EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 8
activities
in EL Electrical Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EM000ELEH2
01,03,05 Develop & Issue Earthing / Grounding Dwgs - IFC
31-Mar-26
27-Dec-26
—
9%
EK100ELEK2
01,03,04,05 Develop & Issue Cable Ladder Plans - IFC Except 01H & 05A
27-Dec-26
27-Dec-26
—
0%
EK200ELEK2
01H Develop & Issue Cable Ladder Plans - IFC
27-Dec-26
27-Dec-26
—
0%
EM000ELEJ2
01,03,05 Develop & Issue Lighting Plans - IFC
27-Dec-26
27-Dec-26
—
0%
EM000ELEK2
01,03,04,05 Develop & Issue Power Plans - IFC
27-Dec-26
27-Dec-26
—
0%
EM000ELEL2
01,03,04,05 Electrical Routing Plans
27-Dec-26
27-Dec-26
—
0%
EM000ELEM2
Dev/Issue Elect Cable/Raceway Sched IFC
27-Dec-26
27-Dec-26
—
0%
EM000ELEN3
01,03 Equipment Interconnection Diagrams
30-Dec-26
30-Jan-27
511.0d
0%