Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 21 activities in T0 Mechanical Completion × clear
Code
Activity
Start
Finish
Flt
%
SC01JT0120
01J RFSU
28-Dec-26
28-Dec-26
441.0d
0%
CO01UDT110
01U Mechanical Completion
26-Mar-27
26-Mar-27
277.0d
0%
SC01UT0120
01U RFSU
26-Mar-27
26-Mar-27
352.0d
0%
CO01ET0110
01E Mechanical Completion
17-Jul-27
17-Jul-27
180.0d
0%
CO01FT0110
01F Mechanical Completion
17-Jul-27
17-Jul-27
152.0d
0%
SC01ET0120
01E RFSU
17-Jul-27
17-Jul-27
239.0d
0%
SC01FT0120
01F RFSU
17-Jul-27
17-Jul-27
239.0d
0%
CO01HT0110
01H Mechanical Completion
10-Sep-27
10-Sep-27
33.0d
0%
SC01HT0120
01H RFSU
17-Oct-27
17-Oct-27
10.0d
0%
CO01GT0110
01G Mechanical Completion
06-Dec-27
06-Dec-27
-35.0d
0%
SC01GT0120
01G RFSU
06-Dec-27
06-Dec-27
-47.0d
0%
CO01DT0110
01D Mechanical Completion
11-Dec-27
11-Dec-27
-22.0d
0%
CO01CT0110
01C Mechanical Completion
23-Dec-27
23-Dec-27
-7.0d
0%
CO01AT0110
01A Mechanical Completion
28-Dec-27
28-Dec-27
-12.0d
0%
CO01BT0110
01B Mechanical Completion
28-Dec-27
28-Dec-27
-11.0d
0%
SC01AT0120
01A RFSU
29-Dec-27
29-Dec-27
-14.0d
0%
SC01CT0120
01C RFSU
29-Dec-27
29-Dec-27
-14.0d
0%
SC01DT0120
01D RFSU
29-Dec-27
29-Dec-27
-28.0d
0%
CO01YT0110
01Y Mechanical Completion
03-Jan-28
03-Jan-28
59.0d
0%
SC01YT0120
01Y RFSU
10-Jan-28
10-Jan-28
62.0d
0%
SC01BT0120
01B RFSU
19-Jan-28
19-Jan-28
-35.0d
0%
Dec 2026 Jan 2027 Feb 2027 Mar 2027 Apr 2027 May 2027 Jun 2027 Jul 2027 Aug 2027 Sep 2027 Oct 2027 Nov 2027 Dec 2027 Jan 2028 Data Date
SC01JT0120 — 01J RFSU | 28-Dec-26 | Not Started CO01UDT110 — 01U Mechanical Completion | 26-Mar-27 | Not Started SC01UT0120 — 01U RFSU | 26-Mar-27 | Not Started CO01ET0110 — 01E Mechanical Completion | 17-Jul-27 | Not Started CO01FT0110 — 01F Mechanical Completion | 17-Jul-27 | Not Started SC01ET0120 — 01E RFSU | 17-Jul-27 | Not Started SC01FT0120 — 01F RFSU | 17-Jul-27 | Not Started CO01HT0110 — 01H Mechanical Completion | 10-Sep-27 | Not Started SC01HT0120 — 01H RFSU | 17-Oct-27 | Not Started CO01GT0110 — 01G Mechanical Completion | 06-Dec-27 | Not Started SC01GT0120 — 01G RFSU | 06-Dec-27 | Not Started CO01DT0110 — 01D Mechanical Completion | 11-Dec-27 | Not Started CO01CT0110 — 01C Mechanical Completion | 23-Dec-27 | Not Started CO01AT0110 — 01A Mechanical Completion | 28-Dec-27 | Not Started CO01BT0110 — 01B Mechanical Completion | 28-Dec-27 | Not Started SC01AT0120 — 01A RFSU | 29-Dec-27 | Not Started SC01CT0120 — 01C RFSU | 29-Dec-27 | Not Started SC01DT0120 — 01D RFSU | 29-Dec-27 | Not Started CO01YT0110 — 01Y Mechanical Completion | 03-Jan-28 | Not Started SC01YT0120 — 01Y RFSU | 10-Jan-28 | Not Started SC01BT0120 — 01B RFSU | 19-Jan-28 | Not Started