EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 21
activities
in T0 Mechanical Completion
× clear
Code
Activity
Start
Finish
Flt
%
SC01JT0120
01J RFSU
28-Dec-26
28-Dec-26
441.0d
0%
CO01UDT110
01U Mechanical Completion
26-Mar-27
26-Mar-27
277.0d
0%
SC01UT0120
01U RFSU
26-Mar-27
26-Mar-27
352.0d
0%
CO01ET0110
01E Mechanical Completion
17-Jul-27
17-Jul-27
180.0d
0%
CO01FT0110
01F Mechanical Completion
17-Jul-27
17-Jul-27
152.0d
0%
SC01ET0120
01E RFSU
17-Jul-27
17-Jul-27
239.0d
0%
SC01FT0120
01F RFSU
17-Jul-27
17-Jul-27
239.0d
0%
CO01HT0110
01H Mechanical Completion
10-Sep-27
10-Sep-27
33.0d
0%
SC01HT0120
01H RFSU
17-Oct-27
17-Oct-27
10.0d
0%
CO01GT0110
01G Mechanical Completion
06-Dec-27
06-Dec-27
-35.0d
0%
SC01GT0120
01G RFSU
06-Dec-27
06-Dec-27
-47.0d
0%
CO01DT0110
01D Mechanical Completion
11-Dec-27
11-Dec-27
-22.0d
0%
CO01CT0110
01C Mechanical Completion
23-Dec-27
23-Dec-27
-7.0d
0%
CO01AT0110
01A Mechanical Completion
28-Dec-27
28-Dec-27
-12.0d
0%
CO01BT0110
01B Mechanical Completion
28-Dec-27
28-Dec-27
-11.0d
0%
SC01AT0120
01A RFSU
29-Dec-27
29-Dec-27
-14.0d
0%
SC01CT0120
01C RFSU
29-Dec-27
29-Dec-27
-14.0d
0%
SC01DT0120
01D RFSU
29-Dec-27
29-Dec-27
-28.0d
0%
CO01YT0110
01Y Mechanical Completion
03-Jan-28
03-Jan-28
59.0d
0%
SC01YT0120
01Y RFSU
10-Jan-28
10-Jan-28
62.0d
0%
SC01BT0120
01B RFSU
19-Jan-28
19-Jan-28
-35.0d
0%