Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 34 activities in T0 Mechanical Completion × clear
Code
Activity
Start
Finish
Flt
%
CO02UDT110
02U Mechanical Completion
26-Feb-27
26-Feb-27
301.0d
0%
SC02UT0120
02U RFSU
26-Feb-27
26-Feb-27
380.0d
0%
CO02BT0110
02B Mechanical Completion
15-Dec-27
15-Dec-27
75.0d
0%
CO02GT0110
02G Mechanical Completion
16-Dec-27
16-Dec-27
74.0d
0%
SC02BT0120
02B RFSU
18-Dec-27
18-Dec-27
85.0d
0%
CO02AT0110
02A Mechanical Completion
20-Dec-27
20-Dec-27
71.0d
0%
CO02DT0110
02D Mechanical Completion
20-Dec-27
20-Dec-27
71.0d
0%
CO02KT0110
02K Mechanical Completion
22-Dec-27
22-Dec-27
69.0d
0%
CO02NT0110
02N Mechanical Completion
22-Dec-27
22-Dec-27
69.0d
0%
CO02PT0110
02P Mechanical Completion
23-Dec-27
23-Dec-27
68.0d
0%
CO02QT0110
02Q Mechanical Completion
24-Dec-27
24-Dec-27
67.0d
0%
CO02MT0110
02M Mechanical Completion
25-Dec-27
25-Dec-27
66.0d
0%
CO02ET0110
02E Mechanical Completion
27-Dec-27
27-Dec-27
65.0d
0%
CO02JT0110
02J Mechanical Completion
28-Dec-27
28-Dec-27
64.0d
0%
SC02PT0120
02P RFSU
28-Dec-27
28-Dec-27
75.0d
0%
CO02CT0110
02C Mechanical Completion
29-Dec-27
29-Dec-27
63.0d
0%
SC02QT0120
02Q RFSU
29-Dec-27
29-Dec-27
74.0d
0%
CO02FT0110
02F Mechanical Completion
01-Jan-28
01-Jan-28
60.0d
0%
CO02YT0110
02Y Mechanical Completion
03-Jan-28
03-Jan-28
59.0d
0%
SC02DT0120
02D RFSU
04-Jan-28
04-Jan-28
68.0d
0%
SC02NT0120
02N RFSU
06-Jan-28
06-Jan-28
66.0d
0%
SC02GT0120
02G RFSU
09-Jan-28
09-Jan-28
63.0d
0%
SC02YT0120
02Y RFSU
10-Jan-28
10-Jan-28
62.0d
0%
SC02AT0120
02A RFSU
12-Jan-28
12-Jan-28
60.0d
0%
SC02MT0120
02M RFSU
12-Jan-28
12-Jan-28
60.0d
0%
SC02KT0120
02K RFSU
16-Jan-28
16-Jan-28
56.0d
0%
SC02ET0120
02E RFSU
17-Jan-28
17-Jan-28
55.0d
0%
SC02FT0120
02F RFSU
20-Jan-28
20-Jan-28
52.0d
0%
SC02JT0120
02J RFSU
23-Jan-28
23-Jan-28
49.0d
0%
SC02CT0120
02C RFSU
24-Jan-28
24-Jan-28
48.0d
0%
CO02LT0110
02L Mechanical Completion
21-Feb-28
21-Feb-28
17.0d
0%
CO02HT0110
02H Mechanical Completion
23-Feb-28
23-Feb-28
15.0d
0%
SC02HT0120
02H RFSU
29-Feb-28
29-Feb-28
12.0d
0%
SC02LT0120
02L RFSU
29-Mar-28
29-Mar-28
-17.0d
0%
Feb 2027 Mar 2027 Apr 2027 May 2027 Jun 2027 Jul 2027 Aug 2027 Sep 2027 Oct 2027 Nov 2027 Dec 2027 Jan 2028 Feb 2028 Mar 2028 Data Date
CO02UDT110 — 02U Mechanical Completion | 26-Feb-27 | Not Started SC02UT0120 — 02U RFSU | 26-Feb-27 | Not Started CO02BT0110 — 02B Mechanical Completion | 15-Dec-27 | Not Started CO02GT0110 — 02G Mechanical Completion | 16-Dec-27 | Not Started SC02BT0120 — 02B RFSU | 18-Dec-27 | Not Started CO02AT0110 — 02A Mechanical Completion | 20-Dec-27 | Not Started CO02DT0110 — 02D Mechanical Completion | 20-Dec-27 | Not Started CO02KT0110 — 02K Mechanical Completion | 22-Dec-27 | Not Started CO02NT0110 — 02N Mechanical Completion | 22-Dec-27 | Not Started CO02PT0110 — 02P Mechanical Completion | 23-Dec-27 | Not Started CO02QT0110 — 02Q Mechanical Completion | 24-Dec-27 | Not Started CO02MT0110 — 02M Mechanical Completion | 25-Dec-27 | Not Started CO02ET0110 — 02E Mechanical Completion | 27-Dec-27 | Not Started CO02JT0110 — 02J Mechanical Completion | 28-Dec-27 | Not Started SC02PT0120 — 02P RFSU | 28-Dec-27 | Not Started CO02CT0110 — 02C Mechanical Completion | 29-Dec-27 | Not Started SC02QT0120 — 02Q RFSU | 29-Dec-27 | Not Started CO02FT0110 — 02F Mechanical Completion | 01-Jan-28 | Not Started CO02YT0110 — 02Y Mechanical Completion | 03-Jan-28 | Not Started SC02DT0120 — 02D RFSU | 04-Jan-28 | Not Started SC02NT0120 — 02N RFSU | 06-Jan-28 | Not Started SC02GT0120 — 02G RFSU | 09-Jan-28 | Not Started SC02YT0120 — 02Y RFSU | 10-Jan-28 | Not Started SC02AT0120 — 02A RFSU | 12-Jan-28 | Not Started SC02MT0120 — 02M RFSU | 12-Jan-28 | Not Started SC02KT0120 — 02K RFSU | 16-Jan-28 | Not Started SC02ET0120 — 02E RFSU | 17-Jan-28 | Not Started SC02FT0120 — 02F RFSU | 20-Jan-28 | Not Started SC02JT0120 — 02J RFSU | 23-Jan-28 | Not Started SC02CT0120 — 02C RFSU | 24-Jan-28 | Not Started CO02LT0110 — 02L Mechanical Completion | 21-Feb-28 | Not Started CO02HT0110 — 02H Mechanical Completion | 23-Feb-28 | Not Started SC02HT0120 — 02H RFSU | 29-Feb-28 | Not Started SC02LT0120 — 02L RFSU | 29-Mar-28 | Not Started