Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 44 activities in CV Civil Engineering × clear
Code
Activity
Start
Finish
Flt
%
EM03DCV160
03D Design & Model Major Eq. Fdns
24-Sep-25
13-Nov-25
100%
EM03YCV130
03Y Design & Model Structural Piperack Fdns
19-Nov-25
24-Dec-25
100%
EM03CCV160
03C Design & Model Major Eq. Fdns
19-Nov-25
17-Jan-26
100%
EM03CCV110
03C Design & Model Containment Area
19-Nov-25
25-Feb-26
100%
EM03BCV110
03B Design & Model Sumps
30-Dec-25
27-Dec-26
32%
EM03FCV160
03F Design & Model Major Eq. Fdns
07-Jan-26
27-Dec-26
30%
EM03ECV110
03E Design & Model Containment Area
25-Feb-26
27-Dec-26
19%
EM03DCV163
03D MF302 2002-F Demineralized Water Tank - Dwgs-IFC
17-Mar-26
28-Mar-26
100%
EM03CCV164
03C Update Model Major Eq. Fdns & Issue Dwgs-IFC
24-Mar-26
11-Apr-26
100%
EM03CCV126
03C Conceptual Misc. Steel Design/ Model
11-Apr-26
27-Dec-26
5%
EM03CCV166
03C Conceptual Misc. Foundations Design/ Model
16-Apr-26
27-Dec-26
5%
EM03YCV120
03Y Design & Model Major Structural Steel
17-Apr-26
27-Dec-26
5%
EM03ACV126
03A Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM03ACV127
03A Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03ACV160
03A Design & Model Major Eq. Fdns
27-Dec-26
27-Dec-26
0%
EM03ACV164
03A Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM03ACV166
03A Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
0%
EM03ACV167
03A Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03BCV112
03B Update Model Sumps & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM03BCV126
03B Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM03BCV127
03B Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03BCV166
03B Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
0%
EM03BCV167
03B Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03CCV127
03C Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03CCV167
03C Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03DCV126
03D Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM03DCV127
03D Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03DCV164
03D Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM03DCV166
03D Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
0%
EM03DCV167
03D Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03ECV112
03E Update Model Containment Area & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM03ECV126
03E Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM03ECV127
03E Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03ECV160
03E Design & Model Major Eq. Fdns
27-Dec-26
27-Dec-26
0%
EM03ECV164
03E Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM03ECV166
03E Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
0%
EM03ECV167
03E Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03FCV126
03F Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM03FCV127
03F Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03FCV164
03F Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM03FCV166
03F Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
0%
EM03FCV167
03F Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03YCV122
03Y Update Model Struct Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03YCV133
03Y Update Model Piperack Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Data Date
EM03DCV160 — 03D Design & Model Major Eq. Fdns | 24-Sep-25 → 13-Nov-25 | Complete 100% | float — EM03DCV160 EM03YCV130 — 03Y Design & Model Structural Piperack Fdns | 19-Nov-25 → 24-Dec-25 | Complete 100% | float — EM03YCV130 EM03CCV160 — 03C Design & Model Major Eq. Fdns | 19-Nov-25 → 17-Jan-26 | Complete 100% | float — EM03CCV160 EM03CCV110 — 03C Design & Model Containment Area | 19-Nov-25 → 25-Feb-26 | Complete 100% | float — EM03CCV110 EM03BCV110 — 03B Design & Model Sumps | 30-Dec-25 → 27-Dec-26 | In Progress 32% | float — EM03BCV110 EM03FCV160 — 03F Design & Model Major Eq. Fdns | 07-Jan-26 → 27-Dec-26 | In Progress 30% | float — EM03FCV160 EM03ECV110 — 03E Design & Model Containment Area | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — EM03ECV110 EM03DCV163 — 03D MF302 2002-F Demineralized Water Tank - Dwgs-IFC | 17-Mar-26 → 28-Mar-26 | Complete 100% | float — EM03DCV163 EM03CCV164 — 03C Update Model Major Eq. Fdns & Issue Dwgs-IFC | 24-Mar-26 → 11-Apr-26 | Complete 100% | float — EM03CCV164 EM03CCV126 — 03C Conceptual Misc. Steel Design/ Model | 11-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM03CCV126 EM03CCV166 — 03C Conceptual Misc. Foundations Design/ Model | 16-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM03CCV166 EM03YCV120 — 03Y Design & Model Major Structural Steel | 17-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM03YCV120 EM03ACV126 — 03A Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ACV127 — 03A Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ACV160 — 03A Design & Model Major Eq. Fdns | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ACV164 — 03A Update Model Major Eq. Fdns & Issue Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ACV166 — 03A Conceptual Misc. Foundations Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ACV167 — 03A Update Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BCV112 — 03B Update Model Sumps & Issue Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BCV126 — 03B Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BCV127 — 03B Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BCV166 — 03B Conceptual Misc. Foundations Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BCV167 — 03B Update Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03CCV127 — 03C Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03CCV167 — 03C Update Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DCV126 — 03D Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DCV127 — 03D Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DCV164 — 03D Update Model Major Eq. Fdns & Issue Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DCV166 — 03D Conceptual Misc. Foundations Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DCV167 — 03D Update Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ECV112 — 03E Update Model Containment Area & Issue Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ECV126 — 03E Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ECV127 — 03E Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ECV160 — 03E Design & Model Major Eq. Fdns | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ECV164 — 03E Update Model Major Eq. Fdns & Issue Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ECV166 — 03E Conceptual Misc. Foundations Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ECV167 — 03E Update Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FCV126 — 03F Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FCV127 — 03F Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FCV164 — 03F Update Model Major Eq. Fdns & Issue Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FCV166 — 03F Conceptual Misc. Foundations Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FCV167 — 03F Update Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YCV122 — 03Y Update Model Struct Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YCV133 — 03Y Update Model Piperack Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float —