EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 8 activities in EL Electrical Engineering × clear
Code
Activity
Start
Finish
Flt
%
EM01YEL120
01Y Electrical Conceptual Layouts
28-Aug-25
03-Oct-25
100%
EM01CEL120
01C Electrical Conceptual Layouts
02-Sep-25
17-Feb-26
100%
EM01BEL120
01B Electrical Conceptual Layouts
21-Sep-25
03-Oct-25
100%
EM01DEL120
01D Electrical Conceptual Layouts
21-Sep-25
03-Oct-25
100%
EM01EEL120
01E Electrical Conceptual Layouts
27-Sep-25
12-Nov-25
100%
EM01AEL120
01A Electrical Conceptual Layouts
01-Oct-25
08-Oct-25
100%
EM01HEL120
01H Electrical Conceptual Layouts
01-Oct-25
09-Nov-25
100%
EM01JEL120
01J Electrical Conceptual Layouts
22-Oct-25
12-Nov-25
100%
Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Data Date
EM01YEL120 — 01Y Electrical Conceptual Layouts | 28-Aug-25 → 03-Oct-25 | Complete 100% | float — EM01YEL120 EM01CEL120 — 01C Electrical Conceptual Layouts | 02-Sep-25 → 17-Feb-26 | Complete 100% | float — EM01CEL120 EM01BEL120 — 01B Electrical Conceptual Layouts | 21-Sep-25 → 03-Oct-25 | Complete 100% | float — EM01BEL120 EM01DEL120 — 01D Electrical Conceptual Layouts | 21-Sep-25 → 03-Oct-25 | Complete 100% | float — EM01DEL120 EM01EEL120 — 01E Electrical Conceptual Layouts | 27-Sep-25 → 12-Nov-25 | Complete 100% | float — EM01EEL120 EM01AEL120 — 01A Electrical Conceptual Layouts | 01-Oct-25 → 08-Oct-25 | Complete 100% | float — EM01AEL120 EM01HEL120 — 01H Electrical Conceptual Layouts | 01-Oct-25 → 09-Nov-25 | Complete 100% | float — EM01HEL120 EM01JEL120 — 01J Electrical Conceptual Layouts | 22-Oct-25 → 12-Nov-25 | Complete 100% | float — EM01JEL120