EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 24 activities in EL Electrical Engineering × clear
Code
Activity
Start
Finish
Flt
%
EM02AEL120
02A Electrical Conceptual Layouts
27-Jun-25
30-Aug-25
100%
EM02BEL120
02B Electrical Conceptual Layouts
27-Jun-25
21-Sep-25
100%
EM02EEL120
02E Electrical Conceptual Layouts
01-Jul-25
30-Aug-25
100%
EM02YEL120
02Y Electrical Conceptual Layouts
08-Jul-25
30-Aug-25
100%
EM02HEL120
02H Electrical Conceptual Layouts
11-Jul-25
30-Aug-25
100%
EM02LEL120
02L Electrical Conceptual Layouts
23-Jul-25
04-Oct-25
100%
EM02KEL120
02K Electrical Conceptual Layouts
05-Aug-25
28-Sep-25
100%
EM02GEL120
02G Electrical Conceptual Layouts
05-Aug-25
06-Nov-25
100%
EM02NEL120
02N Electrical Conceptual Layouts
12-Aug-25
05-Oct-25
100%
EM02MEL120
02M Electrical Conceptual Layouts
12-Aug-25
19-Oct-25
100%
EM02JEL120
02J Electrical Conceptual Layouts
12-Aug-25
01-Nov-25
100%
EM02CEL120
02C Electrical Conceptual Layouts
27-Aug-25
27-Sep-25
100%
EM02QEL120
02Q Electrical Conceptual Layouts
10-Sep-25
12-Oct-25
100%
EM020ELEL2
02 U/G Electrical Routing Plans - IFC
16-Sep-25
27-Dec-26
47%
EM02FEL120
02F Electrical Conceptual Layouts
21-Sep-25
27-Sep-25
100%
EM020ELEH2
02 Develop & Issue Earthing / Grounding Dwgs - IFC
24-Sep-25
27-Dec-26
46%
EM02DEL120
02D Electrical Conceptual Layouts
30-Sep-25
15-Nov-25
100%
EM02PEL120
02P Electrical Conceptual Layouts
19-Nov-25
04-Dec-25
100%
EM20ELEK2
02 Develop & Issue Cable Ladder Plans - IFC
03-Mar-26
27-Dec-26
17%
EM020ELEK2
02 Develop & Issue Power Plans - IFC
18-Apr-26
27-Dec-26
5%
EM020ELEJ2
02 Develop & Issue Lighting Plans - IFC
27-Dec-26
27-Dec-26
0%
EM020ELEN1
02 LV WIRING DIAGRAMS & CTL SCHEMATICS
30-Dec-26
29-Jan-27
512.0d
0%
EM020ELEN2
02 MV WIRING DIAGRAMS & CTL SCHEMATICS
30-Dec-26
29-Jan-27
512.0d
0%
EM020ELEN3
02 Equipment Interconnection Diagrams
30-Dec-26
30-Jan-27
511.0d
0%
26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul 04-Aug 11-Aug 18-Aug 25-Aug 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan Data Date
EM02AEL120 — 02A Electrical Conceptual Layouts | 27-Jun-25 → 30-Aug-25 | Complete 100% | float — EM02AEL120 EM02BEL120 — 02B Electrical Conceptual Layouts | 27-Jun-25 → 21-Sep-25 | Complete 100% | float — EM02BEL120 EM02EEL120 — 02E Electrical Conceptual Layouts | 01-Jul-25 → 30-Aug-25 | Complete 100% | float — EM02EEL120 EM02YEL120 — 02Y Electrical Conceptual Layouts | 08-Jul-25 → 30-Aug-25 | Complete 100% | float — EM02YEL120 EM02HEL120 — 02H Electrical Conceptual Layouts | 11-Jul-25 → 30-Aug-25 | Complete 100% | float — EM02HEL120 EM02LEL120 — 02L Electrical Conceptual Layouts | 23-Jul-25 → 04-Oct-25 | Complete 100% | float — EM02LEL120 EM02KEL120 — 02K Electrical Conceptual Layouts | 05-Aug-25 → 28-Sep-25 | Complete 100% | float — EM02KEL120 EM02GEL120 — 02G Electrical Conceptual Layouts | 05-Aug-25 → 06-Nov-25 | Complete 100% | float — EM02GEL120 EM02NEL120 — 02N Electrical Conceptual Layouts | 12-Aug-25 → 05-Oct-25 | Complete 100% | float — EM02NEL120 EM02MEL120 — 02M Electrical Conceptual Layouts | 12-Aug-25 → 19-Oct-25 | Complete 100% | float — EM02MEL120 EM02JEL120 — 02J Electrical Conceptual Layouts | 12-Aug-25 → 01-Nov-25 | Complete 100% | float — EM02JEL120 EM02CEL120 — 02C Electrical Conceptual Layouts | 27-Aug-25 → 27-Sep-25 | Complete 100% | float — EM02CEL120 EM02QEL120 — 02Q Electrical Conceptual Layouts | 10-Sep-25 → 12-Oct-25 | Complete 100% | float — EM02QEL120 EM020ELEL2 — 02 U/G Electrical Routing Plans - IFC | 16-Sep-25 → 27-Dec-26 | In Progress 47% | float — EM020ELEL2 EM02FEL120 — 02F Electrical Conceptual Layouts | 21-Sep-25 → 27-Sep-25 | Complete 100% | float — EM02FEL120 EM020ELEH2 — 02 Develop & Issue Earthing / Grounding Dwgs - IFC | 24-Sep-25 → 27-Dec-26 | In Progress 46% | float — EM020ELEH2 EM02DEL120 — 02D Electrical Conceptual Layouts | 30-Sep-25 → 15-Nov-25 | Complete 100% | float — EM02DEL120 EM02PEL120 — 02P Electrical Conceptual Layouts | 19-Nov-25 → 04-Dec-25 | Complete 100% | float — EM02PEL120 EM20ELEK2 — 02 Develop & Issue Cable Ladder Plans - IFC | 03-Mar-26 → 27-Dec-26 | In Progress 17% | float — EM20ELEK2 EM020ELEK2 — 02 Develop & Issue Power Plans - IFC | 18-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM020ELEK2 EM020ELEJ2 — 02 Develop & Issue Lighting Plans - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM020ELEN1 — 02 LV WIRING DIAGRAMS & CTL SCHEMATICS | 30-Dec-26 → 29-Jan-27 | Not Started 0% | float 512.0d EM020ELEN1 EM020ELEN2 — 02 MV WIRING DIAGRAMS & CTL SCHEMATICS | 30-Dec-26 → 29-Jan-27 | Not Started 0% | float 512.0d EM020ELEN2 EM020ELEN3 — 02 Equipment Interconnection Diagrams | 30-Dec-26 → 30-Jan-27 | Not Started 0% | float 511.0d EM020ELEN3