EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 14 activities in V1 Painting × clear
Code
Activity
Start
Finish
Flt
%
CO01AV1110
01A Paint Fabricated Pipe Spools
31-Dec-26
02-Jan-27
253.0d
0%
WO010V1100
010 Paint
31-Dec-26
05-Oct-27
131.0d
0%
CO01YV1110
01Y Paint Fabricated Pipe Spools
28-Jan-27
05-Feb-27
149.0d
0%
CO01CV1110
01C Paint Fabricated Pipe Spools
06-Mar-27
13-Mar-27
174.0d
0%
CO01BV1110
01B Paint Fabricated Pipe Spools
08-Mar-27
30-Mar-27
153.0d
0%
CO01DV1110
01D Paint Fabricated Pipe Spools
11-Mar-27
29-Mar-27
142.0d
0%
CO01BV1130
01B Paint Touch-up - Equipment
03-Jun-27
25-Jun-27
100.0d
0%
CO01DV1130
01D Paint Touch-up - Equipment
08-Jun-27
25-Jun-27
88.0d
0%
CO01YV1120
01Y Paint Touch-up - Piping
19-Jun-27
30-Jul-27
169.0d
0%
CO01CV1120
01C Paint Touch-up - Piping
21-Jun-27
12-Jul-27
93.0d
0%
CO01CV1130
01C Paint Touch-up - Equipment
21-Jun-27
12-Jul-27
93.0d
0%
CO01DV1120
01D Paint Touch-up - Piping
10-Aug-27
10-Sep-27
45.0d
0%
CO01BV1120
01B Paint Touch-up - Piping
30-Aug-27
05-Oct-27
56.0d
0%
CO01AV1120
01A Paint Touch-up - Piping
29-Sep-27
01-Oct-27
58.0d
0%
30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan 01-Feb 08-Feb 15-Feb 22-Feb 01-Mar 08-Mar 15-Mar 22-Mar 29-Mar 05-Apr 12-Apr 19-Apr 26-Apr 03-May 10-May 17-May 24-May 31-May 07-Jun 14-Jun 21-Jun 28-Jun 05-Jul 12-Jul 19-Jul 26-Jul 02-Aug 09-Aug 16-Aug 23-Aug 30-Aug 06-Sep 13-Sep 20-Sep 27-Sep 04-Oct 11-Oct 18-Oct 25-Oct Data Date
CO01AV1110 — 01A Paint Fabricated Pipe Spools | 31-Dec-26 → 02-Jan-27 | Not Started 0% | float 253.0d CO01AV1110 WO010V1100 — 010 Paint | 31-Dec-26 → 05-Oct-27 | Not Started 0% | float 131.0d WO010V1100 CO01YV1110 — 01Y Paint Fabricated Pipe Spools | 28-Jan-27 → 05-Feb-27 | Not Started 0% | float 149.0d CO01YV1110 CO01CV1110 — 01C Paint Fabricated Pipe Spools | 06-Mar-27 → 13-Mar-27 | Not Started 0% | float 174.0d CO01CV1110 CO01BV1110 — 01B Paint Fabricated Pipe Spools | 08-Mar-27 → 30-Mar-27 | Not Started 0% | float 153.0d CO01BV1110 CO01DV1110 — 01D Paint Fabricated Pipe Spools | 11-Mar-27 → 29-Mar-27 | Not Started 0% | float 142.0d CO01DV1110 CO01BV1130 — 01B Paint Touch-up - Equipment | 03-Jun-27 → 25-Jun-27 | Not Started 0% | float 100.0d CO01BV1130 CO01DV1130 — 01D Paint Touch-up - Equipment | 08-Jun-27 → 25-Jun-27 | Not Started 0% | float 88.0d CO01DV1130 CO01YV1120 — 01Y Paint Touch-up - Piping | 19-Jun-27 → 30-Jul-27 | Not Started 0% | float 169.0d CO01YV1120 CO01CV1120 — 01C Paint Touch-up - Piping | 21-Jun-27 → 12-Jul-27 | Not Started 0% | float 93.0d CO01CV1120 CO01CV1130 — 01C Paint Touch-up - Equipment | 21-Jun-27 → 12-Jul-27 | Not Started 0% | float 93.0d CO01CV1130 CO01DV1120 — 01D Paint Touch-up - Piping | 10-Aug-27 → 10-Sep-27 | Not Started 0% | float 45.0d CO01DV1120 CO01BV1120 — 01B Paint Touch-up - Piping | 30-Aug-27 → 05-Oct-27 | Not Started 0% | float 56.0d CO01BV1120 CO01AV1120 — 01A Paint Touch-up - Piping | 29-Sep-27 → 01-Oct-27 | Not Started 0% | float 58.0d CO01AV1120