EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in K1 Perimeter Wall × clear
Code
Activity
Start
Finish
Flt
%
CO000C0150
Perimeter Wall
15-Dec-25
29-Mar-27
27.0d
28%
WO010K0110
010 Site Prep - Perimeter Wall
15-Dec-25
29-Mar-27
27.0d
28%
01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan 01-Feb 08-Feb 15-Feb 22-Feb 01-Mar 08-Mar 15-Mar 22-Mar 29-Mar Data Date
CO000C0150 — Perimeter Wall | 15-Dec-25 → 29-Mar-27 | In Progress 28% | float 27.0d CO000C0150 WO010K0110 — 010 Site Prep - Perimeter Wall | 15-Dec-25 → 29-Mar-27 | In Progress 28% | float 27.0d WO010K0110