EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 14
activities
in V1 Painting
× clear
Code
Activity
Start
Finish
Flt
%
CO01AV1110
01A Paint Fabricated Pipe Spools
31-Dec-26
02-Jan-27
253.0d
0%
WO010V1100
010 Paint
31-Dec-26
05-Oct-27
131.0d
0%
CO01YV1110
01Y Paint Fabricated Pipe Spools
28-Jan-27
05-Feb-27
149.0d
0%
CO01CV1110
01C Paint Fabricated Pipe Spools
06-Mar-27
13-Mar-27
174.0d
0%
CO01BV1110
01B Paint Fabricated Pipe Spools
08-Mar-27
30-Mar-27
153.0d
0%
CO01DV1110
01D Paint Fabricated Pipe Spools
11-Mar-27
29-Mar-27
142.0d
0%
CO01BV1130
01B Paint Touch-up - Equipment
03-Jun-27
25-Jun-27
100.0d
0%
CO01DV1130
01D Paint Touch-up - Equipment
08-Jun-27
25-Jun-27
88.0d
0%
CO01YV1120
01Y Paint Touch-up - Piping
19-Jun-27
30-Jul-27
169.0d
0%
CO01CV1120
01C Paint Touch-up - Piping
21-Jun-27
12-Jul-27
93.0d
0%
CO01CV1130
01C Paint Touch-up - Equipment
21-Jun-27
12-Jul-27
93.0d
0%
CO01DV1120
01D Paint Touch-up - Piping
10-Aug-27
10-Sep-27
45.0d
0%
CO01BV1120
01B Paint Touch-up - Piping
30-Aug-27
05-Oct-27
56.0d
0%
CO01AV1120
01A Paint Touch-up - Piping
29-Sep-27
01-Oct-27
58.0d
0%