EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 2
activities
in MD Vessels Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EM01BMD228
01B Clips Release IFC (Tanks, 2001FA/FB)
18-Mar-26
01-Apr-26
—
100%
EM01BMD229
01B Vessel Steel Release IFC
01-Apr-26
27-Dec-26
—
9%