Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in U4 U/G Piping × clear
Code
Activity
Start
Finish
Flt
%
CO01UP0150
01U LB Pipe Erection (Firewater Piping)
05-Jan-27
06-Feb-27
212.0d
0%
WO010U4100
010 U/G Piping Installation
05-Jan-27
26-Mar-27
171.0d
0%
CO01JP0230
01J U/G Pipe Erection - Piping to Corridor
29-Jan-27
26-Feb-27
160.0d
0%
CO01BU4120
01B U/G Piping Installation
30-Jan-27
10-Mar-27
173.0d
0%
CO01DU4120
01D U/G Piping Installation
30-Jan-27
02-Mar-27
49.0d
0%
CO01EU4130
01E/F/G U/G Piping Installation (to Bldg Stub Outs)
30-Jan-27
26-Mar-27
147.0d
0%
CO01CU4120
01C U/G Piping Installation
22-Feb-27
06-Mar-27
160.0d
0%
28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar Data Date
CO01UP0150 — 01U LB Pipe Erection (Firewater Piping) | 05-Jan-27 → 06-Feb-27 | Not Started 0% | float 212.0d CO01UP0150 WO010U4100 — 010 U/G Piping Installation | 05-Jan-27 → 26-Mar-27 | Not Started 0% | float 171.0d WO010U4100 CO01JP0230 — 01J U/G Pipe Erection - Piping to Corridor | 29-Jan-27 → 26-Feb-27 | Not Started 0% | float 160.0d CO01JP0230 CO01BU4120 — 01B U/G Piping Installation | 30-Jan-27 → 10-Mar-27 | Not Started 0% | float 173.0d CO01BU4120 CO01DU4120 — 01D U/G Piping Installation | 30-Jan-27 → 02-Mar-27 | Not Started 0% | float 49.0d CO01DU4120 CO01EU4130 — 01E/F/G U/G Piping Installation (to Bldg Stub Outs) | 30-Jan-27 → 26-Mar-27 | Not Started 0% | float 147.0d CO01EU4130 CO01CU4120 — 01C U/G Piping Installation | 22-Feb-27 → 06-Mar-27 | Not Started 0% | float 160.0d CO01CU4120