EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 69 activities in EBPM Payment Milestones × clear
Code
Activity
Start
Finish
Flt
%
EK000YA827
(PC-04) Issue Cooling Tower,Item No. 2101-U Purchase Order
03-Sep-25
03-Sep-25
100%
EK000YA812
(EP-13) Vendor Acceptance of Commitment for Boiler Package, 2002-U
05-Sep-25
05-Sep-25
100%
EK000YA820
(EP-20) Vendor Acceptance of Commitment for 101-B
20-Sep-25
20-Sep-25
100%
EK000YA803
(PC-02,EP-04) Issue Project Specific Quality Control Manual
30-Oct-25
30-Oct-25
100%
EK000YA815
(PC-05) Award Contract - Ammonia Storage Tanks - 2101-F/2102
03-Jan-26
03-Jan-26
100%
EK000YA000
(PC-01,EP-01, TLA-01) Receive Owner's ""Notice to Proceed""
17-Jan-26
17-Jan-26
100%
EK000YA814
(EP-15) Vendor Acceptance of Commitment for 101-J, 102-J, 103-J & 105-J
11-Feb-26
11-Feb-26
100%
EK000YA816
(EP-16) Vendor Acceptance of Commitment for 105-D
11-Feb-26
11-Feb-26
100%
EK000YA817
(EP-17) Vendor Acceptance of Commitment for High Pressure Boiler Feed Water pumps, 104-J & 107-J
11-Feb-26
11-Feb-26
100%
EK000YA819
(EP-19) Vendor Acceptance of Commitment for 120-C
11-Feb-26
11-Feb-26
100%
EK000YA821
(PC-03,EP-21) Vendor Acceptance of Commitment for Methanator, 106-D
11-Feb-26
11-Feb-26
100%
EK000YA818
(EP-18) Vendor Acceptance of Commitment for 101-C and 102-C
19-Feb-26
19-Feb-26
100%
EK000YA825
(EP-24) Vendor Acceptance of Commitment for Demineralizer, 2001-U, & remaining utility equipment
17-Mar-26
17-Mar-26
100%
EK000YA834
(PC-06,EP-28) Issue ISBL Plot Plan For Construction (IFC)
28-Mar-26
28-Mar-26
100%
EK000YA830
(EP-25) Vendor Acceptance of Commitment for Kellogg Advanced Ammonia Process (KAAP) Catalyst
11-Apr-26
11-Apr-26
100%
EK000YA828
(EP-30) Vendor Acceptance of Commitment for Electrical 20 MVA Transformers
27-Dec-26
27-Dec-26
0%
EK000YA829
(EP-31) Vendor Acceptance of Commitment for Substation
27-Dec-26
27-Dec-26
0%
EK000YA836
(PC-07) Issue 101-B -Primary Reformer Erection Drawings
27-Dec-26
27-Dec-26
0%
EK000YA858
(EP-38) Deliver Syn Gas Compressor, 103-J, and Ammonia Refrig Compressor, 105-J, to site
27-Dec-26
27-Dec-26
0%
EK000YA845
(PC-08) Complete >10% - ISBL -Unit 02 - Pipe Spool Fabrication,>2 Inch Diameter
28-Dec-26
28-Dec-26
0%
EK000YA843
(PC-18) Complete >90% Bldg No. 2604-K Workshop / Warehouse Erection
28-Dec-26
28-Dec-26
750.0d
0%
EK000CS040
Issue Operation & Maintenance Manuals for Review
30-Dec-26
21-Mar-27
215.0d
0%
EK000CS060
Issue Proposed Operating Training Program for Review
27-Jan-27
21-Mar-27
215.0d
0%
EK000YA863
(PC-09) Complete >90% Compressor 101-J/JT Equipment Foundation
01-Feb-27
01-Feb-27
714.0d
0%
EK000YA844
(EP-40) Complete Fabrication of 101-F Steam Drum
07-Feb-27
07-Feb-27
708.0d
0%
EK000YA851
(PC-12) Complete >90% - ISBL - Unit 02 Underground Piping Fabrication and installation
26-Feb-27
26-Feb-27
689.0d
0%
EK000YA855
(EP-45) Deliver Air Compressor, 101-J, and Feed Gas Compressor, 102-J, to site
08-Mar-27
08-Mar-27
680.0d
0%
EK000YA859
(PC-11) Complete >90% - ISBL - Unit 02 Equipment Foundation
23-Mar-27
23-Mar-27
664.0d
0%
EK000YA854
(PC-13) Complete >90% - OSBL Unit 01 & 03 Underground Piping Fabrication & Installation
26-Mar-27
26-Mar-27
661.0d
0%
EK000CS050
Issue Operation & Maintenance Manuals IFC
07-Apr-27
08-Aug-27
375.0d
0%
EK000YA856
(EP-43) Deliver majority of tagged field Instruments
12-Apr-27
12-Apr-27
645.0d
0%
EK000YA852
(EP-42) Deliver BFW pumps, 104-J, & Lean Solution pumps, 107-J, to site
15-Apr-27
15-Apr-27
641.0d
0%
EK000YA865
(PC-16) Erect 101-B Primary Reformer Heater Stack ,Forced & Induced Draft Fans
30-Apr-27
30-Apr-27
626.0d
0%
EK000YA867
(PC-19) Complete >90% - Cooling Tower ,Item No. 2101-U Erection
04-May-27
04-May-27
622.0d
0%
EK000CS070
Issue Operating Training Program
05-May-27
27-Jun-27
375.0d
0%
EK000YA850
(PC-15) Complete >90% ISBL Unit 02 aboveground LB ,Greater than 2"" pipe fabrication
29-May-27
29-May-27
598.0d
0%
EK000YA861
(PC-17) Complete >90% - Erection of Steam Drum 101-F Structure
14-Jun-27
14-Jun-27
581.0d
0%
EK000YA842
(PC-10) Complete >90% - Ammonia Tanks - 2101-F/2102-F Foundation
16-Jun-27
16-Jun-27
579.0d
0%
EK000YA862
(PC-14) Complete >90% -Bldg No. 2601-K Main Control Building Erection
24-Jun-27
24-Jun-27
571.0d
0%
EK000YA846
(EP-41) Issue Proposed Operator Training Program
27-Jun-27
27-Jun-27
568.0d
0%
EK000YA868
(PC-26) Complete >90% 101-B Primary Reformer Erection
24-Jul-27
24-Jul-27
541.0d
0%
EK000YA857
(EP-46) Complete >90% delivery of all ISBL long lead equipment (except 103-J and 105-J) to site
29-Jul-27
29-Jul-27
536.0d
0%
EK000YA864
(PC-22) Complete >90% - ISBL - Unit 02 equipment installation
30-Jul-27
30-Jul-27
535.0d
0%
EK000YA853
(EP-44) Issue Operation & Maintenance Manuals
08-Aug-27
08-Aug-27
526.0d
0%
EK000YA871
(PC-20) Install export Ammonia Line from EBIC site to Storage Tank,2101-F/2102-F Battery Limit
09-Aug-27
09-Aug-27
526.0d
0%
EK000YA866
(PC-25) Complete >90% - OSBL - Unit 01 & 03 Electrical lighting installation
08-Sep-27
08-Sep-27
495.0d
0%
EK000YA873
(PC-21) Install DCS in Main Control Building
10-Sep-27
10-Sep-27
493.0d
0%
EK000YA876
(PC-23) Complete >90% - OSBL - Unit 01 & 03 pipe testing -visual,service,hydrostatic,or pneumatic testing
05-Oct-27
05-Oct-27
468.0d
0%
EK000YA890
(PC-27) Complete >10% - ISBL - Unit 02 Hot & Cold Pipe Insulation
02-Nov-27
02-Nov-27
108.0d
0%
EK000YA869
(PC-30) Complete >90% - ISBL - Unit 02 - Equipment Insulation
01-Dec-27
01-Dec-27
411.0d
0%
EK000YA879
(PC-24) Commence Pre-commissioning Activities
21-Dec-27
21-Dec-27
392.0d
0%
EK000YA878
(PC-28) Mechanical Completion - OSBL - Unit 01 & 03 Utilities &Plant site Offsites
04-Jan-28
04-Jan-28
377.0d
0%
EK000YA872
(EP-47) Deliver Converter Catalyst to site
12-Jan-28
12-Jan-28
369.0d
0%
EK000YA837
(PC-36) Complete >90% - Site Preparation within the EBIC Plant Site boundary wall
28-Jan-28
28-Jan-28
353.0d
0%
EK000YA874
(PC-31) Complete >90% - ISBL - Unit 02 - LB Greater than 2"" piping installation
07-Feb-28
07-Feb-28
343.0d
0%
EK000YA870
(PC-34) Complete >90% - ISBL - Unit 02 Instruments Installed
14-Feb-28
14-Feb-28
336.0d
0%
EK000YA877
(PC-33) Complete >90% - ISBL - Unit 02 pipe testing -visual,service,hydrostatic,or pneumatic testing
14-Feb-28
14-Feb-28
336.0d
0%
EK000YA860
(PC-29) Complete Erection of Ammonia Storage Tanks 2101-F/2102-F
09-Mar-28
09-Mar-28
312.0d
0%
EK000YA875
(PC-35) Complete >90% - ISBL - Unit 02 Instrument loops checked
19-Mar-28
19-Mar-28
302.0d
0%
EK000YA881
(PC-37) Mechanical Completion - ISBL - Unit 02 -Ammonia
19-Mar-28
19-Mar-28
302.0d
0%
EK000YA882
(PC-32) Complete >90% - ISBL - Unit 02 chemical cleaning LP,MP & HP steam systems
29-Mar-28
29-Mar-28
292.0d
0%
EK000YA880
(PC-38) Feed Gas into Ammonia Unit
11-May-28
11-May-28
250.0d
0%
EK000YA883
(PC-39) First Ammonia produced
31-May-28
31-May-28
55.0d
0%
EK000YA884
(PC-40) Begin Production Test run
31-May-28
31-May-28
55.0d
0%
EK000YA886
(PC-41) Begin Reliability Test
31-May-28
31-May-28
55.0d
0%
EK000YA885
(PC-42) Complete Production Test run
04-Jul-28
04-Jul-28
195.0d
0%
EK000YA887
(PC-43) Complete Reliability Test
22-Sep-28
22-Sep-28
-59.0d
0%
SC000T0120
(PC-44) Provisional Completion
22-Sep-28
22-Sep-28
-59.0d
0%
SC000YA700
Contractual Completion Date (15-Feb-09)
15-Mar-29
15-Mar-29
-59.0d
0%
01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 29-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar Data Date
EK000YA827 — (PC-04) Issue Cooling Tower,Item No. 2101-U Purchase Order | 03-Sep-25 | Complete EK000YA812 — (EP-13) Vendor Acceptance of Commitment for Boiler Package, 2002-U | 05-Sep-25 | Complete EK000YA820 — (EP-20) Vendor Acceptance of Commitment for 101-B | 20-Sep-25 | Complete EK000YA803 — (PC-02,EP-04) Issue Project Specific Quality Control Manual | 30-Oct-25 | Complete EK000YA815 — (PC-05) Award Contract - Ammonia Storage Tanks - 2101-F/2102 | 03-Jan-26 | Complete EK000YA000 — (PC-01,EP-01, TLA-01) Receive Owner's ""Notice to Proceed"" | 17-Jan-26 | Complete EK000YA814 — (EP-15) Vendor Acceptance of Commitment for 101-J, 102-J, 103-J & 105-J | 11-Feb-26 | Complete EK000YA816 — (EP-16) Vendor Acceptance of Commitment for 105-D | 11-Feb-26 | Complete EK000YA817 — (EP-17) Vendor Acceptance of Commitment for High Pressure Boiler Feed Water pumps, 104-J & 107-J | 11-Feb-26 | Complete EK000YA819 — (EP-19) Vendor Acceptance of Commitment for 120-C | 11-Feb-26 | Complete EK000YA821 — (PC-03,EP-21) Vendor Acceptance of Commitment for Methanator, 106-D | 11-Feb-26 | Complete EK000YA818 — (EP-18) Vendor Acceptance of Commitment for 101-C and 102-C | 19-Feb-26 | Complete EK000YA825 — (EP-24) Vendor Acceptance of Commitment for Demineralizer, 2001-U, & remaining utility equipment | 17-Mar-26 | Complete EK000YA834 — (PC-06,EP-28) Issue ISBL Plot Plan For Construction (IFC) | 28-Mar-26 | Complete EK000YA830 — (EP-25) Vendor Acceptance of Commitment for Kellogg Advanced Ammonia Process (KAAP) Catalyst | 11-Apr-26 | Complete EK000YA828 — (EP-30) Vendor Acceptance of Commitment for Electrical 20 MVA Transformers | 27-Dec-26 | Not Started EK000YA829 — (EP-31) Vendor Acceptance of Commitment for Substation | 27-Dec-26 | Not Started EK000YA836 — (PC-07) Issue 101-B -Primary Reformer Erection Drawings | 27-Dec-26 | Not Started EK000YA858 — (EP-38) Deliver Syn Gas Compressor, 103-J, and Ammonia Refrig Compressor, 105-J, to site | 27-Dec-26 | Not Started EK000YA845 — (PC-08) Complete >10% - ISBL -Unit 02 - Pipe Spool Fabrication,>2 Inch Diameter | 28-Dec-26 | Not Started EK000YA843 — (PC-18) Complete >90% Bldg No. 2604-K Workshop / Warehouse Erection | 28-Dec-26 | Not Started EK000CS040 — Issue Operation & Maintenance Manuals for Review | 30-Dec-26 → 21-Mar-27 | Not Started 0% | float 215.0d EK000CS040 EK000CS060 — Issue Proposed Operating Training Program for Review | 27-Jan-27 → 21-Mar-27 | Not Started 0% | float 215.0d EK000CS060 EK000YA863 — (PC-09) Complete >90% Compressor 101-J/JT Equipment Foundation | 01-Feb-27 | Not Started EK000YA844 — (EP-40) Complete Fabrication of 101-F Steam Drum | 07-Feb-27 | Not Started EK000YA851 — (PC-12) Complete >90% - ISBL - Unit 02 Underground Piping Fabrication and installation | 26-Feb-27 | Not Started EK000YA855 — (EP-45) Deliver Air Compressor, 101-J, and Feed Gas Compressor, 102-J, to site | 08-Mar-27 | Not Started EK000YA859 — (PC-11) Complete >90% - ISBL - Unit 02 Equipment Foundation | 23-Mar-27 | Not Started EK000YA854 — (PC-13) Complete >90% - OSBL Unit 01 & 03 Underground Piping Fabrication & Installation | 26-Mar-27 | Not Started EK000CS050 — Issue Operation & Maintenance Manuals IFC | 07-Apr-27 → 08-Aug-27 | Not Started 0% | float 375.0d EK000CS050 EK000YA856 — (EP-43) Deliver majority of tagged field Instruments | 12-Apr-27 | Not Started EK000YA852 — (EP-42) Deliver BFW pumps, 104-J, & Lean Solution pumps, 107-J, to site | 15-Apr-27 | Not Started EK000YA865 — (PC-16) Erect 101-B Primary Reformer Heater Stack ,Forced & Induced Draft Fans | 30-Apr-27 | Not Started EK000YA867 — (PC-19) Complete >90% - Cooling Tower ,Item No. 2101-U Erection | 04-May-27 | Not Started EK000CS070 — Issue Operating Training Program | 05-May-27 → 27-Jun-27 | Not Started 0% | float 375.0d EK000CS070 EK000YA850 — (PC-15) Complete >90% ISBL Unit 02 aboveground LB ,Greater than 2"" pipe fabrication | 29-May-27 | Not Started EK000YA861 — (PC-17) Complete >90% - Erection of Steam Drum 101-F Structure | 14-Jun-27 | Not Started EK000YA842 — (PC-10) Complete >90% - Ammonia Tanks - 2101-F/2102-F Foundation | 16-Jun-27 | Not Started EK000YA862 — (PC-14) Complete >90% -Bldg No. 2601-K Main Control Building Erection | 24-Jun-27 | Not Started EK000YA846 — (EP-41) Issue Proposed Operator Training Program | 27-Jun-27 | Not Started EK000YA868 — (PC-26) Complete >90% 101-B Primary Reformer Erection | 24-Jul-27 | Not Started EK000YA857 — (EP-46) Complete >90% delivery of all ISBL long lead equipment (except 103-J and 105-J) to site | 29-Jul-27 | Not Started EK000YA864 — (PC-22) Complete >90% - ISBL - Unit 02 equipment installation | 30-Jul-27 | Not Started EK000YA853 — (EP-44) Issue Operation & Maintenance Manuals | 08-Aug-27 | Not Started EK000YA871 — (PC-20) Install export Ammonia Line from EBIC site to Storage Tank,2101-F/2102-F Battery Limit | 09-Aug-27 | Not Started EK000YA866 — (PC-25) Complete >90% - OSBL - Unit 01 & 03 Electrical lighting installation | 08-Sep-27 | Not Started EK000YA873 — (PC-21) Install DCS in Main Control Building | 10-Sep-27 | Not Started EK000YA876 — (PC-23) Complete >90% - OSBL - Unit 01 & 03 pipe testing -visual,service,hydrostatic,or pneumatic testing | 05-Oct-27 | Not Started EK000YA890 — (PC-27) Complete >10% - ISBL - Unit 02 Hot & Cold Pipe Insulation | 02-Nov-27 | Not Started EK000YA869 — (PC-30) Complete >90% - ISBL - Unit 02 - Equipment Insulation | 01-Dec-27 | Not Started EK000YA879 — (PC-24) Commence Pre-commissioning Activities | 21-Dec-27 | Not Started EK000YA878 — (PC-28) Mechanical Completion - OSBL - Unit 01 & 03 Utilities &Plant site Offsites | 04-Jan-28 | Not Started EK000YA872 — (EP-47) Deliver Converter Catalyst to site | 12-Jan-28 | Not Started EK000YA837 — (PC-36) Complete >90% - Site Preparation within the EBIC Plant Site boundary wall | 28-Jan-28 | Not Started EK000YA874 — (PC-31) Complete >90% - ISBL - Unit 02 - LB Greater than 2"" piping installation | 07-Feb-28 | Not Started EK000YA870 — (PC-34) Complete >90% - ISBL - Unit 02 Instruments Installed | 14-Feb-28 | Not Started EK000YA877 — (PC-33) Complete >90% - ISBL - Unit 02 pipe testing -visual,service,hydrostatic,or pneumatic testing | 14-Feb-28 | Not Started EK000YA860 — (PC-29) Complete Erection of Ammonia Storage Tanks 2101-F/2102-F | 09-Mar-28 | Not Started EK000YA875 — (PC-35) Complete >90% - ISBL - Unit 02 Instrument loops checked | 19-Mar-28 | Not Started EK000YA881 — (PC-37) Mechanical Completion - ISBL - Unit 02 -Ammonia | 19-Mar-28 | Not Started EK000YA882 — (PC-32) Complete >90% - ISBL - Unit 02 chemical cleaning LP,MP & HP steam systems | 29-Mar-28 | Not Started EK000YA880 — (PC-38) Feed Gas into Ammonia Unit | 11-May-28 | Not Started EK000YA883 — (PC-39) First Ammonia produced | 31-May-28 | Not Started EK000YA884 — (PC-40) Begin Production Test run | 31-May-28 | Not Started EK000YA886 — (PC-41) Begin Reliability Test | 31-May-28 | Not Started EK000YA885 — (PC-42) Complete Production Test run | 04-Jul-28 | Not Started EK000YA887 — (PC-43) Complete Reliability Test | 22-Sep-28 | Not Started SC000T0120 — (PC-44) Provisional Completion | 22-Sep-28 | Not Started SC000YA700 — Contractual Completion Date (15-Feb-09) | 15-Mar-29 | Not Started