EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in K1 Perimeter Wall × clear
Code
Activity
Start
Finish
Flt
%
CO000C0150
Perimeter Wall
15-Dec-25
29-Mar-27
27.0d
28%
WO010K0110
010 Site Prep - Perimeter Wall
15-Dec-25
29-Mar-27
27.0d
28%
Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Jan 2027 Feb 2027 Mar 2027 Data Date
CO000C0150 — Perimeter Wall | 15-Dec-25 → 29-Mar-27 | In Progress 28% | float 27.0d CO000C0150 WO010K0110 — 010 Site Prep - Perimeter Wall | 15-Dec-25 → 29-Mar-27 | In Progress 28% | float 27.0d WO010K0110