EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 7
activities
in U3 U/G Electrical
× clear
Code
Activity
Start
Finish
Flt
%
CO01YU3110
01Y U/G Earthing Installation - Pipe Rack
28-Dec-26
06-Feb-27
134.0d
0%
WO010U3100
010 Install U/G Electrical
28-Dec-26
27-Mar-27
170.0d
0%
CO01HU3110
01H U/G Earthing Installation
25-Jan-27
06-Feb-27
134.0d
0%
CO01DU3110
01D U/G Earthing Installation
03-Mar-27
17-Mar-27
113.0d
0%
CO01BU3110
01B U/G Earthing Installation
05-Mar-27
24-Mar-27
173.0d
0%
CO01CU3110
01C U/G Earthing Installation
15-Mar-27
20-Mar-27
166.0d
0%
CO01GU3110
01G U/G Earthing Installation
15-Mar-27
27-Mar-27
146.0d
0%