EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 115
activities
in PI Piping Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EM03EPI120
03E Plant Layout Model
14-Jun-25
27-Dec-26
—
56%
EM03API120
03A Plant Layout Model
22-Jul-25
27-Dec-26
—
53%
EM03YPI120
03Y Plant Layout Model
22-Jul-25
27-Dec-26
—
53%
EM03DPI120
03D Plant Layout Model
08-Aug-25
15-Feb-26
—
100%
EM03API123
03A Plant Layout Nozzle Release
15-Aug-25
27-Sep-25
—
100%
EM03DPI123
03D Plant Layout Nozzle Release
18-Sep-25
27-Sep-25
—
100%
EM03CPI120
03C Plant Layout Model
01-Oct-25
17-Dec-25
—
100%
EM03UPIASB
03U IDP - Plant Layout - Acid Sewer
01-Oct-25
11-Oct-25
—
100%
EM03UPICSB
03U IDP - Plant Layout - Caustic Sewer
01-Oct-25
11-Oct-25
—
100%
EM03UPIFWB
03U IDP - Plant Layout - Firewater
01-Oct-25
11-Oct-25
—
100%
EM03UPIOSB
03U IDP - Plant Layout - Outfall Sewer
01-Oct-25
11-Oct-25
—
100%
EM03UPIASC
03U Model Review Mtg (HOC/MEC) - Acid Sewer
28-Oct-25
02-Nov-25
—
100%
EM03UPICSC
03U Model Review Mtg (HOC/MEC) - Caustic Sewer
28-Oct-25
02-Nov-25
—
100%
EM03UPIFWC
03U Model Review Mtg (HOC/MEC) - Firewater
28-Oct-25
02-Nov-25
—
100%
EM03UPIOSC
03U Model Review Mtg (HOC/MEC) - Outfall Sewer
28-Oct-25
02-Nov-25
—
100%
EM03CPI123
03C Plant Layout Nozzle Release
19-Nov-25
23-Nov-25
—
100%
EM03UPIASD
03U Planning Release - Acid Sewer
19-Nov-25
23-Dec-25
—
100%
EM03UPICSD
03U Planning Release - Caustic Sewer
19-Nov-25
23-Dec-25
—
100%
EM03UPIFWD
03U Planning Release - Firewater
19-Nov-25
23-Dec-25
—
100%
EM03UPIOSD
03U Planning Release - Outfall Sewer
19-Nov-25
23-Dec-25
—
100%
EM03DPI130
03D Model Review Mtg
16-Jan-26
16-Jan-26
—
100%
EM03API200
03A Equipment Location Plans
28-Jan-26
27-Dec-26
—
26%
EM03BPI200
03B Equipment Location Plans
28-Jan-26
27-Dec-26
—
26%
EM03EPI200
03E Equipment Location Plans
28-Jan-26
27-Dec-26
—
26%
EM03CPI130
03C Model Review Mtg
28-Jan-26
29-Jan-26
—
100%
EM03UPIFWE
03U Detail Model Development - FW, Outfall/Acid/Caustic Sewer
28-Jan-26
07-Feb-26
—
100%
EM03CPI200
03C Equipment Location Plans
28-Jan-26
08-Mar-26
—
100%
EM03DPI200
03D Equipment Location Plans
28-Jan-26
08-Mar-26
—
100%
EK030PI014
Plot Plan - Utility Plant Issue IFC
28-Jan-26
29-Mar-26
—
100%
EM03DPI021
03D Model Review Comment Resolution
11-Feb-26
13-Feb-26
—
100%
EM03UPIFWF
03U IDP - Detail Design - HDPE Piping (FW)
11-Feb-26
15-Feb-26
—
100%
EM03CPI140
03C Model Review Comment Resolution
11-Feb-26
28-Feb-26
—
100%
EM03UPIOSF
03U IDP - Detail Design - Metalic Piping (OS)
11-Feb-26
04-Apr-26
—
100%
EM03UPIASF
03U IDP - Detail Design - Other HDPE (AS & NA)
11-Feb-26
11-Apr-26
—
100%
EM03DPI133
03D IDP - Plant Layout
14-Feb-26
15-Feb-26
—
100%
EM03BPI120
03B Plant Layout Model
19-Feb-26
20-Feb-26
—
100%
EM03FPI120
03F Plant Layout Model
22-Feb-26
12-Mar-26
—
100%
EM03DPI132
03D Planning Release
25-Feb-26
25-Feb-26
—
100%
EM03UPIFWG
03U Iso Issue IFC - HDPE Piping (FW)
25-Feb-26
01-Mar-26
—
100%
EM03CPI133
03C IDP - Plant Layout
01-Mar-26
04-Mar-26
—
100%
EM03FPI123
03F Plant Layout Nozzle Release
11-Mar-26
18-Mar-26
—
100%
EM03CPI132
03C Planning Release
12-Mar-26
12-Mar-26
—
100%
EM03CPI134
03C Detail Model Development
13-Mar-26
18-Apr-26
—
100%
EM03CPI138
03C Design / Issue Pipe Supports IFC
21-Mar-26
27-Dec-26
—
12%
EM03BPI123
03B Plant Layout Nozzle Release
16-Apr-26
22-Apr-26
—
100%
EM03UPI190
03U U/G Plan Dwgs Issue IFC
22-Apr-26
27-Dec-26
—
5%
EM03UPIASG
03U Iso Issue IFC - Other HDPE (AS & NA)
22-Apr-26
27-Dec-26
—
5%
EM03UPIOSG
03U Iso Issue IFC - Metalic Piping (OS)
22-Apr-26
27-Dec-26
—
5%
EM03CPI141
03C Detail OP's & Services Model Review Mtg
24-Apr-26
27-Dec-26
—
5%
EM03API130
03A Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03API132
03A Planning Release
27-Dec-26
27-Dec-26
—
0%
EM03API133
03A IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM03API134
03A Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM03API135
03A A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM03API136
03A IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM03API138
03A Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM03API140
03A Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03API141
03A Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03API142
03A OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03BPI130
03B Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03BPI132
03B Planning Release
27-Dec-26
27-Dec-26
—
0%
EM03BPI133
03B IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM03BPI134
03B Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM03BPI135
03B A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM03BPI136
03B IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM03BPI138
03B Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM03BPI140
03B Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03BPI141
03B Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03BPI142
03B OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03CPI135
03C A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM03CPI136
03C IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM03CPI142
03C OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03DPI134
03D Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM03DPI135
03D A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM03DPI136
03D IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM03DPI138
03D Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM03DPI141
03D Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03DPI143
03D OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM03EPI123
03E Plant Layout Nozzle Release
27-Dec-26
27-Dec-26
—
0%
EM03EPI130
03E Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03EPI132
03E Planning Release
27-Dec-26
27-Dec-26
—
0%
EM03EPI133
03E IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM03EPI134
03E Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM03EPI135
03E A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM03EPI136
03E IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM03EPI138
03E Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM03EPI141
03E Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03EPI142
03E Detail OP's & Service Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03EPI143
03E OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03FPI130
03F Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03FPI132
03F Planning Release
27-Dec-26
27-Dec-26
—
0%
EM03FPI133
03F IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM03FPI134
03F Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM03FPI135
03F A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM03FPI136
03F IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM03FPI138
03F Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM03FPI141
03F Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03FPI142
03F Detail OP's & Service Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03FPI143
03F OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM03FPI200
03F Equipment Location Plans
27-Dec-26
27-Dec-26
—
0%
EM03YPI130
03Y Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03YPI132
03Y Planning Release
27-Dec-26
27-Dec-26
—
0%
EM03YPI133
03Y IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM03YPI134
03Y Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM03YPI135
03Y A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM03YPI136
03Y IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM03YPI138
03Y Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM03YPI141
03Y Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM03YPI143
03Y OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM05API140
05A Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM05API142
05A Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM05API143
05A OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM05BPI141
05B Model Review Comment Resolution
30-Dec-26
10-Jan-27
75.0d
0%
EM05BPI142
05B Detail OP's & Services Model Review Mtg
03-Feb-27
03-Feb-27
75.0d
0%
EM05BPI143
05B OP's & Serv. Model Review Comments Resolution
04-Feb-27
06-Feb-27
75.0d
0%