EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 7
activities
in C1 Concrete Paving
× clear
Code
Activity
Start
Finish
Flt
%
CO01YC0130
01Y Install Paving
08-Feb-27
27-Feb-27
134.0d
0%
WO010C0110
010 Concrete Paving
08-Feb-27
08-Jul-27
188.0d
0%
CO01EC0135
01E Install Paving - Guard House
04-Mar-27
17-Mar-27
285.0d
0%
CO01CC0130
01C Install Paving
29-Mar-27
10-Apr-27
160.0d
0%
CO01FC0135
01F Install Paving - Mosque
29-Apr-27
19-May-27
203.0d
0%
CO01DC0130
01D Install Paving
05-May-27
18-May-27
72.0d
0%
CO01GC0130
01G Install Paving - Control Building
25-Jun-27
08-Jul-27
70.0d
0%