EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 14
activities
in CV Civil Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EM05ACV120
05A Design & Model PR Structural Steel
22-Nov-25
26-Feb-26
—
100%
EM05ACV130
05A Design & Model Structural Piperack Fdns
03-Dec-25
24-Feb-26
—
100%
EM05ACV160
05A Design & Model Major Eq. Fdns
03-Jan-26
27-Dec-26
—
31%
EK000MF32D
05A MF312 2105-F Water Tank - Fdn Dwgs - IFC
27-Dec-26
27-Dec-26
—
0%
EM05ACV126
05A Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM05ACV166
05A Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
—
0%
EM05ACV122
05A Update Model PR Struct Steel & Issue Dwgs - IFC
30-Dec-26
10-Jan-27
21.0d
0%
EM05ACV127
05A Model Misc. Steel & Issue Dwgs - IFC
30-Dec-26
10-Jan-27
25.0d
0%
EM05ACV164
05A Update Model Major Eq. Fdns & Issue Dwgs-IFC
30-Dec-26
27-Jan-27
-14.0d
0%
EM05BCV122
05B Design / Model / IFC - Sleeper Steel & FDN's
30-Dec-26
24-Jan-27
71.0d
0%
EM05BCV133
05B Design / Model / IFC - S/S at Jetty
30-Dec-26
24-Jan-27
71.0d
0%
EM05ACV133
05A Update Model Structural Piperack Fdns & Issue Dwgs - IFC
01-Jan-27
10-Jan-27
121.0d
0%
EM05ACV167
05A Update Model Misc Fdns & Issue Dwgs - IFC
15-Jan-27
24-Jan-27
111.0d
0%
EM05BCV167
05B Design / Model / IFC - Equip. Fdn's.
20-Jan-27
20-Jan-27
221.0d
0%