EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 7
activities
in U4 U/G Piping
× clear
Code
Activity
Start
Finish
Flt
%
CO01UP0150
01U LB Pipe Erection (Firewater Piping)
05-Jan-27
06-Feb-27
212.0d
0%
WO010U4100
010 U/G Piping Installation
05-Jan-27
26-Mar-27
171.0d
0%
CO01JP0230
01J U/G Pipe Erection - Piping to Corridor
29-Jan-27
26-Feb-27
160.0d
0%
CO01BU4120
01B U/G Piping Installation
30-Jan-27
10-Mar-27
173.0d
0%
CO01DU4120
01D U/G Piping Installation
30-Jan-27
02-Mar-27
49.0d
0%
CO01EU4130
01E/F/G U/G Piping Installation (to Bldg Stub Outs)
30-Jan-27
26-Mar-27
147.0d
0%
CO01CU4120
01C U/G Piping Installation
22-Feb-27
06-Mar-27
160.0d
0%