Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in EL Electrical Engineering × clear
Code
Activity
Start
Finish
Flt
%
EM03EEL120
03E Electrical Conceptual Layouts
01-Jul-25
01-Mar-26
100%
EM03AEL120
03A Electrical Conceptual Layouts
23-Jul-25
27-Sep-25
100%
EM03DEL120
03D Electrical Conceptual Layouts
09-Aug-25
19-Oct-25
100%
EM03BEL120
03B Electrical Conceptual Layouts
12-Aug-25
19-Oct-25
100%
EM03YEL120
03Y Electrical Conceptual Layouts
19-Aug-25
11-Oct-25
100%
EM03FEL120
03F Electrical Conceptual Layouts
19-Aug-25
23-Oct-25
100%
EM03CEL120
03C Electrical Conceptual Layouts
01-Oct-25
06-Nov-25
100%
30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar Data Date
EM03EEL120 — 03E Electrical Conceptual Layouts | 01-Jul-25 → 01-Mar-26 | Complete 100% | float — EM03EEL120 EM03AEL120 — 03A Electrical Conceptual Layouts | 23-Jul-25 → 27-Sep-25 | Complete 100% | float — EM03AEL120 EM03DEL120 — 03D Electrical Conceptual Layouts | 09-Aug-25 → 19-Oct-25 | Complete 100% | float — EM03DEL120 EM03BEL120 — 03B Electrical Conceptual Layouts | 12-Aug-25 → 19-Oct-25 | Complete 100% | float — EM03BEL120 EM03YEL120 — 03Y Electrical Conceptual Layouts | 19-Aug-25 → 11-Oct-25 | Complete 100% | float — EM03YEL120 EM03FEL120 — 03F Electrical Conceptual Layouts | 19-Aug-25 → 23-Oct-25 | Complete 100% | float — EM03FEL120 EM03CEL120 — 03C Electrical Conceptual Layouts | 01-Oct-25 → 06-Nov-25 | Complete 100% | float — EM03CEL120