Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in P02 Procurement (Tanks) × clear
Code
Activity
Start
Finish
Flt
%
PO000MF000
Field Erected Tanks Subcontract - Prepare Inquiry, Bid, NTP
28-Jul-25
03-Jan-26
100%
PO000MF010
Field Erected Tanks Subcontract - Purchasing & Fabrication
04-Jan-26
27-Dec-26
31%
Jul 2025 Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Data Date
PO000MF000 — Field Erected Tanks Subcontract - Prepare Inquiry, Bid, NTP | 28-Jul-25 → 03-Jan-26 | Complete 100% | float — PO000MF000 PO000MF010 — Field Erected Tanks Subcontract - Purchasing & Fabrication | 04-Jan-26 → 27-Dec-26 | In Progress 31% | float — PO000MF010