EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 26 activities in PI Piping Engineering × clear
Code
Activity
Start
Finish
Flt
%
EM05UPI175
05U Plant Layout Model - Common
01-Oct-25
11-Oct-25
100%
EM05API120
05A Plant Layout Model
19-Nov-25
25-Feb-26
100%
EM05UPI141
05U Model Review Mtg
27-Jan-26
28-Jan-26
100%
EM05API200
05A Equipment Location Plans
28-Jan-26
27-Dec-26
26%
EM05UPI176
05U IDP - Plant Layout
29-Jan-26
31-Jan-26
100%
EM05UPI186
05U Planning Release
31-Jan-26
05-Feb-26
100%
EM05UPI177
05U Detail Model Development
05-Feb-26
11-Feb-26
100%
EM05UPI178
05U IDP - Detail Design - HDPE Piping (FW)
11-Feb-26
17-Feb-26
100%
EM05UPI190
05U U/G Iso Issue IFC - HDPE Piping (FW)
25-Feb-26
01-Mar-26
100%
EM05UPI191
05U U/G Plan Dwgs IFC
15-Apr-26
27-Dec-26
5%
EM05API130
05A Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM05API132
05A Planning Release
27-Dec-26
27-Dec-26
0%
EM05API133
05A IDP - Plant Layout
27-Dec-26
27-Dec-26
0%
EM05API134
05A Detail Model Development
27-Dec-26
27-Dec-26
0%
EM05API136
05A IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM05BPI120
05B Plant Layout Model
27-Dec-26
27-Dec-26
0%
EM05BPI130
05B Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM05API135
05A A/G Piping Iso's - Issue IFC
30-Dec-26
03-Jan-27
90.0d
0%
EM05API138
05A Design / Issue Pipe Supports IFC
30-Dec-26
03-Jan-27
162.0d
0%
EM05BPI133
05B IDP - Plant Layout
13-Jan-27
14-Jan-27
75.0d
0%
EM05BPI132
05B Planning Release
20-Jan-27
24-Jan-27
75.0d
0%
EM05BPI200
05B Equipment Location Plans
20-Jan-27
24-Jan-27
221.0d
0%
EM05BPI134
05B Detail Model Development
27-Jan-27
31-Jan-27
75.0d
0%
EM05BPI136
05B IDP - Detail Design
07-Feb-27
10-Feb-27
75.0d
0%
EM05BPI135
05B A/G Piping Iso's - Issue IFC
14-Feb-27
21-Feb-27
75.0d
0%
EM05BPI138
05B Design / Issue Pipe Supports IFC
14-Feb-27
21-Feb-27
230.0d
0%
Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Jan 2027 Feb 2027 Data Date
EM05UPI175 — 05U Plant Layout Model - Common | 01-Oct-25 → 11-Oct-25 | Complete 100% | float — EM05UPI175 EM05API120 — 05A Plant Layout Model | 19-Nov-25 → 25-Feb-26 | Complete 100% | float — EM05API120 EM05UPI141 — 05U Model Review Mtg | 27-Jan-26 → 28-Jan-26 | Complete 100% | float — EM05API200 — 05A Equipment Location Plans | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — EM05API200 EM05UPI176 — 05U IDP - Plant Layout | 29-Jan-26 → 31-Jan-26 | Complete 100% | float — EM05UPI186 — 05U Planning Release | 31-Jan-26 → 05-Feb-26 | Complete 100% | float — EM05UPI186 EM05UPI177 — 05U Detail Model Development | 05-Feb-26 → 11-Feb-26 | Complete 100% | float — EM05UPI177 EM05UPI178 — 05U IDP - Detail Design - HDPE Piping (FW) | 11-Feb-26 → 17-Feb-26 | Complete 100% | float — EM05UPI178 EM05UPI190 — 05U U/G Iso Issue IFC - HDPE Piping (FW) | 25-Feb-26 → 01-Mar-26 | Complete 100% | float — EM05UPI190 EM05UPI191 — 05U U/G Plan Dwgs IFC | 15-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM05UPI191 EM05API130 — 05A Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API132 — 05A Planning Release | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API133 — 05A IDP - Plant Layout | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API134 — 05A Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API136 — 05A IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05BPI120 — 05B Plant Layout Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05BPI130 — 05B Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API135 — 05A A/G Piping Iso's - Issue IFC | 30-Dec-26 → 03-Jan-27 | Not Started 0% | float 90.0d EM05API135 EM05API138 — 05A Design / Issue Pipe Supports IFC | 30-Dec-26 → 03-Jan-27 | Not Started 0% | float 162.0d EM05API138 EM05BPI133 — 05B IDP - Plant Layout | 13-Jan-27 → 14-Jan-27 | Not Started 0% | float 75.0d EM05BPI132 — 05B Planning Release | 20-Jan-27 → 24-Jan-27 | Not Started 0% | float 75.0d EM05BPI132 EM05BPI200 — 05B Equipment Location Plans | 20-Jan-27 → 24-Jan-27 | Not Started 0% | float 221.0d EM05BPI200 EM05BPI134 — 05B Detail Model Development | 27-Jan-27 → 31-Jan-27 | Not Started 0% | float 75.0d EM05BPI134 EM05BPI136 — 05B IDP - Detail Design | 07-Feb-27 → 10-Feb-27 | Not Started 0% | float 75.0d EM05BPI135 — 05B A/G Piping Iso's - Issue IFC | 14-Feb-27 → 21-Feb-27 | Not Started 0% | float 75.0d EM05BPI135 EM05BPI138 — 05B Design / Issue Pipe Supports IFC | 14-Feb-27 → 21-Feb-27 | Not Started 0% | float 230.0d EM05BPI138