EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 8 activities in EL Electrical Engineering × clear
Code
Activity
Start
Finish
Flt
%
EM000ELEH2
01,03,05 Develop & Issue Earthing / Grounding Dwgs - IFC
31-Mar-26
27-Dec-26
9%
EK100ELEK2
01,03,04,05 Develop & Issue Cable Ladder Plans - IFC Except 01H & 05A
27-Dec-26
27-Dec-26
0%
EK200ELEK2
01H Develop & Issue Cable Ladder Plans - IFC
27-Dec-26
27-Dec-26
0%
EM000ELEJ2
01,03,05 Develop & Issue Lighting Plans - IFC
27-Dec-26
27-Dec-26
0%
EM000ELEK2
01,03,04,05 Develop & Issue Power Plans - IFC
27-Dec-26
27-Dec-26
0%
EM000ELEL2
01,03,04,05 Electrical Routing Plans
27-Dec-26
27-Dec-26
0%
EM000ELEM2
Dev/Issue Elect Cable/Raceway Sched IFC
27-Dec-26
27-Dec-26
0%
EM000ELEN3
01,03 Equipment Interconnection Diagrams
30-Dec-26
30-Jan-27
511.0d
0%
Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Jan 2027 Data Date
EM000ELEH2 — 01,03,05 Develop & Issue Earthing / Grounding Dwgs - IFC | 31-Mar-26 → 27-Dec-26 | In Progress 9% | float — EM000ELEH2 EK100ELEK2 — 01,03,04,05 Develop & Issue Cable Ladder Plans - IFC Except 01H & 05A | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK200ELEK2 — 01H Develop & Issue Cable Ladder Plans - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM000ELEJ2 — 01,03,05 Develop & Issue Lighting Plans - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM000ELEK2 — 01,03,04,05 Develop & Issue Power Plans - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM000ELEL2 — 01,03,04,05 Electrical Routing Plans | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM000ELEM2 — Dev/Issue Elect Cable/Raceway Sched IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM000ELEN3 — 01,03 Equipment Interconnection Diagrams | 30-Dec-26 → 30-Jan-27 | Not Started 0% | float 511.0d EM000ELEN3