EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 24
activities
in MD Vessels Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EM000MD42C
Prepare & Issue Prelim. RFQ - MD402 to Proc.
12-Feb-25
16-Feb-25
—
100%
EM000MD22C
Prepare & Issue Prelim. RFQ - MD202 to Proc.
26-Feb-25
28-Feb-25
—
100%
EM000MD44C
Prepare & Issue Prelim. RFQ - MD404 to Proc.
26-Feb-25
28-Feb-25
—
100%
EM000MD46C
Prepare & Issue Prelim. RFQ - MD411 to Proc.
26-Feb-25
28-Feb-25
—
100%
EM00MD45C
Prepare & Issue Prelim. RFQ - MD405 to Proc.
26-Feb-25
28-Feb-25
—
100%
EM000MD22D
Technical Evaluation - MD202
22-Mar-25
18-Apr-25
—
100%
EM000MD42D
Technical Evaluation - MD402
22-Mar-25
18-Apr-25
—
100%
EM000MD44D
Technical Evaluation - MD404
22-Mar-25
18-Apr-25
—
100%
EM000MD46D
Technical Evaluation - MD411
22-Mar-25
19-Apr-25
—
100%
EM000MD45D
Technical Evaluation - MD405
26-Mar-25
18-Apr-25
—
100%
EM000MD47F
Develop & Issue Inquiry for ERW - MD406
27-Apr-25
11-May-25
—
100%
EM000MD42E
Prepare & Issue Purchase ERW - MD402
01-May-25
04-May-25
—
100%
EM000MD44E
Prepare & Issue Purchase ERW - MD404
03-Jun-25
05-Jun-25
—
100%
EM000MD45E
Prepare & Issue Purchase ERW - MD405
03-Jun-25
05-Jun-25
—
100%
EM000MD46E
Prepare & Issue Purchase ERW - MD411
03-Jun-25
05-Jun-25
—
100%
EM000MD22E
Prepare & Issue Purchase ERW - MD202
10-Jun-25
13-Jun-25
—
100%
EM000MD47D
Technical Evaluation - MD406
02-Jul-25
06-Jul-25
—
100%
EM000MD47E
Prepare & Issue Purchase ERW - MD406
16-Aug-25
21-Aug-25
—
100%
PM000MD45N
Recv. Planning V. Data MD405
16-Aug-25
02-Sep-25
—
100%
PM000MD42N
Recv. Planning V. Data MD402
16-Aug-25
19-Oct-25
—
100%
PM000MD22N
Recv. Planning V. Data MD202
16-Aug-25
12-Nov-25
—
100%
PM000MD46N
Recv. Planning V. Data MD411
27-Aug-25
13-Sep-25
—
100%
PM000MD44N
Recv. Planning V. Data MD404
17-Sep-25
30-Sep-25
—
100%
PM000MD47N
Recv. Planning V. Data MD406
23-Sep-25
09-Oct-25
—
100%