Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 8 activities in V2 Insulation × clear
Code
Activity
Start
Finish
Flt
%
CO01BV2110
01B Insulate - Equipment
01-Jul-27
23-Jul-27
100.0d
0%
WO010V2100
010 Insulation
01-Jul-27
02-Nov-27
107.0d
0%
CO01DV2110
01D Insulate - Equipment
06-Jul-27
23-Jul-27
88.0d
0%
CO01CV2120
01C Insulate - Piping
08-Jul-27
29-Jul-27
96.0d
0%
CO01CV2110
01C Insulate - Equipment
12-Jul-27
02-Aug-27
93.0d
0%
CO01YV2120
01Y Insulate - Piping
31-Jul-27
02-Oct-27
133.0d
0%
CO01DV2120
01D Insulate - Piping
23-Sep-27
16-Oct-27
34.0d
0%
CO01BV2120
01B Insulate - Piping
02-Oct-27
02-Nov-27
32.0d
0%
28-Jun 05-Jul 12-Jul 19-Jul 26-Jul 02-Aug 09-Aug 16-Aug 23-Aug 30-Aug 06-Sep 13-Sep 20-Sep 27-Sep 04-Oct 11-Oct 18-Oct 25-Oct 01-Nov 08-Nov 15-Nov 22-Nov 29-Nov Data Date
CO01BV2110 — 01B Insulate - Equipment | 01-Jul-27 → 23-Jul-27 | Not Started 0% | float 100.0d CO01BV2110 WO010V2100 — 010 Insulation | 01-Jul-27 → 02-Nov-27 | Not Started 0% | float 107.0d WO010V2100 CO01DV2110 — 01D Insulate - Equipment | 06-Jul-27 → 23-Jul-27 | Not Started 0% | float 88.0d CO01DV2110 CO01CV2120 — 01C Insulate - Piping | 08-Jul-27 → 29-Jul-27 | Not Started 0% | float 96.0d CO01CV2120 CO01CV2110 — 01C Insulate - Equipment | 12-Jul-27 → 02-Aug-27 | Not Started 0% | float 93.0d CO01CV2110 CO01YV2120 — 01Y Insulate - Piping | 31-Jul-27 → 02-Oct-27 | Not Started 0% | float 133.0d CO01YV2120 CO01DV2120 — 01D Insulate - Piping | 23-Sep-27 → 16-Oct-27 | Not Started 0% | float 34.0d CO01DV2120 CO01BV2120 — 01B Insulate - Piping | 02-Oct-27 → 02-Nov-27 | Not Started 0% | float 32.0d CO01BV2120