Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 14 activities in CV Civil Engineering × clear
Code
Activity
Start
Finish
Flt
%
EM05ACV120
05A Design & Model PR Structural Steel
22-Nov-25
26-Feb-26
100%
EM05ACV130
05A Design & Model Structural Piperack Fdns
03-Dec-25
24-Feb-26
100%
EM05ACV160
05A Design & Model Major Eq. Fdns
03-Jan-26
27-Dec-26
31%
EK000MF32D
05A MF312 2105-F Water Tank - Fdn Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM05ACV126
05A Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM05ACV166
05A Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
0%
EM05ACV122
05A Update Model PR Struct Steel & Issue Dwgs - IFC
30-Dec-26
10-Jan-27
21.0d
0%
EM05ACV127
05A Model Misc. Steel & Issue Dwgs - IFC
30-Dec-26
10-Jan-27
25.0d
0%
EM05ACV164
05A Update Model Major Eq. Fdns & Issue Dwgs-IFC
30-Dec-26
27-Jan-27
-14.0d
0%
EM05BCV122
05B Design / Model / IFC - Sleeper Steel & FDN's
30-Dec-26
24-Jan-27
71.0d
0%
EM05BCV133
05B Design / Model / IFC - S/S at Jetty
30-Dec-26
24-Jan-27
71.0d
0%
EM05ACV133
05A Update Model Structural Piperack Fdns & Issue Dwgs - IFC
01-Jan-27
10-Jan-27
121.0d
0%
EM05ACV167
05A Update Model Misc Fdns & Issue Dwgs - IFC
15-Jan-27
24-Jan-27
111.0d
0%
EM05BCV167
05B Design / Model / IFC - Equip. Fdn's.
20-Jan-27
20-Jan-27
221.0d
0%
Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q4 2026 Q1 2027 Data Date
EM05ACV120 — 05A Design & Model PR Structural Steel | 22-Nov-25 → 26-Feb-26 | Complete 100% | float — EM05ACV120 EM05ACV130 — 05A Design & Model Structural Piperack Fdns | 03-Dec-25 → 24-Feb-26 | Complete 100% | float — EM05ACV130 EM05ACV160 — 05A Design & Model Major Eq. Fdns | 03-Jan-26 → 27-Dec-26 | In Progress 31% | float — EM05ACV160 EK000MF32D — 05A MF312 2105-F Water Tank - Fdn Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05ACV126 — 05A Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05ACV166 — 05A Conceptual Misc. Foundation Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05ACV122 — 05A Update Model PR Struct Steel & Issue Dwgs - IFC | 30-Dec-26 → 10-Jan-27 | Not Started 0% | float 21.0d EM05ACV127 — 05A Model Misc. Steel & Issue Dwgs - IFC | 30-Dec-26 → 10-Jan-27 | Not Started 0% | float 25.0d EM05ACV164 — 05A Update Model Major Eq. Fdns & Issue Dwgs-IFC | 30-Dec-26 → 27-Jan-27 | Not Started 0% | float -14.0d EM05BCV122 — 05B Design / Model / IFC - Sleeper Steel & FDN's | 30-Dec-26 → 24-Jan-27 | Not Started 0% | float 71.0d EM05BCV133 — 05B Design / Model / IFC - S/S at Jetty | 30-Dec-26 → 24-Jan-27 | Not Started 0% | float 71.0d EM05ACV133 — 05A Update Model Structural Piperack Fdns & Issue Dwgs - IFC | 01-Jan-27 → 10-Jan-27 | Not Started 0% | float 121.0d EM05ACV167 — 05A Update Model Misc Fdns & Issue Dwgs - IFC | 15-Jan-27 → 24-Jan-27 | Not Started 0% | float 111.0d EM05BCV167 — 05B Design / Model / IFC - Equip. Fdn's. | 20-Jan-27 → 20-Jan-27 | Not Started 0% | float 221.0d