EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 26
activities
in PI Piping Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EM05UPI175
05U Plant Layout Model - Common
01-Oct-25
11-Oct-25
—
100%
EM05API120
05A Plant Layout Model
19-Nov-25
25-Feb-26
—
100%
EM05UPI141
05U Model Review Mtg
27-Jan-26
28-Jan-26
—
100%
EM05API200
05A Equipment Location Plans
28-Jan-26
27-Dec-26
—
26%
EM05UPI176
05U IDP - Plant Layout
29-Jan-26
31-Jan-26
—
100%
EM05UPI186
05U Planning Release
31-Jan-26
05-Feb-26
—
100%
EM05UPI177
05U Detail Model Development
05-Feb-26
11-Feb-26
—
100%
EM05UPI178
05U IDP - Detail Design - HDPE Piping (FW)
11-Feb-26
17-Feb-26
—
100%
EM05UPI190
05U U/G Iso Issue IFC - HDPE Piping (FW)
25-Feb-26
01-Mar-26
—
100%
EM05UPI191
05U U/G Plan Dwgs IFC
15-Apr-26
27-Dec-26
—
5%
EM05API130
05A Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM05API132
05A Planning Release
27-Dec-26
27-Dec-26
—
0%
EM05API133
05A IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM05API134
05A Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM05API136
05A IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM05BPI120
05B Plant Layout Model
27-Dec-26
27-Dec-26
—
0%
EM05BPI130
05B Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM05API135
05A A/G Piping Iso's - Issue IFC
30-Dec-26
03-Jan-27
90.0d
0%
EM05API138
05A Design / Issue Pipe Supports IFC
30-Dec-26
03-Jan-27
162.0d
0%
EM05BPI133
05B IDP - Plant Layout
13-Jan-27
14-Jan-27
75.0d
0%
EM05BPI132
05B Planning Release
20-Jan-27
24-Jan-27
75.0d
0%
EM05BPI200
05B Equipment Location Plans
20-Jan-27
24-Jan-27
221.0d
0%
EM05BPI134
05B Detail Model Development
27-Jan-27
31-Jan-27
75.0d
0%
EM05BPI136
05B IDP - Detail Design
07-Feb-27
10-Feb-27
75.0d
0%
EM05BPI135
05B A/G Piping Iso's - Issue IFC
14-Feb-27
21-Feb-27
75.0d
0%
EM05BPI138
05B Design / Issue Pipe Supports IFC
14-Feb-27
21-Feb-27
230.0d
0%