EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in U4 U/G Piping × clear
Code
Activity
Start
Finish
Flt
%
CO01UP0150
01U LB Pipe Erection (Firewater Piping)
05-Jan-27
06-Feb-27
212.0d
0%
WO010U4100
010 U/G Piping Installation
05-Jan-27
26-Mar-27
171.0d
0%
CO01JP0230
01J U/G Pipe Erection - Piping to Corridor
29-Jan-27
26-Feb-27
160.0d
0%
CO01BU4120
01B U/G Piping Installation
30-Jan-27
10-Mar-27
173.0d
0%
CO01DU4120
01D U/G Piping Installation
30-Jan-27
02-Mar-27
49.0d
0%
CO01EU4130
01E/F/G U/G Piping Installation (to Bldg Stub Outs)
30-Jan-27
26-Mar-27
147.0d
0%
CO01CU4120
01C U/G Piping Installation
22-Feb-27
06-Mar-27
160.0d
0%
Jan 2027 Feb 2027 Mar 2027 Data Date
CO01UP0150 — 01U LB Pipe Erection (Firewater Piping) | 05-Jan-27 → 06-Feb-27 | Not Started 0% | float 212.0d CO01UP0150 WO010U4100 — 010 U/G Piping Installation | 05-Jan-27 → 26-Mar-27 | Not Started 0% | float 171.0d WO010U4100 CO01JP0230 — 01J U/G Pipe Erection - Piping to Corridor | 29-Jan-27 → 26-Feb-27 | Not Started 0% | float 160.0d CO01JP0230 CO01BU4120 — 01B U/G Piping Installation | 30-Jan-27 → 10-Mar-27 | Not Started 0% | float 173.0d CO01BU4120 CO01DU4120 — 01D U/G Piping Installation | 30-Jan-27 → 02-Mar-27 | Not Started 0% | float 49.0d CO01DU4120 CO01EU4130 — 01E/F/G U/G Piping Installation (to Bldg Stub Outs) | 30-Jan-27 → 26-Mar-27 | Not Started 0% | float 147.0d CO01EU4130 CO01CU4120 — 01C U/G Piping Installation | 22-Feb-27 → 06-Mar-27 | Not Started 0% | float 160.0d CO01CU4120