EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 14
activities
in U3 U/G Electrical
× clear
Code
Activity
Start
Finish
Flt
%
CO02YU3110
02Y U/G Earthing Installation
28-Dec-26
29-Jan-27
100.0d
0%
WO020U3100
020 Install U/G Electrical
28-Dec-26
12-Mar-27
265.0d
0%
CO02HU3110
02H U/G Earthing Installation
13-Jan-27
12-Feb-27
162.0d
0%
CO02CU3110
02C U/G Earthing Installation
14-Jan-27
12-Feb-27
168.0d
0%
CO02LU3110
02L U/G Earthing Installation
16-Jan-27
12-Feb-27
129.0d
0%
CO02AU3110
02A U/G Earthing Installation
20-Jan-27
05-Feb-27
228.0d
0%
CO02JU3110
02J U/G Earthing Installation
25-Jan-27
12-Feb-27
211.0d
0%
CO02KU3110
02K U/G Earthing Installation
26-Jan-27
12-Feb-27
214.0d
0%
CO02EU3110
02E U/G Earthing Installation
28-Jan-27
12-Feb-27
227.0d
0%
CO02FU3110
02F U/G Earthing Installation
29-Jan-27
12-Feb-27
234.0d
0%
CO02MU3110
02M U/G Earthing Installation
30-Jan-27
12-Feb-27
239.0d
0%
CO02DU3110
02D U/G Earthing Installation
02-Feb-27
12-Feb-27
248.0d
0%
CO02BU3110
02B U/G Earthing Installation
10-Feb-27
12-Feb-27
289.0d
0%
CO02GU3110
02G U/G Earthing Installation
15-Feb-27
12-Mar-27
159.0d
0%