EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in EL Electrical Engineering × clear
Code
Activity
Start
Finish
Flt
%
EM03EEL120
03E Electrical Conceptual Layouts
01-Jul-25
01-Mar-26
100%
EM03AEL120
03A Electrical Conceptual Layouts
23-Jul-25
27-Sep-25
100%
EM03DEL120
03D Electrical Conceptual Layouts
09-Aug-25
19-Oct-25
100%
EM03BEL120
03B Electrical Conceptual Layouts
12-Aug-25
19-Oct-25
100%
EM03YEL120
03Y Electrical Conceptual Layouts
19-Aug-25
11-Oct-25
100%
EM03FEL120
03F Electrical Conceptual Layouts
19-Aug-25
23-Oct-25
100%
EM03CEL120
03C Electrical Conceptual Layouts
01-Oct-25
06-Nov-25
100%
Q3 2025 Q4 2025 Q1 2026 Data Date
EM03EEL120 — 03E Electrical Conceptual Layouts | 01-Jul-25 → 01-Mar-26 | Complete 100% | float — EM03EEL120 EM03AEL120 — 03A Electrical Conceptual Layouts | 23-Jul-25 → 27-Sep-25 | Complete 100% | float — EM03AEL120 EM03DEL120 — 03D Electrical Conceptual Layouts | 09-Aug-25 → 19-Oct-25 | Complete 100% | float — EM03DEL120 EM03BEL120 — 03B Electrical Conceptual Layouts | 12-Aug-25 → 19-Oct-25 | Complete 100% | float — EM03BEL120 EM03YEL120 — 03Y Electrical Conceptual Layouts | 19-Aug-25 → 11-Oct-25 | Complete 100% | float — EM03YEL120 EM03FEL120 — 03F Electrical Conceptual Layouts | 19-Aug-25 → 23-Oct-25 | Complete 100% | float — EM03FEL120 EM03CEL120 — 03C Electrical Conceptual Layouts | 01-Oct-25 → 06-Nov-25 | Complete 100% | float —