EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 26 activities in PI Piping Engineering × clear
Code
Activity
Start
Finish
Flt
%
EM05UPI175
05U Plant Layout Model - Common
01-Oct-25
11-Oct-25
100%
EM05API120
05A Plant Layout Model
19-Nov-25
25-Feb-26
100%
EM05UPI141
05U Model Review Mtg
27-Jan-26
28-Jan-26
100%
EM05API200
05A Equipment Location Plans
28-Jan-26
27-Dec-26
26%
EM05UPI176
05U IDP - Plant Layout
29-Jan-26
31-Jan-26
100%
EM05UPI186
05U Planning Release
31-Jan-26
05-Feb-26
100%
EM05UPI177
05U Detail Model Development
05-Feb-26
11-Feb-26
100%
EM05UPI178
05U IDP - Detail Design - HDPE Piping (FW)
11-Feb-26
17-Feb-26
100%
EM05UPI190
05U U/G Iso Issue IFC - HDPE Piping (FW)
25-Feb-26
01-Mar-26
100%
EM05UPI191
05U U/G Plan Dwgs IFC
15-Apr-26
27-Dec-26
5%
EM05API130
05A Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM05API132
05A Planning Release
27-Dec-26
27-Dec-26
0%
EM05API133
05A IDP - Plant Layout
27-Dec-26
27-Dec-26
0%
EM05API134
05A Detail Model Development
27-Dec-26
27-Dec-26
0%
EM05API136
05A IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM05BPI120
05B Plant Layout Model
27-Dec-26
27-Dec-26
0%
EM05BPI130
05B Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM05API135
05A A/G Piping Iso's - Issue IFC
30-Dec-26
03-Jan-27
90.0d
0%
EM05API138
05A Design / Issue Pipe Supports IFC
30-Dec-26
03-Jan-27
162.0d
0%
EM05BPI133
05B IDP - Plant Layout
13-Jan-27
14-Jan-27
75.0d
0%
EM05BPI132
05B Planning Release
20-Jan-27
24-Jan-27
75.0d
0%
EM05BPI200
05B Equipment Location Plans
20-Jan-27
24-Jan-27
221.0d
0%
EM05BPI134
05B Detail Model Development
27-Jan-27
31-Jan-27
75.0d
0%
EM05BPI136
05B IDP - Detail Design
07-Feb-27
10-Feb-27
75.0d
0%
EM05BPI135
05B A/G Piping Iso's - Issue IFC
14-Feb-27
21-Feb-27
75.0d
0%
EM05BPI138
05B Design / Issue Pipe Supports IFC
14-Feb-27
21-Feb-27
230.0d
0%
29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan 01-Feb 08-Feb 15-Feb 22-Feb Data Date
EM05UPI175 — 05U Plant Layout Model - Common | 01-Oct-25 → 11-Oct-25 | Complete 100% | float — EM05UPI175 EM05API120 — 05A Plant Layout Model | 19-Nov-25 → 25-Feb-26 | Complete 100% | float — EM05API120 EM05UPI141 — 05U Model Review Mtg | 27-Jan-26 → 28-Jan-26 | Complete 100% | float — EM05API200 — 05A Equipment Location Plans | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — EM05API200 EM05UPI176 — 05U IDP - Plant Layout | 29-Jan-26 → 31-Jan-26 | Complete 100% | float — EM05UPI176 EM05UPI186 — 05U Planning Release | 31-Jan-26 → 05-Feb-26 | Complete 100% | float — EM05UPI186 EM05UPI177 — 05U Detail Model Development | 05-Feb-26 → 11-Feb-26 | Complete 100% | float — EM05UPI177 EM05UPI178 — 05U IDP - Detail Design - HDPE Piping (FW) | 11-Feb-26 → 17-Feb-26 | Complete 100% | float — EM05UPI178 EM05UPI190 — 05U U/G Iso Issue IFC - HDPE Piping (FW) | 25-Feb-26 → 01-Mar-26 | Complete 100% | float — EM05UPI190 EM05UPI191 — 05U U/G Plan Dwgs IFC | 15-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM05UPI191 EM05API130 — 05A Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API132 — 05A Planning Release | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API133 — 05A IDP - Plant Layout | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API134 — 05A Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API136 — 05A IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05BPI120 — 05B Plant Layout Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05BPI130 — 05B Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API135 — 05A A/G Piping Iso's - Issue IFC | 30-Dec-26 → 03-Jan-27 | Not Started 0% | float 90.0d EM05API135 EM05API138 — 05A Design / Issue Pipe Supports IFC | 30-Dec-26 → 03-Jan-27 | Not Started 0% | float 162.0d EM05API138 EM05BPI133 — 05B IDP - Plant Layout | 13-Jan-27 → 14-Jan-27 | Not Started 0% | float 75.0d EM05BPI132 — 05B Planning Release | 20-Jan-27 → 24-Jan-27 | Not Started 0% | float 75.0d EM05BPI132 EM05BPI200 — 05B Equipment Location Plans | 20-Jan-27 → 24-Jan-27 | Not Started 0% | float 221.0d EM05BPI200 EM05BPI134 — 05B Detail Model Development | 27-Jan-27 → 31-Jan-27 | Not Started 0% | float 75.0d EM05BPI134 EM05BPI136 — 05B IDP - Detail Design | 07-Feb-27 → 10-Feb-27 | Not Started 0% | float 75.0d EM05BPI136 EM05BPI135 — 05B A/G Piping Iso's - Issue IFC | 14-Feb-27 → 21-Feb-27 | Not Started 0% | float 75.0d EM05BPI135 EM05BPI138 — 05B Design / Issue Pipe Supports IFC | 14-Feb-27 → 21-Feb-27 | Not Started 0% | float 230.0d EM05BPI138