Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in U3 U/G Electrical × clear
Code
Activity
Start
Finish
Flt
%
CO01YU3110
01Y U/G Earthing Installation - Pipe Rack
28-Dec-26
06-Feb-27
134.0d
0%
WO010U3100
010 Install U/G Electrical
28-Dec-26
27-Mar-27
170.0d
0%
CO01HU3110
01H U/G Earthing Installation
25-Jan-27
06-Feb-27
134.0d
0%
CO01DU3110
01D U/G Earthing Installation
03-Mar-27
17-Mar-27
113.0d
0%
CO01BU3110
01B U/G Earthing Installation
05-Mar-27
24-Mar-27
173.0d
0%
CO01CU3110
01C U/G Earthing Installation
15-Mar-27
20-Mar-27
166.0d
0%
CO01GU3110
01G U/G Earthing Installation
15-Mar-27
27-Mar-27
146.0d
0%
Q4 2026 Q1 2027 Data Date
CO01YU3110 — 01Y U/G Earthing Installation - Pipe Rack | 28-Dec-26 → 06-Feb-27 | Not Started 0% | float 134.0d CO01YU3110 WO010U3100 — 010 Install U/G Electrical | 28-Dec-26 → 27-Mar-27 | Not Started 0% | float 170.0d WO010U3100 CO01HU3110 — 01H U/G Earthing Installation | 25-Jan-27 → 06-Feb-27 | Not Started 0% | float 134.0d CO01DU3110 — 01D U/G Earthing Installation | 03-Mar-27 → 17-Mar-27 | Not Started 0% | float 113.0d CO01BU3110 — 01B U/G Earthing Installation | 05-Mar-27 → 24-Mar-27 | Not Started 0% | float 173.0d CO01CU3110 — 01C U/G Earthing Installation | 15-Mar-27 → 20-Mar-27 | Not Started 0% | float 166.0d CO01GU3110 — 01G U/G Earthing Installation | 15-Mar-27 → 27-Mar-27 | Not Started 0% | float 146.0d