EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 6 activities in A0 Buildings × clear
Code
Activity
Start
Finish
Flt
%
CO01GA0110
01G Erect Control Building (Continuation w/ Design Rev)
28-Dec-26
24-Jun-27
-14.0d
0%
WO010A0100
010 Buildings
28-Dec-26
24-Jun-27
94.0d
0%
CO01EA0130
01E Erect Guard House
04-Feb-27
03-Mar-27
191.0d
0%
CO01FA0130
01F Erect Mosque
04-Feb-27
28-Apr-27
143.0d
0%
CO01HA0110
01H Set 2610-K Electrical Power House
12-Apr-27
03-May-27
76.0d
0%
CO01CA0110
01C Erect - EDR Shelter
31-May-27
21-Jun-27
98.0d
0%
Q4 2026 Q1 2027 Q2 2027 Data Date
CO01GA0110 — 01G Erect Control Building (Continuation w/ Design Rev) | 28-Dec-26 → 24-Jun-27 | Not Started 0% | float -14.0d CO01GA0110 WO010A0100 — 010 Buildings | 28-Dec-26 → 24-Jun-27 | Not Started 0% | float 94.0d WO010A0100 CO01EA0130 — 01E Erect Guard House | 04-Feb-27 → 03-Mar-27 | Not Started 0% | float 191.0d CO01FA0130 — 01F Erect Mosque | 04-Feb-27 → 28-Apr-27 | Not Started 0% | float 143.0d CO01FA0130 CO01HA0110 — 01H Set 2610-K Electrical Power House | 12-Apr-27 → 03-May-27 | Not Started 0% | float 76.0d CO01CA0110 — 01C Erect - EDR Shelter | 31-May-27 → 21-Jun-27 | Not Started 0% | float 98.0d