EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 233
activities
in PI Piping Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EM02JPI120
02J Plant Layout Model
25-Mar-25
12-Nov-25
—
100%
EM02HPI120
02H Plant Layout Model
10-Apr-25
12-Nov-25
—
100%
EM02EPI120
02E Plant Layout Model
15-Apr-25
11-Nov-25
—
100%
EM02KPI120
02K Plant Layout Model
15-Apr-25
14-Nov-25
—
100%
EM02QPI120
02Q Plant Layout Model
19-Apr-25
19-Nov-25
—
100%
EM02BPI120
02B Plant Layout Model
22-Apr-25
01-Nov-25
—
100%
EM02API120
02A Plant Layout Model
25-Apr-25
13-Dec-25
—
100%
EM02NPI120
02N Plant Layout Model
03-May-25
13-Nov-25
—
100%
EM02YPI121
02Y Plant Layout Model
06-May-25
13-Nov-25
—
100%
EM02DPI120
02D Plant Layout Model
06-May-25
17-Dec-25
—
100%
EM02EPI123
02E Plant Layout Nozzle Release
28-May-25
21-Sep-25
—
100%
EM02DPI123
02D Plant Layout Nozzle Release
06-Jun-25
25-Sep-25
—
100%
EM02JPI123
02J Plant Layout Nozzle Release
07-Jun-25
21-Sep-25
—
100%
EM02QPI123
02Q Plant Layout Nozzle Release
13-Jun-25
21-Sep-25
—
100%
EM02KPI123
02K Plant Layout Nozzle Release
15-Jun-25
21-Sep-25
—
100%
EM02NPI123
02N Plant Layout Nozzle Release
19-Jun-25
21-Sep-25
—
100%
EM02API123
02A Plant Layout Nozzle Release
20-Jun-25
20-Sep-25
—
100%
EM02DPI100
02D Preliminary Drawings for Supersketch J-120,124
24-Jun-25
01-Jul-25
—
100%
EM02MPI120
02M Plant Layout Model
02-Jul-25
18-Dec-25
—
100%
EM02HPI123
02H Plant Layout Nozzle Release
09-Jul-25
24-Sep-25
—
100%
EM02LPI120
02L Plant Layout Model
10-Jul-25
19-Nov-25
—
100%
EM02CPI120
02C Plant Layout Model
15-Jul-25
16-Nov-25
—
100%
EM02GPI120
02G Plant Layout Model
05-Aug-25
15-Apr-26
—
100%
EM02MPI123
02M Plant Layout Nozzle Release
07-Aug-25
21-Sep-25
—
100%
EM02CPI123
02C Plant Layout Nozzle Release
27-Aug-25
20-Sep-25
—
100%
EM02PPI120
02P Plant Layout Model
17-Sep-25
21-Dec-25
—
100%
EK020PI013
020 Plot Plan - Issue IPL (ISBL)
30-Sep-25
23-Jan-26
—
100%
EM02FPI120
02F Plant Layout Model
01-Oct-25
14-Nov-25
—
100%
EM02UPICBB
02U IDP - Plant Layout - Benfield Sewer
01-Oct-25
11-Oct-25
—
100%
EM02UPICWB
02U IDP - Plant Layout - Cooling Water
01-Oct-25
11-Oct-25
—
100%
EM02UPIFWB
02U IDP - Plant Layout - Firewater
01-Oct-25
11-Oct-25
—
100%
EM02UPIOHB
02U IDP - Plant Layout - Hot Outfall Sewer
01-Oct-25
11-Oct-25
—
100%
EM02UPIOWB
02U IDP - Plant Layout - Oily Water Sewer
01-Oct-25
11-Oct-25
—
100%
EM02UPIPSB
02U IDP - Plant Layout - Process Water Sewer
01-Oct-25
11-Oct-25
—
100%
EM02UPICBC
02U Model Review Mtg (HOC/MEC) - Benfield Sewer
10-Oct-25
16-Oct-25
—
100%
EM02UPIPSC
02U Model Review Mtg (HOC/MEC) - Process Water Sewer
10-Oct-25
16-Oct-25
—
100%
EM02LPI123
02L Plant Layout Nozzle Release
10-Oct-25
19-Oct-25
—
100%
EM02PPI123
02P Plant Layout Nozzle Release
15-Oct-25
19-Oct-25
—
100%
EM02UPIOHC
02U Model Review Mtg (HOC/MEC) - Hot Outfall Sewer
28-Oct-25
31-Oct-25
—
100%
EK02UPIFWC
02U Model Review Mtg (HOC/MEC) - Firewater
28-Oct-25
02-Nov-25
—
100%
EM02UPICWC
02U Model Review Mtg (HOC/MEC) - Cooling Water
28-Oct-25
02-Nov-25
—
100%
EM02UPIOWC
02U Model Review Mtg (HOC/MEC) - Oily Water Sewer
29-Oct-25
31-Oct-25
—
100%
EM02FPI123
02F Plant Layout Nozzle Release
29-Oct-25
02-Nov-25
—
100%
EM02UPICBD
02U Planning Release - Benfield Sewer
07-Nov-25
09-Dec-25
—
100%
EM02UPICWD
02U Planning Release - Cooling Water
07-Nov-25
09-Dec-25
—
100%
EM02UPIFWD
02U Planning Release - Firewater
07-Nov-25
09-Dec-25
—
100%
EM02UPIOHD
02U Planning Release - Hot Outfall Sewer
07-Nov-25
09-Dec-25
—
100%
EM02UPIPSD
02U Planning Release - Process Water Sewer
07-Nov-25
09-Dec-25
—
100%
EM02UPIOWD
02U Planning Release - Oily Water Sewer
08-Nov-25
10-Dec-25
—
100%
EM02BPI130
02B Model Review Mtg
11-Nov-25
11-Nov-25
—
100%
EM02EPI130
02E Model Review Mtg
13-Nov-25
13-Nov-25
—
100%
EM02EPI140
02E Model Review Comment Resolution
14-Nov-25
18-Nov-25
—
100%
EM02HPI130
02H Model Review Mtg
14-Nov-25
19-Nov-25
—
100%
EM02JPI130
02J Model Review Mtg
19-Nov-25
19-Nov-25
—
100%
EM02EPI133
02E IDP - Plant Layout
19-Nov-25
22-Nov-25
—
100%
EM02KPI130
02K Model Review Mtg
20-Nov-25
20-Nov-25
—
100%
EM02LPI130
02L Model Review Mtg
21-Nov-25
04-Dec-25
—
100%
EM02HPI133
02H IDP - Plant Layout
02-Dec-25
06-Dec-25
—
100%
EM02CPI130
02C Model Review Mtg
05-Dec-25
06-Dec-25
—
100%
EM02KPI140
02K Model Review Comment Resolution
09-Dec-25
11-Dec-25
—
100%
EM02MPI130
02M Model Review Mtg
09-Dec-25
12-Dec-25
—
100%
EM02UPI190
02U Detail Model Development - All Services
10-Dec-25
07-Feb-26
—
100%
EM02DPI130
02D Model Review Mtg
12-Dec-25
13-Dec-25
—
100%
EM02KPI133
02K IDP - Plant Layout
12-Dec-25
13-Dec-25
—
100%
EM02MPI140
02M Model Review Comment Resolution
12-Dec-25
16-Dec-25
—
100%
EM02FPI130
02F Model Review Mtg
13-Dec-25
17-Dec-25
—
100%
EM02PPI130
02P Model Review Mtg
16-Dec-25
16-Dec-25
—
100%
EM02DPI140
02D Model Review Comment Resolution
16-Dec-25
17-Dec-25
—
100%
EM02NPI130
02N Model Review Mtg
16-Dec-25
17-Dec-25
—
100%
EM02QPI130
02Q Model Review Mtg
17-Dec-25
17-Dec-25
—
100%
EM02MPI133
02M IDP - Plant Layout
17-Dec-25
18-Dec-25
—
100%
EM02FPI140
02F Model Review Comment Resolution
17-Dec-25
25-Dec-25
—
100%
EM02API130
02A Model Review Mtg
18-Dec-25
18-Dec-25
—
100%
EM02DPI133
02D IDP - Plant Layout
18-Dec-25
20-Dec-25
—
100%
EM02QPI141
02Q Model Review Comment Resolution
18-Dec-25
20-Dec-25
—
100%
EM02API141
02A Model Review Comment Resolution
18-Dec-25
25-Dec-25
—
100%
EM02YPI122
02Y Model Review Mtg
19-Dec-25
24-Dec-25
—
100%
EM02KPI051
02K Planning Release
20-Dec-25
25-Dec-25
—
100%
EM02QPI133
02Q IDP - Plant Layout
23-Dec-25
27-Dec-25
—
100%
EM02PPI141
02P Model Review Comment Resolution
24-Dec-25
27-Dec-25
—
100%
EM02YPI123
02Y Model Review Comment Resolution
24-Dec-25
27-Dec-25
—
100%
EM02API133
02A IDP - Plant Layout
26-Dec-25
27-Dec-25
—
100%
EM02FPI133
02F IDP - Plant Layout
26-Dec-25
27-Dec-25
—
100%
EM02NPI141
02N Model Review Comment Resolution
27-Dec-25
31-Dec-25
—
100%
EM02PPI133
02P IDP - Plant Layout
27-Dec-25
31-Dec-25
—
100%
EM02LPI140
02L Model Review Comment Resolution
27-Dec-25
01-Jan-26
—
100%
EM02YPI124
02Y IDP - Plant Layout
30-Dec-25
31-Dec-25
—
100%
EM02BPI141
02B Model Review Comment Resolution
31-Dec-25
01-Jan-26
—
100%
EK02YPI050
02Y Model Comment Resolution Approval
01-Jan-26
03-Jan-26
—
100%
EM02BPI133
02B IDP - Plant Layout
02-Jan-26
03-Jan-26
—
100%
EM02NPI133
02N IDP - Plant Layout
02-Jan-26
03-Jan-26
—
100%
EM02JPI021
02J Model Review Comment Resolution
02-Jan-26
04-Jan-26
—
100%
EM02LPI133
02L IDP - Plant Layout
02-Jan-26
06-Jan-26
—
100%
EM02JPI133
02J IDP - Plant Layout
06-Jan-26
08-Jan-26
—
100%
EM02YPI132
02Y Planning Release
06-Jan-26
10-Jan-26
—
100%
EM02BPI132
02B Planning Release
09-Jan-26
09-Jan-26
—
100%
EM02QPI132
02Q Planning Release
09-Jan-26
15-Jan-26
—
100%
EM02API132
02A Planning Release
10-Jan-26
10-Jan-26
—
100%
EM02PPI132
02P Planning Release
10-Jan-26
10-Jan-26
—
100%
EM02JPI132
02J Planning Release
13-Jan-26
15-Jan-26
—
100%
EM02JPI134
02J Detail Model Development
15-Jan-26
27-Dec-26
—
29%
EM02QPI134
02Q Detail Model Development
16-Jan-26
27-Dec-26
—
28%
EM02FPI132
02F Planning Release
17-Jan-26
17-Jan-26
—
100%
EM02CPI133
02C IDP - Plant Layout
17-Jan-26
21-Jan-26
—
100%
EM02HPI132
02H Planning Release
18-Jan-26
18-Jan-26
—
100%
EM02DPI132
02D Planning Release
22-Jan-26
22-Jan-26
—
100%
EM02API200
02A Equipment Location Plans
23-Jan-26
26-Feb-26
—
100%
EM02GPI200
02G Equipment Location Plans
28-Jan-26
27-Dec-26
—
26%
EM02YPI134
02Y Detail Model Development
28-Jan-26
27-Dec-26
—
26%
EM02EPI132
02E Planning Release
28-Jan-26
28-Jan-26
—
100%
EM02LPI132
02L Planning Release
28-Jan-26
28-Jan-26
—
100%
EM02MPI132
02M Planning Release
28-Jan-26
29-Jan-26
—
100%
EM02KPI200
02K Equipment Location Plans
28-Jan-26
14-Feb-26
—
100%
EM02FPI200
02F Equipment Location Plans
28-Jan-26
17-Feb-26
—
100%
EM02QPI200
02Q Equipment Location Plans
28-Jan-26
17-Feb-26
—
100%
EM02BPI200
02B Equipment Location Plans
28-Jan-26
18-Feb-26
—
100%
EM02DPI200
02D Equipment Location Plans
28-Jan-26
18-Feb-26
—
100%
EM02EPI200
02E Equipment Location Plans
28-Jan-26
18-Feb-26
—
100%
EM02HPI200
02H Equipment Location Plans
28-Jan-26
18-Feb-26
—
100%
EM02JPI200
02J Equipment Location Plans
28-Jan-26
18-Feb-26
—
100%
EM02NPI200
02N Equipment Location Plans
28-Jan-26
18-Feb-26
—
100%
EM02PPI200
02P Equipment Location Plans
28-Jan-26
18-Feb-26
—
100%
EM02MPI200
02M Equipment Location Plans
28-Jan-26
25-Feb-26
—
100%
EM02LPI200
02L Equipment Location Plans
28-Jan-26
26-Feb-26
—
100%
EM02CPI200
02C Equipment Location Plans
28-Jan-26
04-Mar-26
—
100%
EM02BPI134
02B Detail Model Development
28-Jan-26
12-Mar-26
—
100%
EK020PI014
Plot Plan - ISBL (Area 02) Issue IFC
28-Jan-26
29-Mar-26
—
100%
EM02DPI134
02D Detail Model Development
28-Jan-26
18-Apr-26
—
100%
EM02EPI134
02E Detail Model Development
29-Jan-26
27-Dec-26
—
26%
EM02MPI134
02M Detail Model Development
29-Jan-26
27-Dec-26
—
26%
EM02NPI132
02N Planning Release
31-Jan-26
06-Feb-26
—
100%
EM02LPI134
02L Detail Model Development
06-Feb-26
27-Dec-26
—
24%
EM02PPI134
02P Detail Model Development
08-Feb-26
21-Mar-26
—
100%
EM02BPI138
02B Design / Issue Pipe Supports IFC
10-Feb-26
15-Apr-26
—
100%
EM02CPI132
02C Planning Release
11-Feb-26
11-Feb-26
—
100%
EM02UPICBF
02U IDP - Detail Design - Benfield Sewer
11-Feb-26
15-Feb-26
—
100%
EM02UPIFWF
02U IDP - Detail Design - Firewater
11-Feb-26
15-Feb-26
—
100%
EM02UPIOWF
02U IDP - Detail Design - Oily Water Sewer
11-Feb-26
15-Feb-26
—
100%
EM02UPICWG
02U U/G Plan Dwgs Issue IFC
14-Feb-26
27-Dec-26
—
22%
EM02UPIFWG
02U Iso Issue IFC - HDPE Piping (FW)
14-Feb-26
01-Mar-26
—
100%
EM02UPIOWG
02U Iso Issue IFC - Other HDPE Piping (OW, PW & CW)
14-Feb-26
18-Mar-26
—
100%
EM02UPICBG
02U Iso Issue IFC - Metalic Piping (BS & OS)
14-Feb-26
11-Apr-26
—
100%
EM02CPI134
02C Detail Model Development
20-Feb-26
27-Dec-26
—
20%
EM02NPI134
02N Detail Model Development
20-Feb-26
11-Apr-26
—
100%
EM02GPI123
02G Plant Layout Nozzle Release
25-Feb-26
21-Mar-26
—
100%
EM02FPI134
02F Detail Model Development
04-Mar-26
27-Dec-26
—
17%
EM02HPI134
02H Detail Model Development
07-Mar-26
27-Dec-26
—
16%
EM02PPI142
02P Detail OP's & Service Model Review Mtg
18-Mar-26
20-Mar-26
—
100%
EM02BPI142
02B Detail OP's & Service Model Review Mtg
19-Mar-26
20-Mar-26
—
100%
EM02BPI143
02B OP's & Serv. Model Review Comment Resolution
21-Mar-26
22-Mar-26
—
100%
EM02API134
02A Detail Model Development
22-Mar-26
27-Dec-26
—
12%
EM02PPI143
02P OP's & Serv. Model Review Comment Resolution
22-Mar-26
31-Mar-26
—
100%
EM02BPI136
02B IDP - Detail Design
25-Mar-26
26-Mar-26
—
100%
EM02BPI135
02B A/G Piping Iso's - Issue IFC
28-Mar-26
15-Apr-26
—
100%
EM02PPI136
02P IDP - Detail Design
31-Mar-26
31-Mar-26
—
100%
EM02PPI135
02P A/G Piping Iso's - Issue IFC
14-Apr-26
15-Apr-26
—
100%
EM02PPI138
02P Design / Issue Pipe Supports IFC
14-Apr-26
15-Apr-26
—
100%
EM02NPI142
02N Detail OP's & Service Model Review Mtg
15-Apr-26
16-Apr-26
—
100%
EM02NPI143
02N OP's & Service Model Review Comment Resolution
16-Apr-26
27-Dec-26
—
5%
EM02GPI130
02G Model Review Mtg
16-Apr-26
18-Apr-26
—
100%
EM02GPI021
02G Model Review Comment Resolution
21-Apr-26
27-Dec-26
—
5%
EM02DPI141
02D Detail OP's & Services Model Review Mtg
24-Apr-26
27-Dec-26
—
5%
EM02API135
02A A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02API136
02A IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02API138
02A Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02API142
02A Detail OP's & Service Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02API143
02A OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02CPI135
02C A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02CPI136
02C IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02CPI138
02C Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02CPI141
02C Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02CPI143
02C OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM02DPI135
02D A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02DPI136
02D IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02DPI138
02D Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02DPI142
02D OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02EPI135
02E A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02EPI136
02E IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02EPI138
02E Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02EPI141
02E Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02EPI142
02E OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02FPI135
02F A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02FPI136
02F IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02FPI138
02F Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02FPI141
02F Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02FPI142
02F OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02GPI132
02G Planning Release
27-Dec-26
27-Dec-26
—
0%
EM02GPI133
02G IDP - Plant Layout
27-Dec-26
27-Dec-26
—
0%
EM02GPI134
02G Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM02GPI141
02G Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02HPI135
02H A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02HPI136
02H IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02HPI138
02H Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02HPI141
02H Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02HPI143
02H OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM02JPI135
02J A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02JPI136
02J IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02JPI138
02J Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02JPI141
02J Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02JPI143
02J OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM02KPI134
02K Plant Detail Model Development
27-Dec-26
27-Dec-26
—
0%
EM02KPI135
02K A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02KPI136
02K IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02KPI138
02K Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02KPI141
02K Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02KPI142
02K OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02LPI135
02L A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02LPI136
02L IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02LPI138
02L Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02LPI141
02L Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02LPI142
02L OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02MPI135
02M A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02MPI136
02M IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02MPI138
02M Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02MPI141
02M Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02MPI142
02M OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02NPI135
02N A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02NPI136
02N IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02NPI138
02N Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02QPI135
02Q A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02QPI136
02Q IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02QPI138
02Q Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02QPI142
02Q Detail OP's & Service Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02QPI143
02Q OP's & Service Model Review Comment Resolution
27-Dec-26
27-Dec-26
—
0%
EM02YPI135
02Y A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
—
0%
EM02YPI136
02Y IDP - Detail Design
27-Dec-26
27-Dec-26
—
0%
EM02YPI138
02Y Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
—
0%
EM02YPI142
02Y Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
—
0%
EM02YPI143
02Y OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
—
0%
EM02GPI143
02G OP's & Serv. Model Review Comments Resolution
30-Dec-26
03-Jan-27
88.0d
0%
EM02GPI135
02G A/G Piping Iso's - Issue IFC
03-Jan-27
03-Jan-27
—
0%
EM02GPI136
02G IDP - Detail Design
03-Jan-27
03-Jan-27
—
0%
EM02GPI138
02G Design / Issue Pipe Supports IFC
03-Jan-27
03-Jan-27
—
0%