EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 3 activities in PI Piping Engineering × clear
Code
Activity
Start
Finish
Flt
%
EM04API120
04A Plant Layout Model
27-Dec-26
27-Dec-26
0%
EM04API134
04A Plant Detail Model Development
27-Dec-26
27-Dec-26
0%
EM04API138
04A Design / Issue Pipe & Supports IFC
27-Dec-26
27-Dec-26
0%
30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec Data Date
EM04API120 — 04A Plant Layout Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM04API134 — 04A Plant Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM04API138 — 04A Design / Issue Pipe & Supports IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float —