EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 8 activities in V2 Insulation × clear
Code
Activity
Start
Finish
Flt
%
CO01BV2110
01B Insulate - Equipment
01-Jul-27
23-Jul-27
100.0d
0%
WO010V2100
010 Insulation
01-Jul-27
02-Nov-27
107.0d
0%
CO01DV2110
01D Insulate - Equipment
06-Jul-27
23-Jul-27
88.0d
0%
CO01CV2120
01C Insulate - Piping
08-Jul-27
29-Jul-27
96.0d
0%
CO01CV2110
01C Insulate - Equipment
12-Jul-27
02-Aug-27
93.0d
0%
CO01YV2120
01Y Insulate - Piping
31-Jul-27
02-Oct-27
133.0d
0%
CO01DV2120
01D Insulate - Piping
23-Sep-27
16-Oct-27
34.0d
0%
CO01BV2120
01B Insulate - Piping
02-Oct-27
02-Nov-27
32.0d
0%
28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov Data Date
CO01BV2110 — 01B Insulate - Equipment | 01-Jul-27 → 23-Jul-27 | Not Started 0% | float 100.0d CO01BV2110 WO010V2100 — 010 Insulation | 01-Jul-27 → 02-Nov-27 | Not Started 0% | float 107.0d WO010V2100 CO01DV2110 — 01D Insulate - Equipment | 06-Jul-27 → 23-Jul-27 | Not Started 0% | float 88.0d CO01DV2110 CO01CV2120 — 01C Insulate - Piping | 08-Jul-27 → 29-Jul-27 | Not Started 0% | float 96.0d CO01CV2120 CO01CV2110 — 01C Insulate - Equipment | 12-Jul-27 → 02-Aug-27 | Not Started 0% | float 93.0d CO01CV2110 CO01YV2120 — 01Y Insulate - Piping | 31-Jul-27 → 02-Oct-27 | Not Started 0% | float 133.0d CO01YV2120 CO01DV2120 — 01D Insulate - Piping | 23-Sep-27 → 16-Oct-27 | Not Started 0% | float 34.0d CO01DV2120 CO01BV2120 — 01B Insulate - Piping | 02-Oct-27 → 02-Nov-27 | Not Started 0% | float 32.0d CO01BV2120