EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in P02 Procurement (Tanks) × clear
Code
Activity
Start
Finish
Flt
%
PO000MF000
Field Erected Tanks Subcontract - Prepare Inquiry, Bid, NTP
28-Jul-25
03-Jan-26
100%
PO000MF010
Field Erected Tanks Subcontract - Purchasing & Fabrication
04-Jan-26
27-Dec-26
31%
Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q4 2026 Data Date
PO000MF000 — Field Erected Tanks Subcontract - Prepare Inquiry, Bid, NTP | 28-Jul-25 → 03-Jan-26 | Complete 100% | float — PO000MF000 PO000MF010 — Field Erected Tanks Subcontract - Purchasing & Fabrication | 04-Jan-26 → 27-Dec-26 | In Progress 31% | float — PO000MF010