Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in U3 U/G Electrical × clear
Code
Activity
Start
Finish
Flt
%
CO01YU3110
01Y U/G Earthing Installation - Pipe Rack
28-Dec-26
06-Feb-27
134.0d
0%
WO010U3100
010 Install U/G Electrical
28-Dec-26
27-Mar-27
170.0d
0%
CO01HU3110
01H U/G Earthing Installation
25-Jan-27
06-Feb-27
134.0d
0%
CO01DU3110
01D U/G Earthing Installation
03-Mar-27
17-Mar-27
113.0d
0%
CO01BU3110
01B U/G Earthing Installation
05-Mar-27
24-Mar-27
173.0d
0%
CO01CU3110
01C U/G Earthing Installation
15-Mar-27
20-Mar-27
166.0d
0%
CO01GU3110
01G U/G Earthing Installation
15-Mar-27
27-Mar-27
146.0d
0%
30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar Data Date
CO01YU3110 — 01Y U/G Earthing Installation - Pipe Rack | 28-Dec-26 → 06-Feb-27 | Not Started 0% | float 134.0d CO01YU3110 WO010U3100 — 010 Install U/G Electrical | 28-Dec-26 → 27-Mar-27 | Not Started 0% | float 170.0d WO010U3100 CO01HU3110 — 01H U/G Earthing Installation | 25-Jan-27 → 06-Feb-27 | Not Started 0% | float 134.0d CO01HU3110 CO01DU3110 — 01D U/G Earthing Installation | 03-Mar-27 → 17-Mar-27 | Not Started 0% | float 113.0d CO01DU3110 CO01BU3110 — 01B U/G Earthing Installation | 05-Mar-27 → 24-Mar-27 | Not Started 0% | float 173.0d CO01BU3110 CO01CU3110 — 01C U/G Earthing Installation | 15-Mar-27 → 20-Mar-27 | Not Started 0% | float 166.0d CO01CU3110 CO01GU3110 — 01G U/G Earthing Installation | 15-Mar-27 → 27-Mar-27 | Not Started 0% | float 146.0d CO01GU3110