%
CO02UV1110
02U Paint Fabricated Pipe Spools (CW & Misc Headers)
28-Dec-26
28-Dec-26
—
0%
CO02YU3110
02Y U/G Earthing Installation
28-Dec-26
29-Jan-27
100.0d
0%
CO03AC0110
03A Form, Pour, Strip Fnds - Major Fnds Gen'l
28-Dec-26
16-Jan-27
155.0d
0%
CO03BC0110
03B Form, Pour, Strip Fnds - Major Fnds (N/A)
28-Dec-26
28-Dec-26
—
0%
CO03BC0140
03B Form, Pour, Strip Fnds - 2401-A Wastewater Sump
28-Dec-26
30-Dec-26
266.0d
0%
CO03DU4120
03D U/G Piping Installation
28-Dec-26
05-Jan-27
199.0d
0%
CO03EC0110
03E Form, Pour, Strip Fnds - 2001-U Water Treatment
28-Dec-26
20-Feb-27
126.0d
0%
CO03FM0110
03F Erect 2002-U Package Boiler
28-Dec-26
13-Mar-27
159.0d
0%
CO03YC0110
03Y Form, Pour, Strip Fnds - Sleeper Fnds
28-Dec-26
01-Jan-27
98.0d
0%
CO03YC0120
03Y Form, Pour, Strip Fnds - Pipe Rack Fnds
28-Dec-26
28-Dec-26
—
0%
CO04AV1100
04A Paint
28-Dec-26
25-May-27
148.0d
0%
CO05AC0175
05A Test Piles (Load Test)
28-Dec-26
09-Jan-27
-51.0d
0%
WO010A0100
010 Buildings
28-Dec-26
24-Jun-27
94.0d
0%
WO010M0100
010 Major Equipment
28-Dec-26
01-Sep-27
54.0d
0%
WO010U3100
010 Install U/G Electrical
28-Dec-26
27-Mar-27
170.0d
0%
WO020M0100
020 Major Equipment
28-Dec-26
16-Aug-27
156.0d
0%
WO020U3100
020 Install U/G Electrical
28-Dec-26
12-Mar-27
265.0d
0%
WO020U4100
020 U/G Piping Installation
28-Dec-26
26-Feb-27
224.0d
0%
WO030M0100
030 Major Equipment
28-Dec-26
26-Apr-27
192.0d
0%
WO030U4100
030 U/G Piping Installation
28-Dec-26
26-Feb-27
229.0d
0%
WO04AV1100
04A Paint
28-Dec-26
25-May-27
148.0d
0%
WO050C0110
050 Concrete Paving
28-Dec-26
28-Dec-26
0.0d
0%
SC01JT0120
01J RFSU
28-Dec-26
28-Dec-26
441.0d
0%
CO01AV1110
01A Paint Fabricated Pipe Spools
31-Dec-26
02-Jan-27
253.0d
0%
WO010V1100
010 Paint
31-Dec-26
05-Oct-27
131.0d
0%
CO02HM0200
02H Start Primary Reformer Erection (101-B)
02-Jan-27
02-Jan-27
108.0d
0%
CO02HM0210
02H Erect Radiant Section Shell (101-B)
02-Jan-27
02-Apr-27
108.0d
0%
CO02LU4120
02L U/G Piping Installation
02-Jan-27
29-Jan-27
123.0d
0%
CO01UP0150
01U LB Pipe Erection (Firewater Piping)
05-Jan-27
06-Feb-27
212.0d
0%
WO010U4100
010 U/G Piping Installation
05-Jan-27
26-Mar-27
171.0d
0%
CO02GU4120
02G U/G Piping Installation
06-Jan-27
26-Feb-27
159.0d
0%
CO03DC0120
03D Form, Pour, Strip Fnds - Misc Fnds
06-Jan-27
19-Jan-27
199.0d
0%
EK05ACV210
05A COSMO Design Approval (Assuming No Change)
11-Jan-27
16-Jan-27
-51.0d
0%
CO02CM0125
02C Set - 103/105-J Compressors
12-Jan-27
16-Jan-27
167.0d
0%
CO02YS0110
02Y Erect Structural Steel - Pipe Rack
12-Jan-27
14-Jun-27
-35.0d
0%
WO020S0100
020 Erect Steel
12-Jan-27
07-Oct-27
69.0d
0%
CO02HU3110
02H U/G Earthing Installation
13-Jan-27
12-Feb-27
162.0d
0%
CO03YV1110
03Y Paint Fabricated Pipe Spools
13-Jan-27
13-Feb-27
154.0d
0%
WO030V1100
030 Paint
13-Jan-27
23-Aug-27
153.0d
0%
CO02CU3110
02C U/G Earthing Installation
14-Jan-27
12-Feb-27
168.0d
0%
CO03DU3110
03D U/G Earthing Installation
15-Jan-27
19-Jan-27
199.0d
0%
WO030U3100
030 Install U/G Electrical
15-Jan-27
12-Mar-27
229.0d
0%
CO02HC0120
02H Form, Pour, Strip Fnds - Misc Fnds
16-Jan-27
05-Feb-27
174.0d
0%
CO02LU3110
02L U/G Earthing Installation
16-Jan-27
12-Feb-27
129.0d
0%
CO02UP0150
02U LB Pipe Erection (Firewater Piping)
16-Jan-27
06-Feb-27
212.0d
0%
CO03UP0150
03U LB Pipe Erection (Firewater Piping)
16-Jan-27
06-Feb-27
212.0d
0%
CO02CM0130
02C Install - 103/105-J Compressors & Aux. Equip.
18-Jan-27
13-May-27
167.0d
0%
CO05AC0185
05A Procure Material & Mob Piling Contractor
18-Jan-27
30-Jan-27
-51.0d
0%
CO02AU3110
02A U/G Earthing Installation
20-Jan-27
05-Feb-27
228.0d
0%
CO02CV1110
02C Paint Fabricated Pipe Spools
20-Jan-27
27-Feb-27
245.0d
0%
WO020V1100
020 Paint
20-Jan-27
14-Feb-28
23.0d
0%
CO02GC0110
02G Form, Pour, Strip Fnds - Major Fnds Gen'l
23-Jan-27
26-Feb-27
159.0d
0%
CO01HU3110
01H U/G Earthing Installation
25-Jan-27
06-Feb-27
134.0d
0%
CO02JU3110
02J U/G Earthing Installation
25-Jan-27
12-Feb-27
211.0d
0%
CO02BM0110
02B Set Static Equipment
25-Jan-27
25-Jan-27
—
0%
CO02BV1130
02B Paint Touch-up - Equipment
25-Jan-27
01-Feb-27
300.0d
0%
CO02KU3110
02K U/G Earthing Installation
26-Jan-27
12-Feb-27
214.0d
0%
CO02EU3110
02E U/G Earthing Installation
28-Jan-27
12-Feb-27
227.0d
0%
CO01YV1110
01Y Paint Fabricated Pipe Spools
28-Jan-27
05-Feb-27
149.0d
0%
CO02FU3110
02F U/G Earthing Installation
29-Jan-27
12-Feb-27
234.0d
0%
CO01JP0230
01J U/G Pipe Erection - Piping to Corridor
29-Jan-27
26-Feb-27
160.0d
0%
CO04AU4120
04A U/G Piping Installation
29-Jan-27
09-Aug-27
108.0d
0%
WO04AE0100
04A Above Ground Electrical
29-Jan-27
01-Sep-27
108.0d
0%
WO04AI0100
04A Install Instruments & Test
29-Jan-27
01-Sep-27
108.0d
0%
WO04AM0100
04A Major Equipment
29-Jan-27
01-Sep-27
108.0d
0%
WO04AS0100
04A Erect Steel
29-Jan-27
01-Sep-27
108.0d
0%
WO04AU4100
04A U/G Piping Installation
29-Jan-27
01-Sep-27
108.0d
0%
CO02BC0120
02B Form, Pour, Strip Fnds - Misc Fnds
29-Jan-27
29-Jan-27
—
0%
CO01BU4120
01B U/G Piping Installation
30-Jan-27
10-Mar-27
173.0d
0%
CO01DU4120
01D U/G Piping Installation
30-Jan-27
02-Mar-27
49.0d
0%
CO01EU4130
01E/F/G U/G Piping Installation (to Bldg Stub Outs)
30-Jan-27
26-Mar-27
147.0d
0%
CO02CC0120
02C Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
19-Feb-27
162.0d
0%
CO02DC0120
02D Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
30-Jan-27
260.0d
0%
CO02EC0120
02E Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
227.0d
0%
CO02FC0120
02F Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
234.0d
0%
CO02FM0110
02F Set Static Equipment
30-Jan-27
26-Feb-27
241.0d
0%
CO02JC0120
02J Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
211.0d
0%
CO02KC0120
02K Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
214.0d
0%
CO02LC0120
02L Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
19-Feb-27
123.0d
0%
CO02MC0120
02M Form, Pour, Strip Fnds - Misc Fnds
30-Jan-27
12-Feb-27
239.0d
0%
CO02MU3110
02M U/G Earthing Installation
30-Jan-27
12-Feb-27
239.0d
0%
CO02YC0130
02Y Install Paving
30-Jan-27
17-Mar-27
71.0d
0%
CO03AU4120
03A U/G Piping Installation
30-Jan-27
18-Feb-27
135.0d
0%
CO03BU4120
03B U/G Piping Installation
30-Jan-27
17-Feb-27
237.0d
0%
CO03CU4120
03C U/G Piping Installation
30-Jan-27
18-Feb-27
166.0d
0%
CO03EU4120
03E U/G Piping Installation
30-Jan-27
26-Feb-27
121.0d
0%
CO03FU4120
03F U/G Piping Installation
30-Jan-27
18-Feb-27
155.0d
0%
WO020C0110
020 Concrete Paving
30-Jan-27
22-May-27
210.0d
0%
CO01HC0140
01H Form Pour Strip Fnds - Transformers & Generator
01-Feb-27
27-Feb-27
116.0d
0%
CO03DC0130
03D Install Paving
01-Feb-27
06-Feb-27
189.0d
0%
CO03FM0150
03F Install Chemical Injection System
01-Feb-27
13-Mar-27
159.0d
0%
CO05AC0150
05A Install Piling - 2101-F Ammonia Tank
01-Feb-27
19-Apr-27
-51.0d
0%
CO05AC0155
05A Install Piling - 2102-F Ammonia Tank
01-Feb-27
19-Apr-27
-40.0d
0%
WO030C0110
030 Concrete Paving
01-Feb-27
17-Apr-27
210.0d
0%
WO050C0100
050 Concrete & Excavation
01-Feb-27
30-Jul-27
152.0d
0%
CO02DU3110
02D U/G Earthing Installation
02-Feb-27
12-Feb-27
248.0d
0%
CO01EA0130
01E Erect Guard House
04-Feb-27
03-Mar-27
191.0d
0%
CO01FA0130
01F Erect Mosque
04-Feb-27
28-Apr-27
143.0d
0%
CO02YV1110
02Y Paint Fabricated Pipe Spools
05-Feb-27
19-Feb-27
131.0d
0%
CO01CC0110
01C Form, Pour, Strip Fnds - Major Fnds Gen'l
08-Feb-27
06-Mar-27
117.0d
0%
CO01YC0130
01Y Install Paving
08-Feb-27
27-Feb-27
134.0d
0%
WO010C0110
010 Concrete Paving
08-Feb-27
08-Jul-27
188.0d
0%
CO02BU3110
02B U/G Earthing Installation
10-Feb-27
12-Feb-27
289.0d
0%
CO02EV1110
02E Paint Fabricated Pipe Spools
12-Feb-27
04-Mar-27
250.0d
0%
CO03AC0120
03A Form, Pour, Strip Fnds - Misc Fnds
12-Feb-27
25-Feb-27
141.0d
0%
CO03CV1110
03C Paint Fabricated Pipe Spools
13-Feb-27
24-Feb-27
191.0d
0%
CO02GU3110
02G U/G Earthing Installation
15-Feb-27
12-Mar-27
159.0d
0%
CO02GV1110
02G Paint Fabricated Pipe Spools
16-Feb-27
22-Mar-27
230.0d
0%
CO03BC0120
03B Form, Pour, Strip Fnds - Misc Fnds
18-Feb-27
03-Mar-27
243.0d
0%
CO03CC0120
03C Form, Pour, Strip Fnds - Misc Fnds
19-Feb-27
04-Mar-27
166.0d
0%
CO03EV1110
03E Paint Fabricated Pipe Spools
19-Feb-27
09-Mar-27
171.0d
0%
CO03FC0120
03F Form, Pour, Strip Fnds - Misc Fnds
19-Feb-27
11-Mar-27
155.0d
0%
CO03FV1110
03F Paint Fabricated Pipe Spools
19-Feb-27
02-Mar-27
183.0d
0%
CO02CC0130
02C Install Paving
20-Feb-27
05-Mar-27
162.0d
0%
CO02LC0130
02L Install Paving
20-Feb-27
05-Mar-27
123.0d
0%
CO01CU4120
01C U/G Piping Installation
22-Feb-27
06-Mar-27
160.0d
0%
CO02HM0220
02H Erect Radiant Ducting / Burners (101-B)
22-Feb-27
20-Mar-27
151.0d
0%
CO03BU3110
03B U/G Earthing Installation
23-Feb-27
03-Mar-27
237.0d
0%
CO03CU3110
03C U/G Earthing Installation
24-Feb-27
04-Mar-27
166.0d
0%
CO03FU3110
03F U/G Earthing Installation
24-Feb-27
04-Mar-27
161.0d
0%
CO03AU3110
03A U/G Earthing Installation
26-Feb-27
04-Mar-27
135.0d
0%
CO02UDT110
02U Mechanical Completion
26-Feb-27
26-Feb-27
301.0d
0%
CO03UDT110
03U Mechanical Completion
26-Feb-27
26-Feb-27
301.0d
0%
SC02UT0120
02U RFSU
26-Feb-27
26-Feb-27
380.0d
0%
SC03UT0120
03U RFSU
26-Feb-27
26-Feb-27
380.0d
0%
CO02GC0120
02G Form, Pour, Strip Fnds - Misc Fnds
27-Feb-27
19-Mar-27
165.0d
0%
CO02GM0110
02G Set Static Equipment - Gen'l
27-Feb-27
31-Mar-27
208.0d
0%
CO03AV1110
03A Paint Fabricated Pipe Spools
27-Feb-27
10-Mar-27
148.0d
0%
CO03EC0120
03E Form, Pour, Strip Fnds - Misc Fnds
27-Feb-27
19-Mar-27
121.0d
0%
CO03EU3110
03E U/G Earthing Installation
27-Feb-27
12-Mar-27
127.0d
0%
CO01HC0120
01H Form, Pour, Strip Fnds - Misc Fnds
01-Mar-27
13-Mar-27
176.0d
0%
CO02JS0130
02J Pre-Install Misc Steel - 104-D2
01-Mar-27
15-Mar-27
103.0d
0%
CO02JS0140
02J Pre-Install Misc Steel - 104-D1
01-Mar-27
15-Mar-27
108.0d
0%
CO02LS0130
02L Pre-Install Misc Steel - 101-E
01-Mar-27
15-Mar-27
113.0d
0%
CO03BM0110
03B Set Static Equipment - Gen'l
01-Mar-27
02-Apr-27
212.0d
0%
CO03EM0110
03E Set Static Equipment - Gen'l
01-Mar-27
05-Apr-27
135.0d
0%
CO01DC0110
01D Form, Pour, Strip Fnds - Major Fnds Gen'l
03-Mar-27
13-Apr-27
49.0d
0%
CO01DU3110
01D U/G Earthing Installation
03-Mar-27
17-Mar-27
113.0d
0%
CO01EC0135
01E Install Paving - Guard House
04-Mar-27
17-Mar-27
285.0d
0%
CO03BC0130
03B Install Paving
04-Mar-27
17-Mar-27
237.0d
0%
CO01BU3110
01B U/G Earthing Installation
05-Mar-27
24-Mar-27
173.0d
0%
CO01YS0110
01Y Erect Structural Steel - Pipe Rack
06-Mar-27
30-Apr-27
39.0d
0%
CO03DV1110
03D Paint Fabricated Pipe Spools
06-Mar-27
11-Mar-27
172.0d
0%
CO03YS0110
03Y Erect Structural Steel
06-Mar-27
26-Mar-27
39.0d
0%
WO010S0100
010 Erect Steel
06-Mar-27
11-Jun-27
94.0d
0%
WO030S0100
030 Erect Steel
06-Mar-27
25-Jun-27
157.0d
0%
CO01CV1110
01C Paint Fabricated Pipe Spools
06-Mar-27
13-Mar-27
174.0d
0%
CO01BV1110
01B Paint Fabricated Pipe Spools
08-Mar-27
30-Mar-27
153.0d
0%
CO01CC0120
01C Form, Pour, Strip Fnds - Misc Fnds
08-Mar-27
27-Mar-27
160.0d
0%
CO03AC0130
03A Install Paving
08-Mar-27
13-Mar-27
133.0d
0%
CO02GM0125
02G Set - 101-J/JT Air Compr.
08-Mar-27
05-Apr-27
105.0d
0%
CO02AC0120
02A Form, Pour, Strip Fnds - Misc Fnds
10-Mar-27
23-Mar-27
189.0d
0%
CO02AM0150
02A Set Rotating Equipment
10-Mar-27
06-Apr-27
207.0d
0%
CO01DV1110
01D Paint Fabricated Pipe Spools
11-Mar-27
29-Mar-27
142.0d
0%
CO02GC0130
02G Install Paving
13-Mar-27
26-Mar-27
159.0d
0%
CO01CU3110
01C U/G Earthing Installation
15-Mar-27
20-Mar-27
166.0d
0%
CO01GU3110
01G U/G Earthing Installation
15-Mar-27
27-Mar-27
146.0d
0%
CO03CC0130
03C Install Paving
15-Mar-27
20-Mar-27
158.0d
0%
CO02HM0250
02H Set Forced Draft Fan (101-B)
15-Mar-27
12-Apr-27
234.0d
0%
CO03CM0150
03C Set Rotating Equipment
15-Mar-27
22-Mar-27
146.0d
0%
CO03DM0150
03D Set Rotating Equipment
15-Mar-27
29-Mar-27
158.0d
0%
CO02HM0135
02H Give 30 Day notice to Manufacture Refractory (103-D)
16-Mar-27
16-Mar-27
-40.0d
0%
CO03FV1130
03F Paint Touch-up - Equipment
17-Mar-27
27-Mar-27
183.0d
0%
CO02YS0120
02Y Erect Misc Steel - Pipe Rack
19-Mar-27
14-Jun-27
102.0d
0%
CO02HM0246
02H Install Radiant Sect Coils (101-B)
22-Mar-27
17-Apr-27
151.0d
0%
CO03FC0130
03F Install Paving
22-Mar-27
03-Apr-27
147.0d
0%
CO02HM0255
02H Set Induced Draft Fan (101-B)
22-Mar-27
19-Apr-27
234.0d
0%
CO02KV1130
02K Paint Touch-up - Equipment
23-Mar-27
15-Apr-27
236.0d
0%
CO02AC0130
02A Install Paving
24-Mar-27
30-Mar-27
189.0d
0%
CO03CV1130
03C Paint Touch-up - Equipment
24-Mar-27
05-Apr-27
195.0d
0%
CO02CM0150
02C Set Rotating Equipment - 112-J/JA/JM
26-Mar-27
30-Mar-27
205.0d
0%
CO02GM0150
02G Set Rotating Equipment
26-Mar-27
10-Apr-27
199.0d
0%
CO02KM0150
02K Set Rotating Equipment
26-Mar-27
01-Apr-27
163.0d
0%
CO02LM0150
02L Set Rotating Equipment
26-Mar-27
27-Apr-27
170.0d
0%
CO03BM0150
03B Set Rotating Equipment
26-Mar-27
15-Apr-27
200.0d
0%
CO01UDT110
01U Mechanical Completion
26-Mar-27
26-Mar-27
277.0d
0%
SC01UT0120
01U RFSU
26-Mar-27
26-Mar-27
352.0d
0%
CO02HS0140
02H Install Misc Steel - 156-F
27-Mar-27
09-Apr-27
102.0d
0%
CO03YP0130
03Y LB Pipe Erection
27-Mar-27
09-Jul-27
39.0d
0%
WO030P0100
030 Above Ground Pipe
27-Mar-27
23-Aug-27
138.0d
0%
CO02JV1110
02J Paint Fabricated Pipe Spools
27-Mar-27
27-Mar-27
164.0d
0%
CO01CC0130
01C Install Paving
29-Mar-27
10-Apr-27
160.0d
0%
CO03AM0110
03A Set Static Equipment
29-Mar-27
26-Apr-27
95.0d
0%
CO02AV1130
02A Paint Touch-up - Equipment
30-Mar-27
20-Apr-27
232.0d
0%
CO01BM0110
01B Set Static Equipment
31-Mar-27
27-Apr-27
71.0d
0%
CO02MV1110
02M Paint Fabricated Pipe Spools
01-Apr-27
14-Apr-27
215.0d
0%
CO02NV1110
02N Paint Fabricated Pipe Spools
01-Apr-27
03-Apr-27
216.0d
0%
CO04AU3110
04A U/G Fiber Optic Cable Installation
01-Apr-27
10-Aug-27
137.0d
0%
WO04AU3100
04A Install U/G Electrical
01-Apr-27
10-Aug-27
137.0d
0%
CO02DM0150
02D Set Rotating Equipment
02-Apr-27
15-Apr-27
182.0d
0%
CO01BS0120
01B Erect Misc Steel
03-Apr-27
30-Apr-27
86.0d
0%
CO02HC0130
02H Install Paving
03-Apr-27
16-Apr-27
120.0d
0%
CO02HM0230
02H Set Convection Sections (101-B)
03-Apr-27
30-Apr-27
108.0d
0%
CO02HM0240
02H Set Stack for (101-B)
03-Apr-27
30-Apr-27
223.0d
0%
CO03YP0140
03Y SB Pipe Erection
03-Apr-27
16-Jul-27
45.0d
0%
CO02JC0130
02J Install Paving
05-Apr-27
10-Apr-27
168.0d
0%
CO03BV1110
03B Paint Fabricated Pipe Spools
05-Apr-27
15-Apr-27
223.0d
0%
CO03EC0130
03E Install Paving
05-Apr-27
17-Apr-27
108.0d
0%
CO01CM0110
01C Set Static Equipment - EDR Equipment
05-Apr-27
31-May-27
93.0d
0%
CO01CM0115
01C Set Rotating Equipment - EDR Equipment
05-Apr-27
31-May-27
99.0d
0%
CO02GM0130
02G Install - 101-J/JT Air Compr. & Gen. Turb. & Aux.
05-Apr-27
30-Jul-27
105.0d
0%
CO02HS0130
02H Pre-Install Misc Steel - 103-D
05-Apr-27
19-Apr-27
68.0d
0%
CO03DV1130
03D Paint Touch-up - Equipment (& 2002-F Tank)
06-Apr-27
12-Apr-27
189.0d
0%
CO02FV1110
02F Paint Fabricated Pipe Spools
09-Apr-27
27-Apr-27
204.0d
0%
CO02LV1110
02L Paint Fabricated Pipe Spools
09-Apr-27
29-May-27
162.0d
0%
CO02KV1110
02K Paint Fabricated Pipe Spools
10-Apr-27
04-May-27
181.0d
0%
CO02LS0110
02L Erect Structure
10-Apr-27
18-Jun-27
-15.0d
0%
CO02KC0130
02K Install Paving
12-Apr-27
17-Apr-27
165.0d
0%
CO01HA0110
01H Set 2610-K Electrical Power House
12-Apr-27
03-May-27
76.0d
0%
CO02YP0130
02Y LB Pipe Erection
13-Apr-27
05-Oct-27
-35.0d
0%
WO020P0100
020 Above Ground Pipe
13-Apr-27
14-Feb-28
-1.0d
0%
CO01DC0120
01D Form, Pour, Strip Fnds - Misc Fnds
14-Apr-27
04-May-27
72.0d
0%
CO01DM0110
01D Set Static Equipment
14-Apr-27
25-May-27
49.0d
0%
CO02DV1130
02D Paint Touch-up - Equipment
15-Apr-27
29-Apr-27
224.0d
0%
CO02FM0150
02F Set Rotating Equipment
16-Apr-27
13-May-27
176.0d
0%
CO02QV1110
02Q Paint Fabricated Pipe Spools
16-Apr-27
20-Apr-27
210.0d
0%
CO020M0110
Mobilize / Assemble / Test Heavy Lift Crane
19-Apr-27
01-May-27
56.0d
0%
CO02EC0130
02E Install Paving
19-Apr-27
24-Apr-27
172.0d
0%
CO02HM0248
02H Install Effluent Transfer Line (107-D)
19-Apr-27
01-May-27
151.0d
0%
CO03BV1130
03B Paint Touch-up - Equipment
19-Apr-27
29-Apr-27
248.0d
0%
CO01HM0110
01H Set Static Equipment - 2303-J Emergency Pwr Gen.
19-Apr-27
31-May-27
86.0d
0%
CO02LS0140
02L Pre-Install Misc Steel - 102-E
19-Apr-27
03-May-27
76.0d
0%
CO05AC0160
05A Form, Pour, Strip Fnd - 2101-F Ammonia Tank
20-Apr-27
16-Jun-27
-51.0d
0%
CO05AC0165
05A Form, Pour, Strip Fnd - 2102-F Ammonia Tank
20-Apr-27
16-Jun-27
-40.0d
0%
CO02DV1110
02D Paint Fabricated Pipe Spools
23-Apr-27
07-May-27
177.0d
0%
CO04AC0110
04A Concrete (Valve Boxes & Paving)
23-Apr-27
23-Aug-27
130.0d
0%
WO04AC0100
04A Concrete (Valve Boxes & Paving)
23-Apr-27
23-Aug-27
130.0d
0%
CO01YS0120
01Y Erect Misc Steel - Pipe Rack
24-Apr-27
21-May-27
39.0d
0%
CO02MS0110
02M Erect Structural Steel - Structure
24-Apr-27
14-May-27
123.0d
0%
CO02PV1110
02P Paint Fabricated Pipe Spools
24-Apr-27
28-Apr-27
199.0d
0%
CO02FC0130
02F Install Paving
26-Apr-27
01-May-27
173.0d
0%
CO02HV1110
02H Paint Fabricated Pipe Spools
26-Apr-27
05-Jun-27
54.0d
0%
CO04AU4130
04A Punchlist / Test U/G Piping
28-Apr-27
01-Sep-27
108.0d
0%
CO01FC0135
01F Install Paving - Mosque
29-Apr-27
19-May-27
203.0d
0%
CO01BM0150
01B Set Rotating Equipment
01-May-27
11-Jun-27
32.0d
0%
CO01DM0150
01D Set Rotating Equipment
01-May-27
11-Jun-27
34.0d
0%
CO01YP0130
01Y LB Pipe Erection - Pipe Rack
01-May-27
25-Jun-27
39.0d
0%
CO02CS0120
02C Erect Misc. Steel (Platforms)
01-May-27
02-Aug-27
83.0d
0%
CO02GS0130
02G Erect Misc. Steel (Platforms)
01-May-27
02-Aug-27
107.0d
0%
CO02HM0235
02H Erect Preheater (101-B)
01-May-27
25-Jun-27
175.0d
0%
WO010P0100
010 Above Ground Pipe
01-May-27
05-Oct-27
95.0d
0%
CO020M0120
Heavy Lift Crane Useage
03-May-27
04-Aug-27
56.0d
0%
CO02HM0130
02H Set (Heavy Lift) - 103-D (Secondary Reformer)
03-May-27
07-May-27
56.0d
0%
CO02HM0225
02H Erect Penthouse Roof, & Siding (101-B)
03-May-27
29-May-27
151.0d
0%
CO02MC0130
02M Install Paving
03-May-27
08-May-27
172.0d
0%
CO02KS0130
02K Pre-Install Misc Steel - Static Equipment
03-May-27
17-May-27
101.0d
0%
CO02GP0130
02G LB Pipe Erection
04-May-27
10-Sep-27
105.0d
0%
CO01DC0130
01D Install Paving
05-May-27
18-May-27
72.0d
0%
CO01DS0120
01D Erect Misc Steel
05-May-27
01-Jun-27
61.0d
0%
CO05AV1110
05A Paint Fabricated Pipe Spools
05-May-27
07-Jun-27
166.0d
0%
WO050V1100
050 Paint
05-May-27
12-Apr-28
12.0d
0%
CO02CP0130
02C LB Pipe Erection
08-May-27
08-Oct-27
83.0d
0%
CO02DS0110
02D Erect Structural Steel
08-May-27
28-May-27
93.0d
0%
CO02JM0130
02J Set (Heavy Lift) - 104-D2 (Low Temp Shift Converter)
08-May-27
13-May-27
56.0d
0%
CO02LS0120
02L Erect Misc Steel
08-May-27
04-Jun-27
39.0d
0%
CO02DC0130
02D Install Paving
10-May-27
15-May-27
175.0d
0%
CO02FV1130
02F Paint Touch-up - Equipment
10-May-27
27-May-27
200.0d
0%
CO02MS0130
02M Pre-Install Misc Steel - 105-D
10-May-27
24-May-27
63.0d
0%
CO02YP0140
02Y SB Pipe Erection
11-May-27
02-Nov-27
-29.0d
0%
CO05AC0120
05A Form, Pour, Strip Fnds - Sleeper & Rack
11-May-27
14-Jun-27
44.0d
0%
CO02GP0140
02G SB Pipe Erection
11-May-27
25-Sep-27
105.0d
0%
CO04AV2110
04A Insulation
12-May-27
28-Sep-27
108.0d
0%
WO04AV2100
04A Insulation
12-May-27
28-Sep-27
108.0d
0%
CO05AU4120
05A U/G Piping Installation
13-May-27
07-Jul-27
77.0d
0%
WO050U4100
050 U/G Piping Installation
13-May-27
30-Sep-27
135.0d
0%
CO02CV1130
02C Paint Touch-up - Equipment
14-May-27
22-Jun-27
190.0d
0%
CO02JM0140
02J Set (Heavy Lift) - 104-D1 (High Temp Shift Converter)
14-May-27
19-May-27
56.0d
0%
CO01CS0120
01C Erect Misc Steel
15-May-27
28-May-27
106.0d
0%
CO01HS0110
01H Erect Structural Steel - Stairs & Platform
15-May-27
11-Jun-27
51.0d
0%
CO02AS0110
02A Erect Structural Steel
15-May-27
04-Jun-27
103.0d
0%
CO02CP0140
02C SB Pipe Erection
15-May-27
15-Oct-27
83.0d
0%
CO02MM0110
02M Set Static Equipment - Gen'l
15-May-27
16-Jun-27
147.0d
0%
CO03BS0120
03B Erect Misc Steel - Structure
15-May-27
11-Jun-27
169.0d
0%
CO03FS0120
03F Erect Misc Steel
15-May-27
25-Jun-27
88.0d
0%
CO01BE0110
01B Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
105.0d
0%
CO01EE0110
01E Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
180.0d
0%
CO01FE0110
01F Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
152.0d
0%
CO01GE0130
01G Power Tray, Cable, Terminations
17-May-27
12-Jun-27
92.0d
0%
CO02BC0130
02B Install Paving
17-May-27
22-May-27
210.0d
0%
CO03CE0110
03C Lighting JB's, Stands, Tray & Cable
17-May-27
12-Jun-27
123.0d
0%
CO03DE0110
03D Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
105.0d
0%
CO03DE0130
03D Power/Control JB's, Tray, Cable, Termination
17-May-27
04-Jun-27
131.0d
0%
CO03EE0110
03E Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
105.0d
0%
CO03FE0110
03F Lighting JB's, Stands, Tray & Cable
17-May-27
26-Jun-27
111.0d
0%
CO03YE0110
03Y Lighting JB's, Stands, Tray & Cable
17-May-27
07-Aug-27
162.0d
0%
CO03YE0130
03Y Power/Control JB's, Tray, Cable, Termination
17-May-27
07-Aug-27
32.0d
0%
CO03YI0120
03Y Instrument JB's, Field Instr, Tray, Cable
17-May-27
07-Aug-27
32.0d
0%
WO010E0100
010 Above Ground Electrical
17-May-27
05-Oct-27
131.0d
0%
WO030E0100
030 Above Ground Electrical
17-May-27
23-Aug-27
153.0d
0%
WO030I0100
030 Install Instruments & Test
17-May-27
17-Jan-28
41.0d
0%
CO02KM0110
02K Set Static Equipment - Gen'l
17-May-27
07-Jun-27
101.0d
0%
CO04AK0110
04A Site Prep (Leveling)
19-May-27
05-Oct-27
108.0d
0%
WO04AK0100
04A Site Prep (Leveling)
19-May-27
05-Oct-27
108.0d
0%
CO02AV1110
02A Paint Fabricated Pipe Spools
20-May-27
02-Jun-27
172.0d
0%
CO02LM0130
02L Set (Heavy Lift) - 101-E (CO2 Absorber)
20-May-27
25-May-27
56.0d
0%
CO01YE0110
01Y Lighting JB's, Stands, Tray & Cable
22-May-27
02-Jul-27
175.0d
0%
CO02ES0110
02E Erect Structural Steel
22-May-27
11-Jun-27
127.0d
0%
CO02ES0120
02E Erect Misc Steel
22-May-27
11-Jun-27
67.0d
0%
CO02FS0120
02F Erect Misc Steel
22-May-27
11-Jun-27
133.0d
0%
CO02JS0110
02J Erect Structural Steel - Structure
22-May-27
04-Jun-27
98.0d
0%
CO02MS0120
02M Erect Misc Steel - Structure
22-May-27
11-Jun-27
123.0d
0%
CO03AS0120
03A Erect Misc Steel - Structure
22-May-27
18-Jun-27
56.0d
0%
CO03CS0120
03C Erect Misc Steel
22-May-27
11-Jun-27
87.0d
0%
CO03DS0120
03D Erect Misc Steel
22-May-27
18-Jun-27
98.0d
0%
CO03ES0120
03E Erect Misc Steel - Structure
22-May-27
18-Jun-27
58.0d
0%
CO02BV1110
02B Paint Fabricated Pipe Spools
25-May-27
31-May-27
175.0d
0%
CO03FP0130
03F LB Pipe Erection
25-May-27
02-Jul-27
88.0d
0%
CO02LM0140
02L Set (Heavy Lift) - 102-E (CO2 Stripper)
26-May-27
31-May-27
56.0d
0%
CO02GE0130
02G Power/Control JB's, Tray, Cable, Termination
26-May-27
02-Oct-27
108.0d
0%
CO02GI0120
02G Instrument JB's, Field Instr, Tray, Cable
26-May-27
02-Oct-27
108.0d
0%
WO020E0100
020 Above Ground Electrical
26-May-27
14-Feb-28
23.0d
0%
WO020I0100
020 Install Instruments & Test
26-May-27
01-Mar-28
9.0d
0%
CO02CV2110
02C Insulate - Equipment
28-May-27
06-Jul-27
190.0d
0%
WO020V2100
020 Insulation
28-May-27
13-Mar-28
-1.0d
0%
CO01CE0110
01C Lighting JB's, Stands, Tray & Cable
29-May-27
18-Jun-27
124.0d
0%
CO01YP0140
01Y SB Pipe Erection - Pipe Rack
29-May-27
23-Jul-27
39.0d
0%
CO02DM0110
02D Set Static Equipment
29-May-27
11-Jun-27
133.0d
0%
CO02DS0120
02D Erect Misc Steel
29-May-27
18-Jun-27
93.0d
0%
CO02EP0130
02E LB Pipe Erection
29-May-27
06-Nov-27
67.0d
0%
CO02HM0260
02H Compete Installation of Ducts (101-B)
29-May-27
23-Jul-27
175.0d
0%
CO03AP0130
03A LB Pipe Erection
29-May-27
07-Jul-27
56.0d
0%
CO03CP0130
03C LB Pipe Erection
29-May-27
07-Jul-27
87.0d
0%
CO03EP0130
03E LB Pipe Erection
29-May-27
30-Jul-27
58.0d
0%
CO03YV1120
03Y Paint Touch-up - Piping
29-May-27
23-Jul-27
175.0d
0%
CO05BV1110
05B Paint Fabricated Pipe Spools
29-May-27
07-Jun-27
214.0d
0%
CO02HM0215
02H Erect Fuel Gas Lines (101-B)
31-May-27
26-Jun-27
151.0d
0%
CO02HM0227
02H Install Spring Hangers & Align (101-B)
31-May-27
10-Jul-27
186.0d
0%
CO02HM0245
02H Install Insulation (101-B)
31-May-27
24-Jul-27
174.0d
0%
CO01CA0110
01C Erect - EDR Shelter
31-May-27
21-Jun-27
98.0d
0%
CO01AK0150
01A Excavate Evaporation Pond
01-Jun-27
12-Jul-27
54.0d
0%
CO02CE0130
02C Power/Control JB's, Tray, Cable, Termination
01-Jun-27
22-Oct-27
88.0d
0%
CO02CI0120
02C Instrument JB's, Field Instr, Tray, Cable
01-Jun-27
22-Oct-27
88.0d
0%
CO02JM0110
02J Set Static Equipment - Gen'l
01-Jun-27
11-Jun-27
98.0d
0%
CO02MM0130
02M Set (Heavy Lift) - 105-D (Ammonia Converter)
01-Jun-27
05-Jun-27
56.0d
0%
CO03FP0140
03F SB Pipe Erection
01-Jun-27
09-Jul-27
88.0d
0%
WO010K0100
010 Site Prep
01-Jun-27
28-Jan-28
37.0d
0%
CO01DE0110
01D Lighting JB's, Stands, Tray & Cable
02-Jun-27
13-Jul-27
66.0d
0%
CO03YP0150
03Y Punchlist / Test Piping
02-Jun-27
23-Jul-27
139.0d
0%
CO01BV1130
01B Paint Touch-up - Equipment
03-Jun-27
25-Jun-27
100.0d
0%
CO02AM0110
02A Set Static Equipment
05-Jun-27
18-Jun-27
144.0d
0%
CO02JS0120
02J Erect Misc Steel - Structure
05-Jun-27
11-Jun-27
98.0d
0%
CO02LE0110
02L Lighting JB's, Stands, Tray & Cable
05-Jun-27
16-Jul-27
163.0d
0%
CO03AP0140
03A SB Pipe Erection
05-Jun-27
14-Jul-27
56.0d
0%
CO03CP0140
03C SB Pipe Erection
05-Jun-27
14-Jul-27
87.0d
0%
CO03EP0140
03E SB Pipe Erection
05-Jun-27
06-Aug-27
58.0d
0%
CO03FV2110
03F Insulate - Equipment
05-Jun-27
19-Jun-27
135.0d
0%
WO030V2100
030 Insulation
05-Jun-27
02-Oct-27
133.0d
0%
CO02FV2110
02F Insulate - Equipment
07-Jun-27
24-Jun-27
200.0d
0%
CO02MM0140
02M Set (Heavy Lift) - 121-C (Ammonia Conv./ Effl Exch.)
07-Jun-27
11-Jun-27
56.0d
0%
CO03DP0130
03D LB Pipe Erection
07-Jun-27
25-Jun-27
98.0d
0%
CO01CP0130
01C LB Pipe Erection
07-Jun-27
28-Jun-27
93.0d
0%
CO02KS0120
02K Erect Misc Steel
07-Jun-27
28-Jun-27
101.0d
0%
CO01DV1130
01D Paint Touch-up - Equipment
08-Jun-27
25-Jun-27
88.0d
0%
CO03FE0130
03F Power/Control JB's, Tray, Cable, Termination
08-Jun-27
16-Jul-27
97.0d
0%
CO03FI0120
03F Instrument JB's, Field Instr, Tray, Cable
08-Jun-27
16-Jul-27
97.0d
0%
CO02KV2110
02K Insulate - Equipment
10-Jun-27
05-Jul-27
192.0d
0%
CO01BP0130
01B LB Pipe Erection
12-Jun-27
21-Sep-27
32.0d
0%
CO01DP0130
01D LB Pipe Erection
12-Jun-27
13-Aug-27
34.0d
0%
CO01HE0110
01H Lighting JB's, Stands, Tray & Cable
12-Jun-27
02-Jul-27
69.0d
0%
CO02AS0120
02A Erect Misc Steel
12-Jun-27
02-Jul-27
103.0d
0%
CO02BE0110
02B Lighting JB's, Stands, Tray & Cable
12-Jun-27
25-Jun-27
193.0d
0%
CO02EE0110
02E Lighting JB's, Stands, Tray & Cable
12-Jun-27
09-Jul-27
175.0d
0%
CO02EM0110
02E Set Static Equipment
12-Jun-27
09-Jul-27
127.0d
0%
CO02FE0110
02F Lighting JB's, Stands, Tray & Cable
12-Jun-27
09-Jul-27
175.0d
0%
CO02JE0110
02J Lighting JB's, Stands, Tray & Cable
12-Jun-27
23-Jul-27
157.0d
0%
CO02JP0130
02J LB Pipe Erection
12-Jun-27
27-Sep-27
98.0d
0%
CO02ME0110
02M Lighting JB's, Stands, Tray & Cable
12-Jun-27
09-Jul-27
175.0d
0%
CO02MV1130
02M Paint Touch-up - Equipment
12-Jun-27
29-Jun-27
172.0d
0%
CO02NM0110
02N Set (Heavy Lift) - 120-C (Ammonia Unitized Chiller)
12-Jun-27
17-Jun-27
56.0d
0%
CO03AE0130
03A Power/Control JB's, Tray, Cable, Termination
12-Jun-27
21-Jul-27
56.0d
0%
CO03AI0120
03A Instrument JB's, Field Instr, Tray, Cable
12-Jun-27
21-Jul-27
56.0d
0%
CO03BE0110
03B Lighting JB's, Stands, Tray & Cable
12-Jun-27
02-Jul-27
187.0d
0%
CO03CE0130
03C Power/Control JB's, Tray, Cable, Termination
12-Jun-27
21-Jul-27
87.0d
0%
CO03CI0120
03C Instrument JB's, Field Instr, Tray, Cable
12-Jun-27
21-Jul-27
87.0d
0%
CO03EE0130
03E Power/Control JB's, Tray, Cable, Termination
12-Jun-27
13-Aug-27
61.0d
0%
CO03EI0120
03E Instrument JB's, Field Instr, Tray, Cable
12-Jun-27
13-Aug-27
61.0d
0%
CO02BV2110
02B Insulate - Equipment
14-Jun-27
19-Jun-27
204.0d
0%
CO03CE0120
03C Lighting Fixture Installation/Termination
14-Jun-27
26-Jun-27
123.0d
0%
CO01CP0140
01C SB Pipe Erection
14-Jun-27
05-Jul-27
93.0d
0%
CO02PM0110
02P Set 101-U Dearator
15-Jun-27
28-Jun-27
103.0d
0%
CO02QM0110
02Q Set 101-F Steam Drum
15-Jun-27
21-Jun-27
101.0d
0%
CO05BC0110
05B Form, Pour, Strip Fnds - Sleepers
15-Jun-27
30-Jul-27
152.0d
0%
CO03DP0140
03D SB Pipe Erection
15-Jun-27
05-Jul-27
97.0d
0%
CO05AC0110
05A Form, Pour, Strip Fnds - Major Fnds Gen'l
17-Jun-27
07-Jul-27
77.0d
0%
CO05AU3110
05A U/G Earthing Installation
17-Jun-27
14-Jul-27
77.0d
0%
CO05UP0150
05U LB Pipe Erection (Firewater Piping)
17-Jun-27
30-Sep-27
135.0d
0%
WO050U3100
050 Install U/G Electrical
17-Jun-27
14-Jul-27
77.0d
0%
CO02NS0120
02N Erect Misc Steel
18-Jun-27
22-Jul-27
56.0d
0%
CO01BP0140
01B SB Pipe Erection
19-Jun-27
28-Sep-27
32.0d
0%
CO01CE0120
01C Lighting Fixture Installation/Termination
19-Jun-27
25-Jun-27
124.0d
0%
CO01DP0140
01D SB Pipe Erection
19-Jun-27
27-Aug-27
34.0d
0%
CO01HE0140
01H Set Transformers TR-100/ 103/ 104/ 105
19-Jun-27
02-Jul-27
33.0d
0%
CO01YE0130
01Y Power/Control JB's, Tray, Cable, Termination
19-Jun-27
30-Jul-27
39.0d
0%
CO01YI0120
01Y Instrument JB's, Field Instr, Tray, Cable
19-Jun-27
30-Jul-27
39.0d
0%
CO01YV1120
01Y Paint Touch-up - Piping
19-Jun-27
30-Jul-27
169.0d
0%
CO02DE0110
02D Lighting JB's, Stands, Tray & Cable
19-Jun-27
16-Jul-27
169.0d
0%
CO02JP0140
02J SB Pipe Erection
19-Jun-27
04-Oct-27
98.0d
0%
CO02LM0110
02L Set Static Equipment - Gen'l
19-Jun-27
21-Jul-27
103.0d
0%
CO02LM0120
02L Set Static Equipment - 02L Structure
19-Jun-27
30-Jul-27
-15.0d
0%
CO03AE0110
03A Lighting JB's, Stands, Tray & Cable
19-Jun-27
09-Jul-27
75.0d
0%
WO010I0100
010 Install Instruments & Test
19-Jun-27
03-Jan-28
53.0d
0%
CO01CE0130
01C Power/Control JB's, Tray, Cable, Termination
21-Jun-27
12-Jul-27
100.0d
0%
CO01CI0120
01C Instrument JB's, Field Instr, Tray, Cable
21-Jun-27
12-Jul-27
100.0d
0%
CO01CV1120
01C Paint Touch-up - Piping
21-Jun-27
12-Jul-27
93.0d
0%
CO01CV1130
01C Paint Touch-up - Equipment
21-Jun-27
12-Jul-27
93.0d
0%
CO02QS0120
02Q Erect Misc Steel
22-Jun-27
12-Jul-27
101.0d
0%
CO03DI0120
03D Instrument JB's, Field Instr, Tray, Cable
22-Jun-27
12-Jul-27
100.0d
0%
CO01GC0130
01G Install Paving - Control Building
25-Jun-27
08-Jul-27
70.0d
0%
CO01GE0110
01G Lighting JB's, Stands, Tray & Cable
25-Jun-27
05-Aug-27
28.0d
0%
CO01GE0140
01G Install UPS in Control Building
25-Jun-27
15-Jul-27
-8.0d
0%
CO01GI0150
01G Install DCS
25-Jun-27
25-Aug-27
-14.0d
0%
CO02AV2110
02A Insulate - Equipment
25-Jun-27
16-Jul-27
181.0d
0%
CO02DV2110
02D Insulate - Equipment
25-Jun-27
09-Jul-27
187.0d
0%
CO02NP0130
02N LB Pipe Erection
25-Jun-27
10-Nov-27
56.0d
0%
CO01BE0130
01B Power/Control JB's, Tray, Cable, Termination
26-Jun-27
05-Oct-27
32.0d
0%
CO01BI0120
01B Instrument JB's, Field Instr, Tray, Cable
26-Jun-27
05-Oct-27
32.0d
0%
CO01DE0130
01D Power/Control JB's, Tray, Cable, Termination
26-Jun-27
10-Sep-27
39.0d
0%
CO01DI0120
01D Instrument JB's, Field Instr, Tray, Cable
26-Jun-27
10-Sep-27
39.0d
0%
CO02BE0120
02B Lighting Fixture Installation/Termination
26-Jun-27
02-Jul-27
193.0d
0%
CO01BE0120
01B Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
105.0d
0%
CO01EE0120
01E Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
180.0d
0%
CO01FE0120
01F Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
152.0d
0%
CO02MP0130
02M LB Pipe Erection
28-Jun-27
08-Oct-27
92.0d
0%
CO03BP0130
03B LB Pipe Erection
28-Jun-27
04-Aug-27
138.0d
0%
CO03DE0120
03D Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
105.0d
0%
CO03EE0120
03E Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
105.0d
0%
CO03FE0120
03F Lighting Fixture Installation/Termination
28-Jun-27
17-Jul-27
111.0d
0%
CO03FP0150
03F Punchlist / Test Piping
28-Jun-27
16-Jul-27
88.0d
0%
CO02KE0110
02K Lighting JB's, Stands, Tray & Cable
28-Jun-27
09-Aug-27
144.0d
0%
CO02PS0120
02P Erect Misc Steel
29-Jun-27
26-Jul-27
103.0d
0%
CO02QP0130
02Q LB Pipe Erection
29-Jun-27
28-Sep-27
101.0d
0%
CO02YE0110
02Y Lighting JB's, Stands, Tray & Cable
29-Jun-27
12-Oct-27
90.0d
0%
CO03YV2120
03Y Insulate - Piping
30-Jun-27
03-Sep-27
148.0d
0%
CO01BV2110
01B Insulate - Equipment
01-Jul-27
23-Jul-27
100.0d
0%
WO010V2100
010 Insulation
01-Jul-27
02-Nov-27
107.0d
0%
CO01CP0150
01C Punchlist / Test Piping
01-Jul-27
12-Jul-27
96.0d
0%
CO02JE0130
02J Power/Control JB's, Tray, Cable, Termination
02-Jul-27
11-Oct-27
98.0d
0%
CO02JI0120
02J Instrument JB's, Field Instr, Tray, Cable
02-Jul-27
11-Oct-27
98.0d
0%
CO03AP0150
03A Punchlist / Test Piping
02-Jul-27
21-Jul-27
62.0d
0%
CO03CP0150
03C Punchlist / Test Piping
02-Jul-27
21-Jul-27
87.0d
0%
CO03DP0150
03D Punchlist / Test Piping
02-Jul-27
12-Jul-27
97.0d
0%
CO01HE0120
01H Lighting Fixture Installation/Termination
03-Jul-27
16-Jul-27
69.0d
0%
CO01HE0130
01H Power/Control JB's, Tray, Cable, Termination
03-Jul-27
10-Sep-27
33.0d
0%
CO01YE0120
01Y Lighting Fixture Installation/Termination
03-Jul-27
23-Jul-27
175.0d
0%
CO01YP0150
01Y Punchlist / Test Piping - Pipe Rack
03-Jul-27
30-Jul-27
133.0d
0%
CO02AE0110
02A Lighting JB's, Stands, Tray & Cable
03-Jul-27
30-Jul-27
157.0d
0%
CO02EV1130
02E Paint Touch-up - Equipment
03-Jul-27
23-Jul-27
151.0d
0%
CO03BE0120
03B Lighting Fixture Installation/Termination
03-Jul-27
09-Jul-27
187.0d
0%
CO02FP0130
02F LB Pipe Erection
05-Jul-27
27-Sep-27
102.0d
0%
CO03BP0140
03B SB Pipe Erection
05-Jul-27
11-Aug-27
138.0d
0%
CO01DV2110
01D Insulate - Equipment
06-Jul-27
23-Jul-27
88.0d
0%
CO02GE0110
02G Lighting JB's, Stands, Tray & Cable
06-Jul-27
18-Aug-27
149.0d
0%
CO02PP0130
02P LB Pipe Erection
06-Jul-27
21-Sep-27
103.0d
0%
CO03FV1120
03F Paint Touch-up - Piping
06-Jul-27
16-Jul-27
112.0d
0%
CO03DV1120
03D Paint Touch-up - Piping
06-Jul-27
12-Jul-27
111.0d
0%
CO01CV2120
01C Insulate - Piping
08-Jul-27
29-Jul-27
96.0d
0%
CO05AS0110
05A Erect Structural Steel - Structure
09-Jul-27
21-Jul-27
23.0d
0%
WO050S0100
050 Erect Steel
09-Jul-27
13-Aug-27
23.0d
0%
CO02EE0120
02E Lighting Fixture Installation/Termination
10-Jul-27
23-Jul-27
175.0d
0%
CO02FE0120
02F Lighting Fixture Installation/Termination
10-Jul-27
23-Jul-27
175.0d
0%
CO02ME0120
02M Lighting Fixture Installation/Termination
10-Jul-27
23-Jul-27
175.0d
0%
CO02MV2110
02M Insulate - Equipment
10-Jul-27
27-Jul-27
172.0d
0%
CO03AE0120
03A Lighting Fixture Installation/Termination
10-Jul-27
16-Jul-27
75.0d
0%
CO03AV1120
03A Paint Touch-up - Piping
10-Jul-27
21-Jul-27
58.0d
0%
CO03AV1130
03A Paint Touch-up - Equipment
10-Jul-27
21-Jul-27
58.0d
0%
CO03CV1120
03C Paint Touch-up - Piping
10-Jul-27
21-Jul-27
102.0d
0%
CO02DP0130
02D LB Pipe Erection
12-Jul-27
22-Oct-27
62.0d
0%
CO02FP0140
02F SB Pipe Erection
12-Jul-27
04-Oct-27
102.0d
0%
CO03BE0130
03B Power/Control JB's, Tray, Cable, Termination
12-Jul-27
23-Aug-27
138.0d
0%
CO03BI0120
03B Instrument JB's, Field Instr, Tray, Cable
12-Jul-27
23-Aug-27
138.0d
0%
CO01CI0130
01C Install In Line Instruments
12-Jul-27
15-Jul-27
96.0d
0%
CO01CV2110
01C Insulate - Equipment
12-Jul-27
02-Aug-27
93.0d
0%
CO02KP0130
02K LB Pipe Erection
12-Jul-27
23-Oct-27
77.0d
0%
CO03DI0130
03D Install In Line Instruments
12-Jul-27
14-Jul-27
97.0d
0%
CO01AE0110
01A Lighting JB's, Stands, Tray & Cable
13-Jul-27
26-Jul-27
91.0d
0%
CO01AK0160
01A Install Liner at Evaporation Pond
13-Jul-27
18-Aug-27
54.0d
0%
CO01JC0150
01K Excavate Pond
13-Jul-27
09-Aug-27
55.0d
0%
CO02QE0110
02Q Lighting JB's, Stands, Tray & Cable
13-Jul-27
19-Jul-27
162.0d
0%
CO01DE0120
01D Lighting Fixture Installation/Termination
14-Jul-27
03-Aug-27
66.0d
0%
CO03EP0150
03E Punchlist / Test Piping
14-Jul-27
13-Aug-27
58.0d
0%
CO03AV2120
03A Insulate - Piping
16-Jul-27
30-Jul-27
63.0d
0%
CO02GP0150
02G Punchlist / Test Piping
16-Jul-27
02-Oct-27
105.0d
0%
CO02DE0120
02D Lighting Fixture Installation/Termination
17-Jul-27
30-Jul-27
169.0d
0%
CO02LE0120
02L Lighting Fixture Installation/Termination
17-Jul-27
06-Aug-27
163.0d
0%
CO02LP0130
02L LB Pipe Erection
17-Jul-27
31-Jan-28
-15.0d
0%
CO02LV1130
02L Paint Touch-up - Equipment
17-Jul-27
28-Sep-27
69.0d
0%
CO03FI0130
03F Install In Line Instruments
17-Jul-27
20-Jul-27
97.0d
0%
CO01ET0110
01E Mechanical Completion
17-Jul-27
17-Jul-27
180.0d
0%
CO01FT0110
01F Mechanical Completion
17-Jul-27
17-Jul-27
152.0d
0%
SC01ET0120
01E RFSU
17-Jul-27
17-Jul-27
239.0d
0%
SC01FT0120
01F RFSU
17-Jul-27
17-Jul-27
239.0d
0%
CO02AP0130
02A LB Pipe Erection
19-Jul-27
23-Oct-27
78.0d
0%
CO02BP0130
02B LB Pipe Erection
19-Jul-27
16-Aug-27
120.0d
0%
CO02KP0140
02K SB Pipe Erection
19-Jul-27
30-Oct-27
77.0d
0%
CO02QE0120
02Q Lighting Fixture Installation/Termination
20-Jul-27
26-Jul-27
173.0d
0%
CO02YE0130
02Y Power/Control JB's, Tray, Cable, Termination
20-Jul-27
16-Nov-27
-35.0d
0%
CO02YI0120
02Y Instrument JB's, Field Instr, Tray, Cable
20-Jul-27
16-Nov-27
-35.0d
0%
CO02FE0130
02F Power/Control JB's, Tray, Cable, Termination
22-Jul-27
11-Oct-27
104.0d
0%
CO02FI0120
02F Instrument JB's, Field Instr, Tray, Cable
22-Jul-27
11-Oct-27
104.0d
0%
CO03AI0130
03A Install In Line Instruments
22-Jul-27
24-Jul-27
62.0d
0%
CO03AV2110
03A Insulate - Equipment
22-Jul-27
05-Aug-27
58.0d
0%
CO03CI0130
03C Install In Line Instruments
22-Jul-27
24-Jul-27
87.0d
0%
CO02NE0110
02N Lighting JB's, Stands, Tray & Cable
23-Jul-27
12-Aug-27
152.0d
0%
CO02NV1130
02N Paint Touch-up - Equipment
23-Jul-27
29-Jul-27
146.0d
0%
CO02JE0120
02J Lighting Fixture Installation/Termination
24-Jul-27
13-Aug-27
157.0d
0%
CO02LP0140
02L SB Pipe Erection
24-Jul-27
07-Feb-28
-15.0d
0%
CO03YI0130
03Y Install In Line Instruments
24-Jul-27
27-Aug-27
139.0d
0%
CO02HM0275
02H Complete Primary Reformer Erection (101-B)
24-Jul-27
24-Jul-27
174.0d
0%
CO02AP0140
02A SB Pipe Erection
26-Jul-27
30-Oct-27
78.0d
0%
CO01AE0120
01A Lighting Fixture Installation/Termination
27-Jul-27
02-Aug-27
91.0d
0%
CO02HP0130
02H LB Pipe Erection
27-Jul-27
05-Jan-28
10.0d
0%
CO02MP0140
02M SB Pipe Erection
27-Jul-27
15-Oct-27
92.0d
0%
CO02PE0110
02P Lighting JB's, Stands, Tray & Cable
27-Jul-27
02-Aug-27
150.0d
0%
CO02YV1120
02Y Paint Touch-up - Piping
27-Jul-27
09-Nov-27
101.0d
0%
CO02YV1130
02Y Paint Touch-up - Pipe Rack
27-Jul-27
09-Nov-27
101.0d
0%
CO03EV1120
03E Paint Touch-up - Piping
27-Jul-27
13-Aug-27
58.0d
0%
CO03EV1130
03E Paint Touch-up - Equipment
27-Jul-27
13-Aug-27
58.0d
0%
CO01DP0150
01D Punchlist / Test Piping
28-Jul-27
10-Sep-27
34.0d
0%
CO02CP0150
02C Punchlist / Test Piping
28-Jul-27
22-Oct-27
83.0d
0%
CO02HM0120
02H Set (Heavey Lift) - 101-C & 102-C
30-Jul-27
04-Aug-27
10.0d
0%
CO03FV2120
03F Insulate - Piping
30-Jul-27
13-Aug-27
88.0d
0%
CO02GV1130
02G Paint Touch-up - Equipment
30-Jul-27
25-Sep-27
116.0d
0%
CO02KE0130
02K Power/Control JB's, Tray, Cable, Termination
30-Jul-27
06-Nov-27
77.0d
0%
CO02KI0120
02K Instrument JB's, Field Instr, Tray, Cable
30-Jul-27
06-Nov-27
77.0d
0%
CO01YI0130
01Y Install In Line Instruments
31-Jul-27
27-Aug-27
139.0d
0%
CO01YV2120
01Y Insulate - Piping
31-Jul-27
02-Oct-27
133.0d
0%
CO02AE0120
02A Lighting Fixture Installation/Termination
31-Jul-27
13-Aug-27
157.0d
0%
CO02EV2110
02E Insulate - Equipment
31-Jul-27
27-Aug-27
151.0d
0%
CO03BP0150
03B Punchlist / Test Piping
31-Jul-27
23-Aug-27
138.0d
0%
CO05BP0130
05B LB Pipe Erection - To Loading Arm
31-Jul-27
21-Sep-27
152.0d
0%
WO050P0100
050 Above Ground Pipe
31-Jul-27
14-Mar-28
19.0d
0%
CO05BM0110
05B Install Loading Arm
02-Aug-27
04-Dec-27
62.0d
0%
WO050M0100
050 Major Equipment
02-Aug-27
04-Dec-27
61.0d
0%
CO02CE0110
02C Lighting JB's, Stands, Tray & Cable
03-Aug-27
05-Oct-27
113.0d
0%
CO02GE0120
02G Lighting Fixture Installation/Termination
03-Aug-27
01-Sep-27
149.0d
0%
CO02HP0140
02H SB Pipe Erection
03-Aug-27
12-Jan-28
10.0d
0%
CO02PE0120
02P Lighting Fixture Installation/Termination
03-Aug-27
09-Aug-27
161.0d
0%
CO01BP0150
01B Punchlist / Test Piping
05-Aug-27
05-Oct-27
32.0d
0%
CO020M0130
Demobilize Heavy Lift Crane
05-Aug-27
16-Aug-27
56.0d
0%
CO02HS0110
02H Erect Structural Steel - Structure
05-Aug-27
07-Oct-27
10.0d
0%
CO01GE0120
01G Lighting Fixture Installation/Termination
06-Aug-27
08-Sep-27
28.0d
0%
CO02GV1120
02G Paint Touch-up - Piping
06-Aug-27
02-Oct-27
134.0d
0%
CO05AS0120
05A Erect Misc Steel
06-Aug-27
13-Aug-27
23.0d
0%
CO02AE0130
02A Power/Control JB's, Tray, Cable, Termination
07-Aug-27
06-Nov-27
78.0d
0%
CO02AI0120
02A Instrument JB's, Field Instr, Tray, Cable
07-Aug-27
06-Nov-27
78.0d
0%
CO02ME0130
02M Power/Control JB's, Tray, Cable, Termination
07-Aug-27
22-Oct-27
95.0d
0%
CO02MI0120
02M Instrument JB's, Field Instr, Tray, Cable
07-Aug-27
22-Oct-27
95.0d
0%
CO03BV1120
03B Paint Touch-up - Piping
07-Aug-27
23-Aug-27
153.0d
0%
CO05BP0140
05B SB Pipe Erection - To Loading Arm
07-Aug-27
28-Sep-27
152.0d
0%
CO02BP0140
02B SB Pipe Erection
09-Aug-27
30-Aug-27
120.0d
0%
CO02JP0150
02J Punchlist / Test Piping
09-Aug-27
11-Oct-27
102.0d
0%
CO02KE0120
02K Lighting Fixture Installation/Termination
09-Aug-27
21-Sep-27
144.0d
0%
CO01DV1120
01D Paint Touch-up - Piping
10-Aug-27
10-Sep-27
45.0d
0%
CO02YP0150
02Y Punchlist / Test Piping
10-Aug-27
09-Nov-27
65.0d
0%
CO02LE0130
02L Power/Control JB's, Tray, Cable, Termination
11-Aug-27
14-Feb-28
-12.0d
0%
CO02LI0120
02L Instrument JB's, Field Instr, Tray, Cable
11-Aug-27
14-Feb-28
-12.0d
0%
CO02NE0120
02N Lighting Fixture Installation/Termination
13-Aug-27
25-Aug-27
152.0d
0%
CO02NV2110
02N Insulate - Equipment
13-Aug-27
08-Sep-27
146.0d
0%
CO02EP0140
02E SB Pipe Erection
16-Aug-27
13-Nov-27
67.0d
0%
CO02LV2110
02L Insulate - Equipment
16-Aug-27
26-Oct-27
69.0d
0%
CO03EI0130
03E Install In Line Instruments
16-Aug-27
25-Aug-27
65.0d
0%
CO01AM0150
01A Install Spray Devices
20-Aug-27
01-Sep-27
54.0d
0%
CO03EV2110
03E Insulate - Equipment
20-Aug-27
02-Oct-27
58.0d
0%
CO03EV2120
03E Insulate - Piping
20-Aug-27
02-Oct-27
58.0d
0%
CO02HE0130
02H Power/Control JB's, Tray, Cable, Termination
23-Aug-27
19-Jan-28
15.0d
0%
CO02HI0120
02H Instrument JB's, Field Instr, Tray, Cable
23-Aug-27
19-Jan-28
15.0d
0%
CO02FP0150
02F Punchlist / Test Piping
25-Aug-27
11-Oct-27
102.0d
0%
CO03BI0130
03B Install In Line Instruments
25-Aug-27
30-Aug-27
138.0d
0%
CO01BV1120
01B Paint Touch-up - Piping
30-Aug-27
05-Oct-27
56.0d
0%
CO02BE0130
02B Power/Control JB's, Tray, Cable, Termination
30-Aug-27
20-Sep-27
136.0d
0%
CO02BI0120
02B Instrument JB's, Field Instr, Tray, Cable
30-Aug-27
20-Sep-27
136.0d
0%
CO02PP0140
02P SB Pipe Erection
30-Aug-27
28-Sep-27
103.0d
0%
CO02BP0150
02B Punchlist / Test Piping
01-Sep-27
20-Sep-27
120.0d
0%
CO02BV1120
02B Paint Touch-up - Piping
01-Sep-27
20-Sep-27
144.0d
0%
CO02CV1120
02C Paint Touch-up - Piping
01-Sep-27
22-Oct-27
116.0d
0%
CO01AE0130
01A Power/Control JB's, Tray, Cable, Termination
03-Sep-27
21-Sep-27
66.0d
0%
CO01AP0130
01A LB Pipe Erection
03-Sep-27
28-Sep-27
54.0d
0%
CO02GV2120
02G Insulate - Piping
03-Sep-27
30-Oct-27
110.0d
0%
CO02JV1120
02J Paint Touch-up - Piping
06-Sep-27
11-Oct-27
102.0d
0%
CO02JV1130
02J Paint Touch-up - Equipment
06-Sep-27
11-Oct-27
102.0d
0%
CO02EE0130
02E Power/Control JB's, Tray, Cable, Termination
08-Sep-27
26-Nov-27
67.0d
0%
CO02EI0120
02E Instrument JB's, Field Instr, Tray, Cable
08-Sep-27
26-Nov-27
67.0d
0%
CO02HV1130
02H Paint Touch-up - Equipment
10-Sep-27
28-Oct-27
52.0d
0%
CO02GV2110
02G Insulate - Equipment
10-Sep-27
23-Oct-27
116.0d
0%
CO01HT0110
01H Mechanical Completion
10-Sep-27
10-Sep-27
33.0d
0%
CO01DI0130
01D Install In Line Instruments
20-Sep-27
24-Sep-27
41.0d
0%
CO02QP0140
02Q SB Pipe Erection
20-Sep-27
05-Oct-27
101.0d
0%
CO02BI0130
02B Install In Line Instruments
21-Sep-27
22-Sep-27
130.0d
0%
CO02PI0120
02P Instrument JB's, Field Instr, Tray, Cable
21-Sep-27
05-Oct-27
121.0d
0%
CO05BA0110
05B Erect Dock Control Operating Building
21-Sep-27
19-Oct-27
135.0d
0%
WO050A0100
050 Buildings
21-Sep-27
19-Oct-27
135.0d
0%
CO01DV2120
01D Insulate - Piping
23-Sep-27
16-Oct-27
34.0d
0%
CO02FV1120
02F Paint Touch-up - Piping
23-Sep-27
11-Oct-27
126.0d
0%
CO02HE0110
02H Lighting JB's, Stands, Tray & Cable
24-Sep-27
04-Nov-27
87.0d
0%
CO02MP0150
02M Punchlist / Test Piping
24-Sep-27
22-Oct-27
92.0d
0%
CO05BV1120
05B Paint Touch-up - Piping
27-Sep-27
05-Oct-27
170.0d
0%
CO02KP0150
02K Punchlist / Test Piping
27-Sep-27
06-Nov-27
80.0d
0%
CO02PP0150
02P Punchlist / Test Piping
28-Sep-27
05-Oct-27
107.0d
0%
CO02QI0120
02Q Instrument JB's, Field Instr, Tray, Cable
28-Sep-27
12-Oct-27
115.0d
0%
CO01AI0120
01A Instrument JB's, Field Instr, Tray, Cable
29-Sep-27
05-Oct-27
54.0d
0%
CO01AP0150
01A Punchlist / Test Piping
29-Sep-27
01-Oct-27
57.0d
0%
CO01AV1120
01A Paint Touch-up - Piping
29-Sep-27
01-Oct-27
58.0d
0%
CO02CV2120
02C Insulate - Piping
29-Sep-27
25-Nov-27
92.0d
0%
CO02PV1130
02P Paint Touch-up - Equipment
29-Sep-27
02-Oct-27
103.0d
0%
CO02YV2120
02Y Insulate - Piping
29-Sep-27
27-Dec-27
65.0d
0%
CO02DP0140
02D SB Pipe Erection
30-Sep-27
25-Nov-27
62.0d
0%
CO02AP0150
02A Punchlist / Test Piping
01-Oct-27
06-Nov-27
79.0d
0%
CO02PV1120
02P Paint Touch-up - Piping
01-Oct-27
05-Oct-27
125.0d
0%
CO01AI0130
01A Install In Line Instruments
02-Oct-27
02-Oct-27
57.0d
0%
CO01BV2120
01B Insulate - Piping
02-Oct-27
02-Nov-27
32.0d
0%
CO02GI0130
02G Install In Line Instruments
02-Oct-27
13-Oct-27
105.0d
0%
CO02QP0150
02Q Punchlist / Test Piping
05-Oct-27
12-Oct-27
101.0d
0%
CO04AT0110
04A Mechanical Completion
05-Oct-27
05-Oct-27
108.0d
0%
CO01BI0130
01B Install In Line Instruments
06-Oct-27
13-Oct-27
37.0d
0%
CO01GI0120
01G DCS Cable Terminations
06-Oct-27
06-Dec-27
-35.0d
0%
CO02CE0120
02C Lighting Fixture Installation/Termination
06-Oct-27
26-Oct-27
113.0d
0%
CO02JV2120
02J Insulate - Piping
06-Oct-27
08-Nov-27
102.0d
0%
CO02MV1120
02M Paint Touch-up - Piping
06-Oct-27
22-Oct-27
116.0d
0%
CO02PI0130
02P Install In Line Instruments
06-Oct-27
06-Oct-27
118.0d
0%
CO02QV1120
02Q Paint Touch-up - Piping
06-Oct-27
09-Oct-27
121.0d
0%
CO02QV1130
02Q Paint Touch-up - Equipment
06-Oct-27
09-Oct-27
121.0d
0%
CO02DE0130
02D Power/Control JB's, Tray, Cable, Termination
11-Oct-27
02-Dec-27
68.0d
0%
CO02DI0120
02D Instrument JB's, Field Instr, Tray, Cable
11-Oct-27
02-Dec-27
68.0d
0%
CO02QV2110
02Q Insulate - Equipment
11-Oct-27
16-Oct-27
121.0d
0%
CO02BV2120
02B Insulate - Piping
12-Oct-27
18-Oct-27
120.0d
0%
CO02FI0130
02F Install In Line Instruments
12-Oct-27
16-Oct-27
109.0d
0%
CO02JI0130
02J Install In Line Instruments
12-Oct-27
19-Oct-27
104.0d
0%
CO02QI0130
02Q Install In Line Instruments
13-Oct-27
13-Oct-27
112.0d
0%
CO02YE0120
02Y Lighting Fixture Installation/Termination
13-Oct-27
27-Nov-27
90.0d
0%
CO02KV1120
02K Paint Touch-up - Piping
13-Oct-27
06-Nov-27
104.0d
0%
CO02FV2120
02F Insulate - Piping
14-Oct-27
08-Nov-27
102.0d
0%
CO02JV2110
02J Insulate - Equipment
14-Oct-27
08-Nov-27
102.0d
0%
CO02AV1120
02A Paint Touch-up - Piping
16-Oct-27
06-Nov-27
103.0d
0%
CO02HV2110
02H Insulate - Equipment
16-Oct-27
01-Dec-27
52.0d
0%
SC01HT0120
01H RFSU
17-Oct-27
17-Oct-27
10.0d
0%
CO02EP0150
02E Punchlist / Test Piping
18-Oct-27
26-Nov-27
67.0d
0%
CO05BE0130
05B Power/Control JB's, Tray, Cable, Termination
19-Oct-27
30-Oct-27
140.0d
0%
CO05BI0120
05B Instrument JB's, Field Instr, Tray, Cable
19-Oct-27
30-Oct-27
140.0d
0%
WO050E0100
050 Above Ground Electrical
19-Oct-27
06-Apr-28
8.0d
0%
WO050I0100
050 Install Instruments & Test
19-Oct-27
25-Mar-28
24.0d
0%
CO02CI0130
02C Install In Line Instruments
23-Oct-27
04-Nov-27
83.0d
0%
CO02MI0130
02M Install In Line Instruments
23-Oct-27
28-Oct-27
99.0d
0%
CO02PV2120
02P Insulate - Piping
27-Oct-27
02-Nov-27
107.0d
0%
CO02MV2120
02M Insulate - Piping
28-Oct-27
25-Nov-27
92.0d
0%
CO05AM0110
05A Set 2202-B Flare & KO Drum
28-Oct-27
04-Dec-27
21.0d
0%
CO05AM0130
05A Set 2101-L Ammonia Refrigeration Package
28-Oct-27
30-Oct-27
46.0d
0%
CO05AM0150
05A Set Rotating Equipment
28-Oct-27
17-Nov-27
31.0d
0%
CO010K0130
010 Compl Roads, Ditches, Paving, & Rock Surfacing
01-Nov-27
28-Jan-28
9.0d
0%
CO010K0140
010 Finish Grading
01-Nov-27
28-Jan-28
37.0d
0%
CO020K0100
020 Site Prep - Guard Posts & Gravel
01-Nov-27
01-Mar-28
9.0d
0%
CO02EV1120
02E Paint Touch-up - Piping
01-Nov-27
26-Nov-27
91.0d
0%
CO02PV2110
02P Insulate - Equipment
01-Nov-27
06-Nov-27
103.0d
0%
CO030K0100
030 Site Prep - Guard Posts & Gravel
01-Nov-27
01-Mar-28
9.0d
0%
WO020K0100
020 Site Prep
01-Nov-27
01-Mar-28
9.0d
0%
WO030K0100
030 Site Prep
01-Nov-27
01-Mar-28
9.0d
0%
CO02DP0150
02D Punchlist / Test Piping
02-Nov-27
02-Dec-27
62.0d
0%
CO02KV2120
02K Insulate - Piping
02-Nov-27
10-Dec-27
80.0d
0%
SC04AT0120
04A RFSU
02-Nov-27
02-Nov-27
132.0d
0%
CO02QV2120
02Q Insulate - Piping
03-Nov-27
09-Nov-27
101.0d
0%
CO05AP0130
05A LB Pipe Erection
04-Nov-27
29-Feb-28
-29.0d
0%
CO02AV2120
02A Insulate - Piping
05-Nov-27
10-Dec-27
79.0d
0%
CO02HE0120
02H Lighting Fixture Installation/Termination
05-Nov-27
01-Dec-27
87.0d
0%
CO02KI0130
02K Install In Line Instruments
06-Nov-27
15-Nov-27
83.0d
0%
CO02AI0130
02A Install In Line Instruments
08-Nov-27
13-Nov-27
84.0d
0%
CO02NP0140
02N SB Pipe Erection
08-Nov-27
17-Nov-27
56.0d
0%
CO02YI0130
02Y Install In Line Instruments
10-Nov-27
13-Dec-27
65.0d
0%
CO02HP0150
02H Punchlist / Test Piping
11-Nov-27
19-Jan-28
10.0d
0%
CO05AP0140
05A SB Pipe Erection
11-Nov-27
07-Mar-28
-29.0d
0%
CO02DV1120
02D Paint Touch-up - Piping
12-Nov-27
02-Dec-27
86.0d
0%
CO02NE0130
02N Power/Control JB's, Tray, Cable, Termination
15-Nov-27
30-Nov-27
80.0d
0%
CO02NI0120
02N Instrument JB's, Field Instr, Tray, Cable
15-Nov-27
30-Nov-27
80.0d
0%
CO02LP0150
02L Punchlist / Test Piping
16-Nov-27
14-Feb-28
-15.0d
0%
CO02NV1120
02N Paint Touch-up - Piping
18-Nov-27
30-Nov-27
88.0d
0%
CO05AE0130
05A Power/Control JB's, Tray, Cable, Termination
18-Nov-27
14-Mar-28
-25.0d
0%
CO05AI0120
05A Instrument JB's, Field Instr, Tray, Cable
18-Nov-27
14-Mar-28
-25.0d
0%
CO02NP0150
02N Punchlist / Test Piping
26-Nov-27
30-Nov-27
56.0d
0%
CO02EI0130
02E Install In Line Instruments
27-Nov-27
03-Dec-27
73.0d
0%
CO02EV2120
02E Insulate - Piping
27-Nov-27
24-Dec-27
67.0d
0%
CO02NI0130
02N Install In Line Instruments
01-Dec-27
01-Dec-27
75.0d
0%
CO02DI0130
02D Install In Line Instruments
03-Dec-27
07-Dec-27
70.0d
0%
CO01GT0110
01G Mechanical Completion
06-Dec-27
06-Dec-27
-35.0d
0%
SC01GT0120
01G RFSU
06-Dec-27
06-Dec-27
-47.0d
0%
CO01DI0140
01D Continuity Testing
07-Dec-27
11-Dec-27
-22.0d
0%
CO02GI0140
02G Continuity Testing
07-Dec-27
16-Dec-27
54.0d
0%
CO02YI0140
02Y Continuity Testing
07-Dec-27
03-Jan-28
53.0d
0%
CO03AI0140
03A Continuity Testing
07-Dec-27
09-Dec-27
-35.0d
0%
CO03YI0140
03Y Continuity Testing
07-Dec-27
17-Jan-28
41.0d
0%
CO05BI0140
05B Continuity Testing
07-Dec-27
07-Dec-27
118.0d
0%
SC02GI0150
02G Function Testing
07-Dec-27
09-Jan-28
63.0d
0%
WC000T1100
000 Commissioning
07-Dec-27
22-Sep-28
-59.0d
0%
CO03AT0110
03A Mechanical Completion
09-Dec-27
09-Dec-27
-26.0d
0%
CO02DV2120
02D Insulate - Piping
10-Dec-27
30-Dec-27
62.0d
0%
CO02HV1120
02H Paint Touch-up - Piping
10-Dec-27
19-Jan-28
45.0d
0%
CO03FI0140
03F Continuity Testing
10-Dec-27
13-Dec-27
-1.0d
0%
SC03AI0150
03A Function Testing
10-Dec-27
20-Dec-27
-47.0d
0%
CO01DT0110
01D Mechanical Completion
11-Dec-27
11-Dec-27
-22.0d
0%
SC01DI0150
01D Function Testing
12-Dec-27
29-Dec-27
-28.0d
0%
CO03FT0110
03F Mechanical Completion
13-Dec-27
13-Dec-27
8.0d
0%
CO01YI0140
01Y Continuity Testing
14-Dec-27
03-Jan-28
53.0d
0%
CO02AI0140
02A Continuity Testing
14-Dec-27
20-Dec-27
52.0d
0%
CO02BI0140
02B Continuity Testing
14-Dec-27
15-Dec-27
73.0d
0%
SC03FI0150
03F Function Testing
14-Dec-27
24-Dec-27
-2.0d
0%
CO02KI0140
02K Continuity Testing
15-Dec-27
22-Dec-27
48.0d
0%
CO02BT0110
02B Mechanical Completion
15-Dec-27
15-Dec-27
75.0d
0%
CO02DI0140
02D Continuity Testing
16-Dec-27
20-Dec-27
59.0d
0%
SC02BI0150
02B Function Testing
16-Dec-27
18-Dec-27
85.0d
0%
CO02GT0110
02G Mechanical Completion
16-Dec-27
16-Dec-27
74.0d
0%
CO02CI0140
02C Continuity Testing
17-Dec-27
29-Dec-27
41.0d
0%
SC02CI0150
02C Function Testing
17-Dec-27
24-Jan-28
48.0d
0%
SC02YI0150
02Y Function Testing
18-Dec-27
10-Jan-28
62.0d
0%
SC02BT0120
02B RFSU
18-Dec-27
18-Dec-27
85.0d
0%
CO02AT0110
02A Mechanical Completion
20-Dec-27
20-Dec-27
71.0d
0%
CO02DT0110
02D Mechanical Completion
20-Dec-27
20-Dec-27
71.0d
0%
SC03AT0120
03A RFSU
20-Dec-27
20-Dec-27
-47.0d
0%
CO01BI0140
01B Continuity Testing
21-Dec-27
28-Dec-27
-29.0d
0%
CO01CI0140
01C Continuity Testing
21-Dec-27
23-Dec-27
-12.0d
0%
CO02EI0140
02E Continuity Testing
21-Dec-27
27-Dec-27
47.0d
0%
CO02JI0140
02J Continuity Testing
21-Dec-27
28-Dec-27
42.0d
0%
CO02MI0140
02M Continuity Testing
21-Dec-27
25-Dec-27
51.0d
0%
CO03BI0140
03B Continuity Testing
21-Dec-27
23-Dec-27
59.0d
0%
SC02AI0150
02A Function Testing
21-Dec-27
12-Jan-28
60.0d
0%
SC02DI0150
02D Function Testing
21-Dec-27
04-Jan-28
68.0d
0%
SC03AT0130
03A Commission
21-Dec-27
27-Dec-27
-47.0d
0%
CO02NI0140
02N Continuity Testing
22-Dec-27
22-Dec-27
67.0d
0%
CO02KT0110
02K Mechanical Completion
22-Dec-27
22-Dec-27
69.0d
0%
CO02NT0110
02N Mechanical Completion
22-Dec-27
22-Dec-27
69.0d
0%
CO02PI0140
02P Continuity Testing
23-Dec-27
23-Dec-27
64.0d
0%
SC02KI0150
02K Function Testing
23-Dec-27
16-Jan-28
56.0d
0%
SC02NI0150
02N Function Testing
23-Dec-27
25-Dec-27
78.0d
0%
CO01CT0110
01C Mechanical Completion
23-Dec-27
23-Dec-27
-7.0d
0%
CO02PT0110
02P Mechanical Completion
23-Dec-27
23-Dec-27
68.0d
0%
CO03BT0110
03B Mechanical Completion
23-Dec-27
23-Dec-27
68.0d
0%
CO02HV2120
02H Insulate - Piping
24-Dec-27
16-Feb-28
21.0d
0%
CO02NV2120
02N Insulate - Piping
24-Dec-27
06-Jan-28
56.0d
0%
CO02QI0140
02Q Continuity Testing
24-Dec-27
24-Dec-27
63.0d
0%
CO03CI0140
03C Continuity Testing
24-Dec-27
27-Dec-27
-19.0d
0%
SC01CI0150
01C Function Testing
24-Dec-27
29-Dec-27
-14.0d
0%
SC01YI0150
01Y Function Testing
24-Dec-27
10-Jan-28
62.0d
0%
SC02PI0150
02P Function Testing
24-Dec-27
28-Dec-27
75.0d
0%
SC03BI0150
03B Function Testing
24-Dec-27
03-Jan-28
69.0d
0%
CO02QT0110
02Q Mechanical Completion
24-Dec-27
24-Dec-27
67.0d
0%
SC03FT0120
03F RFSU
24-Dec-27
24-Dec-27
-2.0d
0%
CO02LV1120
02L Paint Touch-up - Piping
25-Dec-27
14-Feb-28
23.0d
0%
SC02QI0150
02Q Function Testing
25-Dec-27
29-Dec-27
74.0d
0%
CO02MT0110
02M Mechanical Completion
25-Dec-27
25-Dec-27
66.0d
0%
SC02MI0150
02M Function Testing
26-Dec-27
12-Jan-28
60.0d
0%
CO02ET0110
02E Mechanical Completion
27-Dec-27
27-Dec-27
65.0d
0%
CO03CT0110
03C Mechanical Completion
27-Dec-27
27-Dec-27
-10.0d
0%
CO01AI0140
01A Continuity Testing
28-Dec-27
28-Dec-27
-12.0d
0%
CO02FI0140
02F Continuity Testing
28-Dec-27
01-Jan-28
44.0d
0%
CO03DI0140
03D Continuity Testing
28-Dec-27
29-Dec-27
-17.0d
0%
SC01DT0130
01D Commission
28-Dec-27
07-Feb-28
-47.0d
0%
SC02EI0150
02E Function Testing
28-Dec-27
17-Jan-28
55.0d
0%
SC03CI0150
03C Function Testing
28-Dec-27
07-Jan-28
-23.0d
0%
CO01AT0110
01A Mechanical Completion
28-Dec-27
28-Dec-27
-12.0d
0%
CO01BT0110
01B Mechanical Completion
28-Dec-27
28-Dec-27
-11.0d
0%
CO02JT0110
02J Mechanical Completion
28-Dec-27
28-Dec-27
64.0d
0%
SC02PT0120
02P RFSU
28-Dec-27
28-Dec-27
75.0d
0%
SC01AI0150
01A Function Testing
29-Dec-27
29-Dec-27
-14.0d
0%
SC01BI0150
01B Function Testing
29-Dec-27
19-Jan-28
-35.0d
0%
SC02JI0150
02J Function Testing
29-Dec-27
23-Jan-28
49.0d
0%
CO02CT0110
02C Mechanical Completion
29-Dec-27
29-Dec-27
63.0d
0%
CO03DT0110
03D Mechanical Completion
29-Dec-27
29-Dec-27
-12.0d
0%
SC01AT0120
01A RFSU
29-Dec-27
29-Dec-27
-14.0d
0%
SC01CT0120
01C RFSU
29-Dec-27
29-Dec-27
-14.0d
0%
SC01DT0120
01D RFSU
29-Dec-27
29-Dec-27
-28.0d
0%
SC02QT0120
02Q RFSU
29-Dec-27
29-Dec-27
74.0d
0%
CO03EI0140
03E Continuity Testing
30-Dec-27
04-Jan-28
-32.0d
0%
SC03DI0150
03D Function Testing
30-Dec-27
04-Jan-28
-20.0d
0%
SC03YI0150
03Y Function Testing
01-Jan-28
24-Jan-28
48.0d
0%
CO02FT0110
02F Mechanical Completion
01-Jan-28
01-Jan-28
60.0d
0%
SC02FI0150
02F Function Testing
02-Jan-28
20-Jan-28
52.0d
0%
CO01YT0110
01Y Mechanical Completion
03-Jan-28
03-Jan-28
59.0d
0%
CO02YT0110
02Y Mechanical Completion
03-Jan-28
03-Jan-28
59.0d
0%
SC03BT0120
03B RFSU
03-Jan-28
03-Jan-28
69.0d
0%
CO03ET0110
03E Mechanical Completion
04-Jan-28
04-Jan-28
-17.0d
0%
SC02DT0120
02D RFSU
04-Jan-28
04-Jan-28
68.0d
0%
SC03DT0120
03D RFSU
04-Jan-28
04-Jan-28
-20.0d
0%
CO02LV2120
02L Insulate - Piping
05-Jan-28
13-Mar-28
-1.0d
0%
SC03EI0150
03E Function Testing
05-Jan-28
22-Jan-28
-38.0d
0%
SC02NT0120
02N RFSU
06-Jan-28
06-Jan-28
66.0d
0%
SC03CT0120
03C RFSU
07-Jan-28
07-Jan-28
-23.0d
0%
CO05BP0150
05B Punchlist / Test Piping
08-Jan-28
24-Jan-28
63.0d
0%
CO05BV1130
05B Paint Touch-up - Equipment
08-Jan-28
18-Jan-28
62.0d
0%
SC02GT0120
02G RFSU
09-Jan-28
09-Jan-28
63.0d
0%
SC01YT0120
01Y RFSU
10-Jan-28
10-Jan-28
62.0d
0%
SC02YT0120
02Y RFSU
10-Jan-28
10-Jan-28
62.0d
0%
SC02AT0120
02A RFSU
12-Jan-28
12-Jan-28
60.0d
0%
SC02MT0120
02M RFSU
12-Jan-28
12-Jan-28
60.0d
0%
CO02HI0140
02H Continuity Testing
14-Jan-28
26-Jan-28
15.0d
0%
SC02KT0120
02K RFSU
16-Jan-28
16-Jan-28
56.0d
0%
CO03YT0110
03Y Mechanical Completion
17-Jan-28
17-Jan-28
47.0d
0%
SC02ET0120
02E RFSU
17-Jan-28
17-Jan-28
55.0d
0%
CO05AP0150
05A Punchlist / Test Piping
19-Jan-28
14-Mar-28
-29.0d
0%
SC01BT0120
01B RFSU
19-Jan-28
19-Jan-28
-35.0d
0%
CO02HI0130
02H Install In Line Instruments
20-Jan-28
01-Feb-28
10.0d
0%
SC02HI0150
02H Function Testing
20-Jan-28
29-Feb-28
12.0d
0%
SC02FT0120
02F RFSU
20-Jan-28
20-Jan-28
52.0d
0%
SC03ET0120
03E RFSU
22-Jan-28
22-Jan-28
-38.0d
0%
SC02JT0120
02J RFSU
23-Jan-28
23-Jan-28
49.0d
0%
CO05BI0130
05B Install In Line Instruments
24-Jan-28
25-Jan-28
68.0d
0%
CO05BT0110
05B Mechanical Completion
24-Jan-28
24-Jan-28
81.0d
0%
CO05BV2120
05B Insulate - Piping
24-Jan-28
14-Feb-28
63.0d
0%
WO050V2100
050 Insulation
24-Jan-28
10-May-28
-12.0d
0%
SC02CT0120
02C RFSU
24-Jan-28
24-Jan-28
48.0d
0%
SC03YT0120
03Y RFSU
24-Jan-28
24-Jan-28
48.0d
0%
CO05BV2110
05B Insulate - Equipment
25-Jan-28
15-Feb-28
62.0d
0%
CO02HI0145
02H Contingency (101-B)
27-Jan-28
23-Feb-28
15.0d
0%
CO02LI0140
02L Continuity Testing
05-Feb-28
21-Feb-28
-12.0d
0%
SC05BI0150
05B Function Testing
05-Feb-28
08-Feb-28
79.0d
0%
SC02LI0150
02L Function Testing
08-Feb-28
29-Mar-28
-17.0d
0%
SC03FT0130
03F Commission
08-Feb-28
28-Feb-28
-47.0d
0%
CO05AV1120
05A Paint Touch-up - Piping
10-Feb-28
14-Mar-28
-2.0d
0%
CO02LI0130
02L Install In Line Instruments
15-Feb-28
01-Mar-28
-15.0d
0%
SC05BT0120
05B RFSU
15-Feb-28
15-Feb-28
72.0d
0%
CO02LT0110
02L Mechanical Completion
21-Feb-28
21-Feb-28
17.0d
0%
CO02HT0110
02H Mechanical Completion
23-Feb-28
23-Feb-28
15.0d
0%
CO05AK0120
05A Construct Dike (Retaining Wall)
26-Feb-28
05-May-28
-47.0d
0%
CO05AK0130
05A Guard Posts, Fence, Gravel...
26-Feb-28
05-May-28
-47.0d
0%
WO050K0100
050 Site Prep
26-Feb-28
05-May-28
-47.0d
0%
CO05AV2120
05A Insulate - Piping
28-Feb-28
11-Apr-28
-26.0d
0%
CO06AV2120
05A Insulate - Piping
28-Feb-28
11-Apr-28
-26.0d
0%
SC000T0100
020 Commission ISBL
29-Feb-28
28-Apr-28
-47.0d
0%
SC02HT0120
02H RFSU
29-Feb-28
29-Feb-28
12.0d
0%
CO05AE0110
05A Lighting JB's, Stands, Tray & Cable
03-Mar-28
30-Mar-28
-22.0d
0%
CO05AI0140
05A Continuity Testing
10-Mar-28
21-Mar-28
-25.0d
0%
CO05AV1130
05A Paint Touch-up - Equipment
10-Mar-28
12-Apr-28
-51.0d
0%
CO05AI0130
05A Install In Line Instruments
15-Mar-28
25-Mar-28
-29.0d
0%
SC05AI0150
05A Function Testing
15-Mar-28
15-Apr-28
-34.0d
0%
CO05AE0120
05A Lighting Fixture Installation/Termination
24-Mar-28
06-Apr-28
-22.0d
0%
CO05AV2110
05A Insulate - Equipment
28-Mar-28
10-May-28
-51.0d
0%
CO06AV2110
05A Insulate - Equipment
28-Mar-28
10-May-28
-51.0d
0%
SC02LT0120
02L RFSU
29-Mar-28
29-Mar-28
-17.0d
0%
CO05AT0110
05A Mechanical Completion
05-May-28
05-May-28
-47.0d
0%
SC05AT0120
05A RFSU
10-May-28
10-May-28
-59.0d
0%
SC000T0105
020 Startup ISBL
11-May-28
24-Jun-28
-59.0d
0%
SC000T0110
Performance Test Period
25-Jun-28
22-Sep-28
-59.0d
0%
SC000YA100
Construction Bonus Period
23-Sep-28
15-Mar-29
-59.0d
0%