EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 6
activities
in A0 Buildings
× clear
Code
Activity
Start
Finish
Flt
%
CO01GA0110
01G Erect Control Building (Continuation w/ Design Rev)
28-Dec-26
24-Jun-27
-14.0d
0%
WO010A0100
010 Buildings
28-Dec-26
24-Jun-27
94.0d
0%
CO01EA0130
01E Erect Guard House
04-Feb-27
03-Mar-27
191.0d
0%
CO01FA0130
01F Erect Mosque
04-Feb-27
28-Apr-27
143.0d
0%
CO01HA0110
01H Set 2610-K Electrical Power House
12-Apr-27
03-May-27
76.0d
0%
CO01CA0110
01C Erect - EDR Shelter
31-May-27
21-Jun-27
98.0d
0%