Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 36 activities in EBCL EBIC Client × clear
Code
Activity
Start
Finish
Flt
%
EK000EB005
Approve Project Coordination Procedure (EBIC)
26-Feb-25
30-May-25
100%
XE000K0110
(EBIC) Clear & Level EBIC Site (by Owner)
07-Oct-25
30-Nov-25
100%
EK000EB010
Client to confirm Gas Composition (EBIC)
15-Oct-25
15-Oct-25
100%
XE000OW160
(EBIC) Execute Contracts - EPC
17-Oct-25
17-Oct-25
100%
XE000OW301
05B SPDC TO Provide Required Eng. Data
29-Jan-26
27-Dec-26
26%
XE000OW341
(EBIC) Permit - Wall
21-Feb-26
21-Feb-26
100%
XE000OW290
(EBIC) Telephones @ Site & Port
27-Feb-26
27-Feb-26
100%
XE000OW300
04A SPDC TO Provide Required Eng. Data
24-Mar-26
27-Dec-26
11%
XE000OW270
(EBIC) Permit - Buildings (SIDC)
30-Mar-26
30-Mar-26
100%
XE000OW305
(EBIC) Permit - Free Zone Status (SIDC)
27-Dec-26
27-Dec-26
0%
XE000OW310
(EBIC) Arrange For Solid Waste Collection/Disposal
27-Dec-26
27-Dec-26
0%
XE000OW325
(EBIC) Tie-In Construction Elec Power Supply
27-Dec-26
27-Dec-26
0%
XE000OW373
(EBIC) Permit - Free Zone Status (SPDC)
27-Dec-26
27-Dec-26
0%
XE05AOW340
(EBIC) Clear & Level Site For Ammonia Storage
27-Dec-26
27-Dec-26
0%
XE000OW335
(EBIC) Permit - Land Easement (SIDC Assistance)
28-Dec-26
28-Dec-26
750.0d
0%
XE000OW340
(EBIC) Permit - Tanks (SIDC)
28-Dec-26
28-Dec-26
750.0d
0%
XE000OW345
(EBIC) Purchase Chemicals For Operation
28-Dec-26
28-Dec-26
750.0d
0%
XE000OW355
(EBIC) Tie-In Municipal Water To Site
28-Dec-26
28-Dec-26
353.0d
0%
XE000OW370
(EBIC) Permit - Tanks (SPDC)
28-Dec-26
28-Dec-26
750.0d
0%
XE000OW375
(EBIC) Tie-In Site Electrical Power Supply
28-Dec-26
28-Dec-26
297.0d
0%
XE000OW405
(EBIC) Tie-In Port Elec Power Supply To Substation
28-Dec-26
28-Dec-26
750.0d
0%
XE000OW230
(EBIC) Permit - Operating Permit (SPDC)
01-Jan-27
01-Jan-27
746.0d
0%
XE000OW374
(EBIC) Permit - Operating Permit (SIDC)
01-Jan-27
01-Jan-27
746.0d
0%
XE000OW350
(EBIC) Clear & Level Site For Corridor Piping
29-Jan-27
29-Jan-27
126.0d
0%
XE000OW410
(EBIC) Tie-In Port Fire Water Supply
02-Mar-27
02-Mar-27
686.0d
0%
XE000OW420
(EBIC) Tie-In Port Municipal Water Supply
02-Mar-27
02-Mar-27
686.0d
0%
XE000OW380
(EBIC) Communication System @ Port
02-Apr-27
02-Apr-27
655.0d
0%
XE000OW360
(EBIC) Tie-In Natural Gas Line To Site
03-May-27
03-May-27
624.0d
0%
XE000OW425
(EBIC) Tie-In Port Natural Gas
03-May-27
03-May-27
624.0d
0%
XE000OW120
(EBIC) Arrange For First Shipment Of Product
01-Jun-27
01-Jun-27
595.0d
0%
XE05BM0150
05B (EBIC) 05B Liquid Cargo Birth at Port (By Owner)
02-Aug-27
02-Aug-27
94.0d
0%
XE000OW450
(EBIC) Operator Training
30-Sep-27
30-Sep-27
473.0d
0%
XE000OW470
(EBIC) Purchase First Gas
28-Oct-27
28-Oct-27
446.0d
0%
XE000OW455
(EBIC) Nitrogen Supply & Storage @ Port
02-Dec-27
02-Dec-27
411.0d
0%
XE000OW460
(EBIC) Nitrogen Supply & Storage @ Site
02-Dec-27
02-Dec-27
411.0d
0%
XE000OW365
(EBIC) Tie-In Site Paved Road, Street Lighting
28-Jan-28
28-Jan-28
11.0d
0%
27-Jan 03-Feb 10-Feb 17-Feb 24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul 04-Aug 11-Aug 18-Aug 25-Aug 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan 01-Feb 08-Feb 15-Feb 22-Feb 01-Mar 08-Mar 15-Mar 22-Mar 29-Mar 05-Apr 12-Apr 19-Apr 26-Apr 03-May 10-May 17-May 24-May 31-May 07-Jun 14-Jun 21-Jun 28-Jun 05-Jul 12-Jul 19-Jul 26-Jul 02-Aug 09-Aug 16-Aug 23-Aug 30-Aug 06-Sep 13-Sep 20-Sep 27-Sep 04-Oct 11-Oct 18-Oct 25-Oct 01-Nov 08-Nov 15-Nov 22-Nov 29-Nov 06-Dec 13-Dec 20-Dec 27-Dec 03-Jan 10-Jan 17-Jan 24-Jan 31-Jan Data Date
EK000EB005 — Approve Project Coordination Procedure (EBIC) | 26-Feb-25 → 30-May-25 | Complete 100% | float — EK000EB005 XE000K0110 — (EBIC) Clear & Level EBIC Site (by Owner) | 07-Oct-25 → 30-Nov-25 | Complete 100% | float — XE000K0110 EK000EB010 — Client to confirm Gas Composition (EBIC) | 15-Oct-25 | Complete XE000OW160 — (EBIC) Execute Contracts - EPC | 17-Oct-25 | Complete XE000OW301 — 05B SPDC TO Provide Required Eng. Data | 29-Jan-26 → 27-Dec-26 | In Progress 26% | float — XE000OW301 XE000OW341 — (EBIC) Permit - Wall | 21-Feb-26 | Complete XE000OW290 — (EBIC) Telephones @ Site & Port | 27-Feb-26 | Complete XE000OW300 — 04A SPDC TO Provide Required Eng. Data | 24-Mar-26 → 27-Dec-26 | In Progress 11% | float — XE000OW300 XE000OW270 — (EBIC) Permit - Buildings (SIDC) | 30-Mar-26 | Complete XE000OW305 — (EBIC) Permit - Free Zone Status (SIDC) | 27-Dec-26 | Not Started XE000OW310 — (EBIC) Arrange For Solid Waste Collection/Disposal | 27-Dec-26 | Not Started XE000OW325 — (EBIC) Tie-In Construction Elec Power Supply | 27-Dec-26 | Not Started XE000OW373 — (EBIC) Permit - Free Zone Status (SPDC) | 27-Dec-26 | Not Started XE05AOW340 — (EBIC) Clear & Level Site For Ammonia Storage | 27-Dec-26 | Not Started XE000OW335 — (EBIC) Permit - Land Easement (SIDC Assistance) | 28-Dec-26 | Not Started XE000OW340 — (EBIC) Permit - Tanks (SIDC) | 28-Dec-26 | Not Started XE000OW345 — (EBIC) Purchase Chemicals For Operation | 28-Dec-26 | Not Started XE000OW355 — (EBIC) Tie-In Municipal Water To Site | 28-Dec-26 | Not Started XE000OW370 — (EBIC) Permit - Tanks (SPDC) | 28-Dec-26 | Not Started XE000OW375 — (EBIC) Tie-In Site Electrical Power Supply | 28-Dec-26 | Not Started XE000OW405 — (EBIC) Tie-In Port Elec Power Supply To Substation | 28-Dec-26 | Not Started XE000OW230 — (EBIC) Permit - Operating Permit (SPDC) | 01-Jan-27 | Not Started XE000OW374 — (EBIC) Permit - Operating Permit (SIDC) | 01-Jan-27 | Not Started XE000OW350 — (EBIC) Clear & Level Site For Corridor Piping | 29-Jan-27 | Not Started XE000OW410 — (EBIC) Tie-In Port Fire Water Supply | 02-Mar-27 | Not Started XE000OW420 — (EBIC) Tie-In Port Municipal Water Supply | 02-Mar-27 | Not Started XE000OW380 — (EBIC) Communication System @ Port | 02-Apr-27 | Not Started XE000OW360 — (EBIC) Tie-In Natural Gas Line To Site | 03-May-27 | Not Started XE000OW425 — (EBIC) Tie-In Port Natural Gas | 03-May-27 | Not Started XE000OW120 — (EBIC) Arrange For First Shipment Of Product | 01-Jun-27 | Not Started XE05BM0150 — 05B (EBIC) 05B Liquid Cargo Birth at Port (By Owner) | 02-Aug-27 | Not Started XE000OW450 — (EBIC) Operator Training | 30-Sep-27 | Not Started XE000OW470 — (EBIC) Purchase First Gas | 28-Oct-27 | Not Started XE000OW455 — (EBIC) Nitrogen Supply & Storage @ Port | 02-Dec-27 | Not Started XE000OW460 — (EBIC) Nitrogen Supply & Storage @ Site | 02-Dec-27 | Not Started XE000OW365 — (EBIC) Tie-In Site Paved Road, Street Lighting | 28-Jan-28 | Not Started