EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 16
activities
in IC Control Sytems Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EM020IC126
Instrument Installation Details (90%) - IFC
07-Oct-25
18-Apr-26
—
100%
EM010IC123
UNIT 01 Instr. Location Plans - IFC
01-Apr-26
27-Dec-26
—
9%
EM020IC124
UNIT 02 Instr. Location Plans - IFC
01-Apr-26
27-Dec-26
—
9%
EM020IC128
Instrument Wiring Diagrams - IFC
01-Apr-26
27-Dec-26
—
9%
EM030IC125
UNIT 03 Instr. Location Plans - IFC
01-Apr-26
27-Dec-26
—
9%
EM050IC130
05B Instr. Location Plans - IFC
01-Apr-26
16-Jan-27
166.0d
8%
EK020IC133
Field Bus J-boxes Wiring Reports - IFC
27-Dec-26
27-Dec-26
—
0%
EM020IC127
Instrument Installation Details (10%) - IFC
27-Dec-26
27-Dec-26
—
0%
EM020IC129
Instrument Loop Diagrams - IFC
27-Dec-26
27-Dec-26
—
0%
EM020IC132
Traditional J-boxes Wiring Reports - IFC
27-Dec-26
27-Dec-26
—
0%
EM020IC134
DCS Marshalling Report - IFC
27-Dec-26
27-Dec-26
—
0%
EM020IC135
SIS Termination Report - IFC
27-Dec-26
27-Dec-26
—
0%
EM020IC136
ITCC Termination Report - IFC
27-Dec-26
27-Dec-26
—
0%
EM020IC137
Miscellaneous Wiring Report - IFC
27-Dec-26
27-Dec-26
—
0%
EK020IC131
Instrument Loop Diagrams FF - IFC
30-Dec-26
03-Jan-27
530.0d
0%
EM000IC100
Instrument Index - IFC
06-Jan-27
06-Jan-27
530.0d
0%