Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 33 activities in V2 Insulation × clear
Code
Activity
Start
Finish
Flt
%
CO02CV2110
02C Insulate - Equipment
28-May-27
06-Jul-27
190.0d
0%
WO020V2100
020 Insulation
28-May-27
13-Mar-28
-1.0d
0%
CO02HM0245
02H Install Insulation (101-B)
31-May-27
24-Jul-27
174.0d
0%
CO02FV2110
02F Insulate - Equipment
07-Jun-27
24-Jun-27
200.0d
0%
CO02KV2110
02K Insulate - Equipment
10-Jun-27
05-Jul-27
192.0d
0%
CO02BV2110
02B Insulate - Equipment
14-Jun-27
19-Jun-27
204.0d
0%
CO02AV2110
02A Insulate - Equipment
25-Jun-27
16-Jul-27
181.0d
0%
CO02DV2110
02D Insulate - Equipment
25-Jun-27
09-Jul-27
187.0d
0%
CO02MV2110
02M Insulate - Equipment
10-Jul-27
27-Jul-27
172.0d
0%
CO02EV2110
02E Insulate - Equipment
31-Jul-27
27-Aug-27
151.0d
0%
CO02NV2110
02N Insulate - Equipment
13-Aug-27
08-Sep-27
146.0d
0%
CO02LV2110
02L Insulate - Equipment
16-Aug-27
26-Oct-27
69.0d
0%
CO02GV2120
02G Insulate - Piping
03-Sep-27
30-Oct-27
110.0d
0%
CO02GV2110
02G Insulate - Equipment
10-Sep-27
23-Oct-27
116.0d
0%
CO02CV2120
02C Insulate - Piping
29-Sep-27
25-Nov-27
92.0d
0%
CO02YV2120
02Y Insulate - Piping
29-Sep-27
27-Dec-27
65.0d
0%
CO02JV2120
02J Insulate - Piping
06-Oct-27
08-Nov-27
102.0d
0%
CO02QV2110
02Q Insulate - Equipment
11-Oct-27
16-Oct-27
121.0d
0%
CO02BV2120
02B Insulate - Piping
12-Oct-27
18-Oct-27
120.0d
0%
CO02FV2120
02F Insulate - Piping
14-Oct-27
08-Nov-27
102.0d
0%
CO02JV2110
02J Insulate - Equipment
14-Oct-27
08-Nov-27
102.0d
0%
CO02HV2110
02H Insulate - Equipment
16-Oct-27
01-Dec-27
52.0d
0%
CO02PV2120
02P Insulate - Piping
27-Oct-27
02-Nov-27
107.0d
0%
CO02MV2120
02M Insulate - Piping
28-Oct-27
25-Nov-27
92.0d
0%
CO02PV2110
02P Insulate - Equipment
01-Nov-27
06-Nov-27
103.0d
0%
CO02KV2120
02K Insulate - Piping
02-Nov-27
10-Dec-27
80.0d
0%
CO02QV2120
02Q Insulate - Piping
03-Nov-27
09-Nov-27
101.0d
0%
CO02AV2120
02A Insulate - Piping
05-Nov-27
10-Dec-27
79.0d
0%
CO02EV2120
02E Insulate - Piping
27-Nov-27
24-Dec-27
67.0d
0%
CO02DV2120
02D Insulate - Piping
10-Dec-27
30-Dec-27
62.0d
0%
CO02HV2120
02H Insulate - Piping
24-Dec-27
16-Feb-28
21.0d
0%
CO02NV2120
02N Insulate - Piping
24-Dec-27
06-Jan-28
56.0d
0%
CO02LV2120
02L Insulate - Piping
05-Jan-28
13-Mar-28
-1.0d
0%
26-Apr 03-May 10-May 17-May 24-May 31-May 07-Jun 14-Jun 21-Jun 28-Jun 05-Jul 12-Jul 19-Jul 26-Jul 02-Aug 09-Aug 16-Aug 23-Aug 30-Aug 06-Sep 13-Sep 20-Sep 27-Sep 04-Oct 11-Oct 18-Oct 25-Oct 01-Nov 08-Nov 15-Nov 22-Nov 29-Nov 06-Dec 13-Dec 20-Dec 27-Dec 03-Jan 10-Jan 17-Jan 24-Jan 31-Jan 07-Feb 14-Feb 21-Feb 28-Feb 06-Mar 13-Mar 20-Mar 27-Mar Data Date
CO02CV2110 — 02C Insulate - Equipment | 28-May-27 → 06-Jul-27 | Not Started 0% | float 190.0d CO02CV2110 WO020V2100 — 020 Insulation | 28-May-27 → 13-Mar-28 | Not Started 0% | float -1.0d WO020V2100 CO02HM0245 — 02H Install Insulation (101-B) | 31-May-27 → 24-Jul-27 | Not Started 0% | float 174.0d CO02HM0245 CO02FV2110 — 02F Insulate - Equipment | 07-Jun-27 → 24-Jun-27 | Not Started 0% | float 200.0d CO02FV2110 CO02KV2110 — 02K Insulate - Equipment | 10-Jun-27 → 05-Jul-27 | Not Started 0% | float 192.0d CO02KV2110 CO02BV2110 — 02B Insulate - Equipment | 14-Jun-27 → 19-Jun-27 | Not Started 0% | float 204.0d CO02BV2110 CO02AV2110 — 02A Insulate - Equipment | 25-Jun-27 → 16-Jul-27 | Not Started 0% | float 181.0d CO02AV2110 CO02DV2110 — 02D Insulate - Equipment | 25-Jun-27 → 09-Jul-27 | Not Started 0% | float 187.0d CO02DV2110 CO02MV2110 — 02M Insulate - Equipment | 10-Jul-27 → 27-Jul-27 | Not Started 0% | float 172.0d CO02MV2110 CO02EV2110 — 02E Insulate - Equipment | 31-Jul-27 → 27-Aug-27 | Not Started 0% | float 151.0d CO02EV2110 CO02NV2110 — 02N Insulate - Equipment | 13-Aug-27 → 08-Sep-27 | Not Started 0% | float 146.0d CO02NV2110 CO02LV2110 — 02L Insulate - Equipment | 16-Aug-27 → 26-Oct-27 | Not Started 0% | float 69.0d CO02LV2110 CO02GV2120 — 02G Insulate - Piping | 03-Sep-27 → 30-Oct-27 | Not Started 0% | float 110.0d CO02GV2120 CO02GV2110 — 02G Insulate - Equipment | 10-Sep-27 → 23-Oct-27 | Not Started 0% | float 116.0d CO02GV2110 CO02CV2120 — 02C Insulate - Piping | 29-Sep-27 → 25-Nov-27 | Not Started 0% | float 92.0d CO02CV2120 CO02YV2120 — 02Y Insulate - Piping | 29-Sep-27 → 27-Dec-27 | Not Started 0% | float 65.0d CO02YV2120 CO02JV2120 — 02J Insulate - Piping | 06-Oct-27 → 08-Nov-27 | Not Started 0% | float 102.0d CO02JV2120 CO02QV2110 — 02Q Insulate - Equipment | 11-Oct-27 → 16-Oct-27 | Not Started 0% | float 121.0d CO02QV2110 CO02BV2120 — 02B Insulate - Piping | 12-Oct-27 → 18-Oct-27 | Not Started 0% | float 120.0d CO02BV2120 CO02FV2120 — 02F Insulate - Piping | 14-Oct-27 → 08-Nov-27 | Not Started 0% | float 102.0d CO02FV2120 CO02JV2110 — 02J Insulate - Equipment | 14-Oct-27 → 08-Nov-27 | Not Started 0% | float 102.0d CO02JV2110 CO02HV2110 — 02H Insulate - Equipment | 16-Oct-27 → 01-Dec-27 | Not Started 0% | float 52.0d CO02HV2110 CO02PV2120 — 02P Insulate - Piping | 27-Oct-27 → 02-Nov-27 | Not Started 0% | float 107.0d CO02PV2120 CO02MV2120 — 02M Insulate - Piping | 28-Oct-27 → 25-Nov-27 | Not Started 0% | float 92.0d CO02MV2120 CO02PV2110 — 02P Insulate - Equipment | 01-Nov-27 → 06-Nov-27 | Not Started 0% | float 103.0d CO02PV2110 CO02KV2120 — 02K Insulate - Piping | 02-Nov-27 → 10-Dec-27 | Not Started 0% | float 80.0d CO02KV2120 CO02QV2120 — 02Q Insulate - Piping | 03-Nov-27 → 09-Nov-27 | Not Started 0% | float 101.0d CO02QV2120 CO02AV2120 — 02A Insulate - Piping | 05-Nov-27 → 10-Dec-27 | Not Started 0% | float 79.0d CO02AV2120 CO02EV2120 — 02E Insulate - Piping | 27-Nov-27 → 24-Dec-27 | Not Started 0% | float 67.0d CO02EV2120 CO02DV2120 — 02D Insulate - Piping | 10-Dec-27 → 30-Dec-27 | Not Started 0% | float 62.0d CO02DV2120 CO02HV2120 — 02H Insulate - Piping | 24-Dec-27 → 16-Feb-28 | Not Started 0% | float 21.0d CO02HV2120 CO02NV2120 — 02N Insulate - Piping | 24-Dec-27 → 06-Jan-28 | Not Started 0% | float 56.0d CO02NV2120 CO02LV2120 — 02L Insulate - Piping | 05-Jan-28 → 13-Mar-28 | Not Started 0% | float -1.0d CO02LV2120