EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in PI Piping Engineering × clear
Code
Activity
Start
Finish
Flt
%
EM000PI025
Develop Piping Specs (PDS)
19-Feb-25
23-Jul-25
100%
EM000U000
Start U/G Model Reviews
16-Oct-25
16-Oct-25
100%
27-Jan 03-Feb 10-Feb 17-Feb 24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul 04-Aug 11-Aug 18-Aug 25-Aug 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct Data Date
EM000PI025 — Develop Piping Specs (PDS) | 19-Feb-25 → 23-Jul-25 | Complete 100% | float — EM000PI025 EM000U000 — Start U/G Model Reviews | 16-Oct-25 | Complete