Flt
%
CO02CV2110
02C Insulate - Equipment
28-May-27
06-Jul-27
190.0d
0%
WO020V2100
020 Insulation
28-May-27
13-Mar-28
-1.0d
0%
CO02HM0245
02H Install Insulation (101-B)
31-May-27
24-Jul-27
174.0d
0%
CO02FV2110
02F Insulate - Equipment
07-Jun-27
24-Jun-27
200.0d
0%
CO02KV2110
02K Insulate - Equipment
10-Jun-27
05-Jul-27
192.0d
0%
CO02BV2110
02B Insulate - Equipment
14-Jun-27
19-Jun-27
204.0d
0%
CO02AV2110
02A Insulate - Equipment
25-Jun-27
16-Jul-27
181.0d
0%
CO02DV2110
02D Insulate - Equipment
25-Jun-27
09-Jul-27
187.0d
0%
CO02MV2110
02M Insulate - Equipment
10-Jul-27
27-Jul-27
172.0d
0%
CO02EV2110
02E Insulate - Equipment
31-Jul-27
27-Aug-27
151.0d
0%
CO02NV2110
02N Insulate - Equipment
13-Aug-27
08-Sep-27
146.0d
0%
CO02LV2110
02L Insulate - Equipment
16-Aug-27
26-Oct-27
69.0d
0%
CO02GV2120
02G Insulate - Piping
03-Sep-27
30-Oct-27
110.0d
0%
CO02GV2110
02G Insulate - Equipment
10-Sep-27
23-Oct-27
116.0d
0%
CO02CV2120
02C Insulate - Piping
29-Sep-27
25-Nov-27
92.0d
0%
CO02YV2120
02Y Insulate - Piping
29-Sep-27
27-Dec-27
65.0d
0%
CO02JV2120
02J Insulate - Piping
06-Oct-27
08-Nov-27
102.0d
0%
CO02QV2110
02Q Insulate - Equipment
11-Oct-27
16-Oct-27
121.0d
0%
CO02BV2120
02B Insulate - Piping
12-Oct-27
18-Oct-27
120.0d
0%
CO02FV2120
02F Insulate - Piping
14-Oct-27
08-Nov-27
102.0d
0%
CO02JV2110
02J Insulate - Equipment
14-Oct-27
08-Nov-27
102.0d
0%
CO02HV2110
02H Insulate - Equipment
16-Oct-27
01-Dec-27
52.0d
0%
CO02PV2120
02P Insulate - Piping
27-Oct-27
02-Nov-27
107.0d
0%
CO02MV2120
02M Insulate - Piping
28-Oct-27
25-Nov-27
92.0d
0%
CO02PV2110
02P Insulate - Equipment
01-Nov-27
06-Nov-27
103.0d
0%
CO02KV2120
02K Insulate - Piping
02-Nov-27
10-Dec-27
80.0d
0%
CO02QV2120
02Q Insulate - Piping
03-Nov-27
09-Nov-27
101.0d
0%
CO02AV2120
02A Insulate - Piping
05-Nov-27
10-Dec-27
79.0d
0%
CO02EV2120
02E Insulate - Piping
27-Nov-27
24-Dec-27
67.0d
0%
CO02DV2120
02D Insulate - Piping
10-Dec-27
30-Dec-27
62.0d
0%
CO02HV2120
02H Insulate - Piping
24-Dec-27
16-Feb-28
21.0d
0%
CO02NV2120
02N Insulate - Piping
24-Dec-27
06-Jan-28
56.0d
0%
CO02LV2120
02L Insulate - Piping
05-Jan-28
13-Mar-28
-1.0d
0%