EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 50 activities in V1 Painting × clear
Code
Activity
Start
Finish
Flt
%
CO02UV1110
02U Paint Fabricated Pipe Spools (CW & Misc Headers)
28-Dec-26
28-Dec-26
0%
CO02CV1110
02C Paint Fabricated Pipe Spools
20-Jan-27
27-Feb-27
245.0d
0%
WO020V1100
020 Paint
20-Jan-27
14-Feb-28
23.0d
0%
CO02BV1130
02B Paint Touch-up - Equipment
25-Jan-27
01-Feb-27
300.0d
0%
CO02YV1110
02Y Paint Fabricated Pipe Spools
05-Feb-27
19-Feb-27
131.0d
0%
CO02EV1110
02E Paint Fabricated Pipe Spools
12-Feb-27
04-Mar-27
250.0d
0%
CO02GV1110
02G Paint Fabricated Pipe Spools
16-Feb-27
22-Mar-27
230.0d
0%
CO02KV1130
02K Paint Touch-up - Equipment
23-Mar-27
15-Apr-27
236.0d
0%
CO02JV1110
02J Paint Fabricated Pipe Spools
27-Mar-27
27-Mar-27
164.0d
0%
CO02AV1130
02A Paint Touch-up - Equipment
30-Mar-27
20-Apr-27
232.0d
0%
CO02MV1110
02M Paint Fabricated Pipe Spools
01-Apr-27
14-Apr-27
215.0d
0%
CO02NV1110
02N Paint Fabricated Pipe Spools
01-Apr-27
03-Apr-27
216.0d
0%
CO02FV1110
02F Paint Fabricated Pipe Spools
09-Apr-27
27-Apr-27
204.0d
0%
CO02LV1110
02L Paint Fabricated Pipe Spools
09-Apr-27
29-May-27
162.0d
0%
CO02KV1110
02K Paint Fabricated Pipe Spools
10-Apr-27
04-May-27
181.0d
0%
CO02DV1130
02D Paint Touch-up - Equipment
15-Apr-27
29-Apr-27
224.0d
0%
CO02QV1110
02Q Paint Fabricated Pipe Spools
16-Apr-27
20-Apr-27
210.0d
0%
CO02DV1110
02D Paint Fabricated Pipe Spools
23-Apr-27
07-May-27
177.0d
0%
CO02PV1110
02P Paint Fabricated Pipe Spools
24-Apr-27
28-Apr-27
199.0d
0%
CO02HV1110
02H Paint Fabricated Pipe Spools
26-Apr-27
05-Jun-27
54.0d
0%
CO02FV1130
02F Paint Touch-up - Equipment
10-May-27
27-May-27
200.0d
0%
CO02CV1130
02C Paint Touch-up - Equipment
14-May-27
22-Jun-27
190.0d
0%
CO02AV1110
02A Paint Fabricated Pipe Spools
20-May-27
02-Jun-27
172.0d
0%
CO02BV1110
02B Paint Fabricated Pipe Spools
25-May-27
31-May-27
175.0d
0%
CO02MV1130
02M Paint Touch-up - Equipment
12-Jun-27
29-Jun-27
172.0d
0%
CO02EV1130
02E Paint Touch-up - Equipment
03-Jul-27
23-Jul-27
151.0d
0%
CO02LV1130
02L Paint Touch-up - Equipment
17-Jul-27
28-Sep-27
69.0d
0%
CO02NV1130
02N Paint Touch-up - Equipment
23-Jul-27
29-Jul-27
146.0d
0%
CO02YV1120
02Y Paint Touch-up - Piping
27-Jul-27
09-Nov-27
101.0d
0%
CO02YV1130
02Y Paint Touch-up - Pipe Rack
27-Jul-27
09-Nov-27
101.0d
0%
CO02GV1130
02G Paint Touch-up - Equipment
30-Jul-27
25-Sep-27
116.0d
0%
CO02GV1120
02G Paint Touch-up - Piping
06-Aug-27
02-Oct-27
134.0d
0%
CO02BV1120
02B Paint Touch-up - Piping
01-Sep-27
20-Sep-27
144.0d
0%
CO02CV1120
02C Paint Touch-up - Piping
01-Sep-27
22-Oct-27
116.0d
0%
CO02JV1120
02J Paint Touch-up - Piping
06-Sep-27
11-Oct-27
102.0d
0%
CO02JV1130
02J Paint Touch-up - Equipment
06-Sep-27
11-Oct-27
102.0d
0%
CO02HV1130
02H Paint Touch-up - Equipment
10-Sep-27
28-Oct-27
52.0d
0%
CO02FV1120
02F Paint Touch-up - Piping
23-Sep-27
11-Oct-27
126.0d
0%
CO02PV1130
02P Paint Touch-up - Equipment
29-Sep-27
02-Oct-27
103.0d
0%
CO02PV1120
02P Paint Touch-up - Piping
01-Oct-27
05-Oct-27
125.0d
0%
CO02MV1120
02M Paint Touch-up - Piping
06-Oct-27
22-Oct-27
116.0d
0%
CO02QV1120
02Q Paint Touch-up - Piping
06-Oct-27
09-Oct-27
121.0d
0%
CO02QV1130
02Q Paint Touch-up - Equipment
06-Oct-27
09-Oct-27
121.0d
0%
CO02KV1120
02K Paint Touch-up - Piping
13-Oct-27
06-Nov-27
104.0d
0%
CO02AV1120
02A Paint Touch-up - Piping
16-Oct-27
06-Nov-27
103.0d
0%
CO02EV1120
02E Paint Touch-up - Piping
01-Nov-27
26-Nov-27
91.0d
0%
CO02DV1120
02D Paint Touch-up - Piping
12-Nov-27
02-Dec-27
86.0d
0%
CO02NV1120
02N Paint Touch-up - Piping
18-Nov-27
30-Nov-27
88.0d
0%
CO02HV1120
02H Paint Touch-up - Piping
10-Dec-27
19-Jan-28
45.0d
0%
CO02LV1120
02L Paint Touch-up - Piping
25-Dec-27
14-Feb-28
23.0d
0%
Q4 2026 Q1 2027 Q2 2027 Q3 2027 Q4 2027 Q1 2028 Data Date
CO02UV1110 — 02U Paint Fabricated Pipe Spools (CW & Misc Headers) | 28-Dec-26 → 28-Dec-26 | Not Started 0% | float — CO02CV1110 — 02C Paint Fabricated Pipe Spools | 20-Jan-27 → 27-Feb-27 | Not Started 0% | float 245.0d CO02CV1110 WO020V1100 — 020 Paint | 20-Jan-27 → 14-Feb-28 | Not Started 0% | float 23.0d WO020V1100 CO02BV1130 — 02B Paint Touch-up - Equipment | 25-Jan-27 → 01-Feb-27 | Not Started 0% | float 300.0d CO02YV1110 — 02Y Paint Fabricated Pipe Spools | 05-Feb-27 → 19-Feb-27 | Not Started 0% | float 131.0d CO02EV1110 — 02E Paint Fabricated Pipe Spools | 12-Feb-27 → 04-Mar-27 | Not Started 0% | float 250.0d CO02GV1110 — 02G Paint Fabricated Pipe Spools | 16-Feb-27 → 22-Mar-27 | Not Started 0% | float 230.0d CO02KV1130 — 02K Paint Touch-up - Equipment | 23-Mar-27 → 15-Apr-27 | Not Started 0% | float 236.0d CO02JV1110 — 02J Paint Fabricated Pipe Spools | 27-Mar-27 → 27-Mar-27 | Not Started 0% | float 164.0d CO02AV1130 — 02A Paint Touch-up - Equipment | 30-Mar-27 → 20-Apr-27 | Not Started 0% | float 232.0d CO02MV1110 — 02M Paint Fabricated Pipe Spools | 01-Apr-27 → 14-Apr-27 | Not Started 0% | float 215.0d CO02NV1110 — 02N Paint Fabricated Pipe Spools | 01-Apr-27 → 03-Apr-27 | Not Started 0% | float 216.0d CO02FV1110 — 02F Paint Fabricated Pipe Spools | 09-Apr-27 → 27-Apr-27 | Not Started 0% | float 204.0d CO02LV1110 — 02L Paint Fabricated Pipe Spools | 09-Apr-27 → 29-May-27 | Not Started 0% | float 162.0d CO02LV1110 CO02KV1110 — 02K Paint Fabricated Pipe Spools | 10-Apr-27 → 04-May-27 | Not Started 0% | float 181.0d CO02DV1130 — 02D Paint Touch-up - Equipment | 15-Apr-27 → 29-Apr-27 | Not Started 0% | float 224.0d CO02QV1110 — 02Q Paint Fabricated Pipe Spools | 16-Apr-27 → 20-Apr-27 | Not Started 0% | float 210.0d CO02DV1110 — 02D Paint Fabricated Pipe Spools | 23-Apr-27 → 07-May-27 | Not Started 0% | float 177.0d CO02PV1110 — 02P Paint Fabricated Pipe Spools | 24-Apr-27 → 28-Apr-27 | Not Started 0% | float 199.0d CO02HV1110 — 02H Paint Fabricated Pipe Spools | 26-Apr-27 → 05-Jun-27 | Not Started 0% | float 54.0d CO02HV1110 CO02FV1130 — 02F Paint Touch-up - Equipment | 10-May-27 → 27-May-27 | Not Started 0% | float 200.0d CO02CV1130 — 02C Paint Touch-up - Equipment | 14-May-27 → 22-Jun-27 | Not Started 0% | float 190.0d CO02CV1130 CO02AV1110 — 02A Paint Fabricated Pipe Spools | 20-May-27 → 02-Jun-27 | Not Started 0% | float 172.0d CO02BV1110 — 02B Paint Fabricated Pipe Spools | 25-May-27 → 31-May-27 | Not Started 0% | float 175.0d CO02MV1130 — 02M Paint Touch-up - Equipment | 12-Jun-27 → 29-Jun-27 | Not Started 0% | float 172.0d CO02EV1130 — 02E Paint Touch-up - Equipment | 03-Jul-27 → 23-Jul-27 | Not Started 0% | float 151.0d CO02LV1130 — 02L Paint Touch-up - Equipment | 17-Jul-27 → 28-Sep-27 | Not Started 0% | float 69.0d CO02LV1130 CO02NV1130 — 02N Paint Touch-up - Equipment | 23-Jul-27 → 29-Jul-27 | Not Started 0% | float 146.0d CO02YV1120 — 02Y Paint Touch-up - Piping | 27-Jul-27 → 09-Nov-27 | Not Started 0% | float 101.0d CO02YV1120 CO02YV1130 — 02Y Paint Touch-up - Pipe Rack | 27-Jul-27 → 09-Nov-27 | Not Started 0% | float 101.0d CO02YV1130 CO02GV1130 — 02G Paint Touch-up - Equipment | 30-Jul-27 → 25-Sep-27 | Not Started 0% | float 116.0d CO02GV1130 CO02GV1120 — 02G Paint Touch-up - Piping | 06-Aug-27 → 02-Oct-27 | Not Started 0% | float 134.0d CO02GV1120 CO02BV1120 — 02B Paint Touch-up - Piping | 01-Sep-27 → 20-Sep-27 | Not Started 0% | float 144.0d CO02CV1120 — 02C Paint Touch-up - Piping | 01-Sep-27 → 22-Oct-27 | Not Started 0% | float 116.0d CO02CV1120 CO02JV1120 — 02J Paint Touch-up - Piping | 06-Sep-27 → 11-Oct-27 | Not Started 0% | float 102.0d CO02JV1130 — 02J Paint Touch-up - Equipment | 06-Sep-27 → 11-Oct-27 | Not Started 0% | float 102.0d CO02HV1130 — 02H Paint Touch-up - Equipment | 10-Sep-27 → 28-Oct-27 | Not Started 0% | float 52.0d CO02HV1130 CO02FV1120 — 02F Paint Touch-up - Piping | 23-Sep-27 → 11-Oct-27 | Not Started 0% | float 126.0d CO02PV1130 — 02P Paint Touch-up - Equipment | 29-Sep-27 → 02-Oct-27 | Not Started 0% | float 103.0d CO02PV1120 — 02P Paint Touch-up - Piping | 01-Oct-27 → 05-Oct-27 | Not Started 0% | float 125.0d CO02MV1120 — 02M Paint Touch-up - Piping | 06-Oct-27 → 22-Oct-27 | Not Started 0% | float 116.0d CO02QV1120 — 02Q Paint Touch-up - Piping | 06-Oct-27 → 09-Oct-27 | Not Started 0% | float 121.0d CO02QV1130 — 02Q Paint Touch-up - Equipment | 06-Oct-27 → 09-Oct-27 | Not Started 0% | float 121.0d CO02KV1120 — 02K Paint Touch-up - Piping | 13-Oct-27 → 06-Nov-27 | Not Started 0% | float 104.0d CO02AV1120 — 02A Paint Touch-up - Piping | 16-Oct-27 → 06-Nov-27 | Not Started 0% | float 103.0d CO02EV1120 — 02E Paint Touch-up - Piping | 01-Nov-27 → 26-Nov-27 | Not Started 0% | float 91.0d CO02DV1120 — 02D Paint Touch-up - Piping | 12-Nov-27 → 02-Dec-27 | Not Started 0% | float 86.0d CO02NV1120 — 02N Paint Touch-up - Piping | 18-Nov-27 → 30-Nov-27 | Not Started 0% | float 88.0d CO02HV1120 — 02H Paint Touch-up - Piping | 10-Dec-27 → 19-Jan-28 | Not Started 0% | float 45.0d CO02HV1120 CO02LV1120 — 02L Paint Touch-up - Piping | 25-Dec-27 → 14-Feb-28 | Not Started 0% | float 23.0d CO02LV1120