Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 14 activities in C1 Concrete Paving × clear
Code
Activity
Start
Finish
Flt
%
CO02YC0130
02Y Install Paving
30-Jan-27
17-Mar-27
71.0d
0%
WO020C0110
020 Concrete Paving
30-Jan-27
22-May-27
210.0d
0%
CO02CC0130
02C Install Paving
20-Feb-27
05-Mar-27
162.0d
0%
CO02LC0130
02L Install Paving
20-Feb-27
05-Mar-27
123.0d
0%
CO02GC0130
02G Install Paving
13-Mar-27
26-Mar-27
159.0d
0%
CO02AC0130
02A Install Paving
24-Mar-27
30-Mar-27
189.0d
0%
CO02HC0130
02H Install Paving
03-Apr-27
16-Apr-27
120.0d
0%
CO02JC0130
02J Install Paving
05-Apr-27
10-Apr-27
168.0d
0%
CO02KC0130
02K Install Paving
12-Apr-27
17-Apr-27
165.0d
0%
CO02EC0130
02E Install Paving
19-Apr-27
24-Apr-27
172.0d
0%
CO02FC0130
02F Install Paving
26-Apr-27
01-May-27
173.0d
0%
CO02MC0130
02M Install Paving
03-May-27
08-May-27
172.0d
0%
CO02DC0130
02D Install Paving
10-May-27
15-May-27
175.0d
0%
CO02BC0130
02B Install Paving
17-May-27
22-May-27
210.0d
0%
28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May Data Date
CO02YC0130 — 02Y Install Paving | 30-Jan-27 → 17-Mar-27 | Not Started 0% | float 71.0d CO02YC0130 WO020C0110 — 020 Concrete Paving | 30-Jan-27 → 22-May-27 | Not Started 0% | float 210.0d WO020C0110 CO02CC0130 — 02C Install Paving | 20-Feb-27 → 05-Mar-27 | Not Started 0% | float 162.0d CO02CC0130 CO02LC0130 — 02L Install Paving | 20-Feb-27 → 05-Mar-27 | Not Started 0% | float 123.0d CO02LC0130 CO02GC0130 — 02G Install Paving | 13-Mar-27 → 26-Mar-27 | Not Started 0% | float 159.0d CO02GC0130 CO02AC0130 — 02A Install Paving | 24-Mar-27 → 30-Mar-27 | Not Started 0% | float 189.0d CO02AC0130 CO02HC0130 — 02H Install Paving | 03-Apr-27 → 16-Apr-27 | Not Started 0% | float 120.0d CO02HC0130 CO02JC0130 — 02J Install Paving | 05-Apr-27 → 10-Apr-27 | Not Started 0% | float 168.0d CO02JC0130 CO02KC0130 — 02K Install Paving | 12-Apr-27 → 17-Apr-27 | Not Started 0% | float 165.0d CO02KC0130 CO02EC0130 — 02E Install Paving | 19-Apr-27 → 24-Apr-27 | Not Started 0% | float 172.0d CO02EC0130 CO02FC0130 — 02F Install Paving | 26-Apr-27 → 01-May-27 | Not Started 0% | float 173.0d CO02FC0130 CO02MC0130 — 02M Install Paving | 03-May-27 → 08-May-27 | Not Started 0% | float 172.0d CO02MC0130 CO02DC0130 — 02D Install Paving | 10-May-27 → 15-May-27 | Not Started 0% | float 175.0d CO02DC0130 CO02BC0130 — 02B Install Paving | 17-May-27 → 22-May-27 | Not Started 0% | float 210.0d CO02BC0130