Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in C1 Concrete Paving × clear
Code
Activity
Start
Finish
Flt
%
CO01YC0130
01Y Install Paving
08-Feb-27
27-Feb-27
134.0d
0%
WO010C0110
010 Concrete Paving
08-Feb-27
08-Jul-27
188.0d
0%
CO01EC0135
01E Install Paving - Guard House
04-Mar-27
17-Mar-27
285.0d
0%
CO01CC0130
01C Install Paving
29-Mar-27
10-Apr-27
160.0d
0%
CO01FC0135
01F Install Paving - Mosque
29-Apr-27
19-May-27
203.0d
0%
CO01DC0130
01D Install Paving
05-May-27
18-May-27
72.0d
0%
CO01GC0130
01G Install Paving - Control Building
25-Jun-27
08-Jul-27
70.0d
0%
Q1 2027 Q2 2027 Q3 2027 Data Date
CO01YC0130 — 01Y Install Paving | 08-Feb-27 → 27-Feb-27 | Not Started 0% | float 134.0d WO010C0110 — 010 Concrete Paving | 08-Feb-27 → 08-Jul-27 | Not Started 0% | float 188.0d WO010C0110 CO01EC0135 — 01E Install Paving - Guard House | 04-Mar-27 → 17-Mar-27 | Not Started 0% | float 285.0d CO01CC0130 — 01C Install Paving | 29-Mar-27 → 10-Apr-27 | Not Started 0% | float 160.0d CO01FC0135 — 01F Install Paving - Mosque | 29-Apr-27 → 19-May-27 | Not Started 0% | float 203.0d CO01DC0130 — 01D Install Paving | 05-May-27 → 18-May-27 | Not Started 0% | float 72.0d CO01GC0130 — 01G Install Paving - Control Building | 25-Jun-27 → 08-Jul-27 | Not Started 0% | float 70.0d