EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 15
activities
in U4 U/G Piping
× clear
Code
Activity
Start
Finish
Flt
%
CO02AU4120
02A U/G Piping Installation
28-Dec-26
29-Jan-27
222.0d
0%
CO02BU4120
02B U/G Piping Installation
28-Dec-26
29-Jan-27
219.0d
0%
CO02CU4120
02C U/G Piping Installation
28-Dec-26
29-Jan-27
162.0d
0%
CO02DU4120
02D U/G Piping Installation
28-Dec-26
29-Jan-27
248.0d
0%
CO02EU4120
02E U/G Piping Installation
28-Dec-26
29-Jan-27
227.0d
0%
CO02FU4120
02F U/G Piping Installation
28-Dec-26
29-Jan-27
234.0d
0%
CO02HU4120
02H U/G Piping Installation
28-Dec-26
29-Jan-27
162.0d
0%
CO02JU4120
02J U/G Piping Installation
28-Dec-26
29-Jan-27
211.0d
0%
CO02KU4120
02K U/G Piping Installation
28-Dec-26
29-Jan-27
214.0d
0%
CO02MU4120
02M U/G Piping Installation
28-Dec-26
29-Jan-27
239.0d
0%
CO02UP0130
02U LB Pipe Erection (CW & Misc Headers)
28-Dec-26
29-Jan-27
71.0d
0%
WO020U4100
020 U/G Piping Installation
28-Dec-26
26-Feb-27
224.0d
0%
CO02LU4120
02L U/G Piping Installation
02-Jan-27
29-Jan-27
123.0d
0%
CO02GU4120
02G U/G Piping Installation
06-Jan-27
26-Feb-27
159.0d
0%
CO02UP0150
02U LB Pipe Erection (Firewater Piping)
16-Jan-27
06-Feb-27
212.0d
0%