EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 14 activities in U3 U/G Electrical × clear
Code
Activity
Start
Finish
Flt
%
CO02YU3110
02Y U/G Earthing Installation
28-Dec-26
29-Jan-27
100.0d
0%
WO020U3100
020 Install U/G Electrical
28-Dec-26
12-Mar-27
265.0d
0%
CO02HU3110
02H U/G Earthing Installation
13-Jan-27
12-Feb-27
162.0d
0%
CO02CU3110
02C U/G Earthing Installation
14-Jan-27
12-Feb-27
168.0d
0%
CO02LU3110
02L U/G Earthing Installation
16-Jan-27
12-Feb-27
129.0d
0%
CO02AU3110
02A U/G Earthing Installation
20-Jan-27
05-Feb-27
228.0d
0%
CO02JU3110
02J U/G Earthing Installation
25-Jan-27
12-Feb-27
211.0d
0%
CO02KU3110
02K U/G Earthing Installation
26-Jan-27
12-Feb-27
214.0d
0%
CO02EU3110
02E U/G Earthing Installation
28-Jan-27
12-Feb-27
227.0d
0%
CO02FU3110
02F U/G Earthing Installation
29-Jan-27
12-Feb-27
234.0d
0%
CO02MU3110
02M U/G Earthing Installation
30-Jan-27
12-Feb-27
239.0d
0%
CO02DU3110
02D U/G Earthing Installation
02-Feb-27
12-Feb-27
248.0d
0%
CO02BU3110
02B U/G Earthing Installation
10-Feb-27
12-Feb-27
289.0d
0%
CO02GU3110
02G U/G Earthing Installation
15-Feb-27
12-Mar-27
159.0d
0%
30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar Data Date
CO02YU3110 — 02Y U/G Earthing Installation | 28-Dec-26 → 29-Jan-27 | Not Started 0% | float 100.0d CO02YU3110 WO020U3100 — 020 Install U/G Electrical | 28-Dec-26 → 12-Mar-27 | Not Started 0% | float 265.0d WO020U3100 CO02HU3110 — 02H U/G Earthing Installation | 13-Jan-27 → 12-Feb-27 | Not Started 0% | float 162.0d CO02HU3110 CO02CU3110 — 02C U/G Earthing Installation | 14-Jan-27 → 12-Feb-27 | Not Started 0% | float 168.0d CO02CU3110 CO02LU3110 — 02L U/G Earthing Installation | 16-Jan-27 → 12-Feb-27 | Not Started 0% | float 129.0d CO02LU3110 CO02AU3110 — 02A U/G Earthing Installation | 20-Jan-27 → 05-Feb-27 | Not Started 0% | float 228.0d CO02AU3110 CO02JU3110 — 02J U/G Earthing Installation | 25-Jan-27 → 12-Feb-27 | Not Started 0% | float 211.0d CO02JU3110 CO02KU3110 — 02K U/G Earthing Installation | 26-Jan-27 → 12-Feb-27 | Not Started 0% | float 214.0d CO02KU3110 CO02EU3110 — 02E U/G Earthing Installation | 28-Jan-27 → 12-Feb-27 | Not Started 0% | float 227.0d CO02EU3110 CO02FU3110 — 02F U/G Earthing Installation | 29-Jan-27 → 12-Feb-27 | Not Started 0% | float 234.0d CO02FU3110 CO02MU3110 — 02M U/G Earthing Installation | 30-Jan-27 → 12-Feb-27 | Not Started 0% | float 239.0d CO02MU3110 CO02DU3110 — 02D U/G Earthing Installation | 02-Feb-27 → 12-Feb-27 | Not Started 0% | float 248.0d CO02DU3110 CO02BU3110 — 02B U/G Earthing Installation | 10-Feb-27 → 12-Feb-27 | Not Started 0% | float 289.0d CO02BU3110 CO02GU3110 — 02G U/G Earthing Installation | 15-Feb-27 → 12-Mar-27 | Not Started 0% | float 159.0d CO02GU3110