Legend: Not Started In Progress Complete Critical Milestone Showing 32 activities in SY Systems Engineering × clear
Code
Activity
Start
Finish
Flt
%
EM02BSY172
02B P&IDs & Line List Issue - IFD
18-Mar-26
18-Mar-26
100%
EM02PSY172
02P P&IDs & Line List Issue - IFD
19-Mar-26
19-Mar-26
100%
EM02NSY172
02N P&IDs & Line List Issue - IFD
10-Apr-26
10-Apr-26
100%
EM02BSY272
02B P&IDs & Line List Issue - IFC
17-Apr-26
17-Apr-26
100%
EM02DSY172
02D P&IDs & Line List Issue - IFD
22-Apr-26
22-Apr-26
100%
EM02ASY172
02A P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM02ASY272
02A P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM02CSY172
02C P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM02CSY272
02C P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM02DSY272
02D P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM02ESY172
02E P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM02ESY272
02E P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM02FSY172
02F P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM02FSY272
02F P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM02GSY172
02G P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM02HSY172
02H P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM02HSY272
02H P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM02JSY172
02J P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM02JSY272
02J P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM02KSY172
02K P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM02KSY272
02K P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM02LSY172
02L P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM02LSY272
02L P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM02MSY172
02M P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM02MSY272
02M P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM02NSY272
02N P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM02PSY272
02P P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM02QSY172
02Q P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM02QSY272
02Q P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM02YSY172
02Y P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM02YSY272
02Y P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM02GSY272
02G P&IDs & Line List Issue - IFC
03-Jan-27
03-Jan-27
0%
Q1 2026 Q2 2026 Q3 2026 Q4 2026 Q1 2027 Data Date
EM02BSY172 — 02B P&IDs & Line List Issue - IFD | 18-Mar-26 | Complete EM02PSY172 — 02P P&IDs & Line List Issue - IFD | 19-Mar-26 | Complete EM02NSY172 — 02N P&IDs & Line List Issue - IFD | 10-Apr-26 | Complete EM02BSY272 — 02B P&IDs & Line List Issue - IFC | 17-Apr-26 | Complete EM02DSY172 — 02D P&IDs & Line List Issue - IFD | 22-Apr-26 | Complete EM02ASY172 — 02A P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM02ASY272 — 02A P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM02CSY172 — 02C P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM02CSY272 — 02C P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM02DSY272 — 02D P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM02ESY172 — 02E P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM02ESY272 — 02E P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM02FSY172 — 02F P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM02FSY272 — 02F P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM02GSY172 — 02G P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM02HSY172 — 02H P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM02HSY272 — 02H P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM02JSY172 — 02J P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM02JSY272 — 02J P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM02KSY172 — 02K P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM02KSY272 — 02K P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM02LSY172 — 02L P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM02LSY272 — 02L P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM02MSY172 — 02M P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM02MSY272 — 02M P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM02NSY272 — 02N P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM02PSY272 — 02P P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM02QSY172 — 02Q P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM02QSY272 — 02Q P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM02YSY172 — 02Y P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM02YSY272 — 02Y P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM02GSY272 — 02G P&IDs & Line List Issue - IFC | 03-Jan-27 | Not Started