EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 8
activities
in V2 Insulation
× clear
Code
Activity
Start
Finish
Flt
%
CO01BV2110
01B Insulate - Equipment
01-Jul-27
23-Jul-27
100.0d
0%
WO010V2100
010 Insulation
01-Jul-27
02-Nov-27
107.0d
0%
CO01DV2110
01D Insulate - Equipment
06-Jul-27
23-Jul-27
88.0d
0%
CO01CV2120
01C Insulate - Piping
08-Jul-27
29-Jul-27
96.0d
0%
CO01CV2110
01C Insulate - Equipment
12-Jul-27
02-Aug-27
93.0d
0%
CO01YV2120
01Y Insulate - Piping
31-Jul-27
02-Oct-27
133.0d
0%
CO01DV2120
01D Insulate - Piping
23-Sep-27
16-Oct-27
34.0d
0%
CO01BV2120
01B Insulate - Piping
02-Oct-27
02-Nov-27
32.0d
0%